HARRIS SS0330 (6433-62-001)
Items: 10
County: HARRIS
Length: N/A
Highway: SS0330
District: HOUSTON
Control Number: 6433-62-001
DBE Goal: N/A
Project: BPM - 643362001
Guaranty: N/A
Time: 84 CALENDAR DAYS
Engineer's Estimate: $227,872.52
Date: 04/11/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPAIR
Mail/Deliver Bids To: N/A
JAMAL ELAHI
VANESSA BOSQUES
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$227,872.52 | |||
| $205,065.00 |
-10.01%
-$22,807.52
|
|||
| $226,100.00 |
-0.78%
-$1,772.52
|
10.26%
$21,035.00
|
||
| $247,900.00 |
8.79%
$20,027.48
|
20.89%
$42,835.00
|
-9.64%
-$21,800.00
|
|
| $446,412.00 |
95.9%
$218,539.48
|
117.69%
$241,347.00
|
-80.08%
-$198,512.00
|
|
| $527,295.00 |
131.4%
$299,422.48
|
157.14%
$322,230.00
|
-18.12%
-$80,883.00
|
E
Engineer's Estimate
$227,872.52
$205,065.00
Over/Under Est:
-10.01%
-$22,807.52
$226,100.00
Over/Under Est:
-0.78%
-$1,772.52
Amt Left:
10.26%
$21,035.00
$247,900.00
Over/Under Est:
8.79%
$20,027.48
Amt Left:
20.89%
$42,835.00
Delta:
-9.64%
-$21,800.00
$446,412.00
Over/Under Est:
95.9%
$218,539.48
Amt Left:
117.69%
$241,347.00
Delta:
-80.08%
-$198,512.00
$527,295.00
Over/Under Est:
131.4%
$299,422.48
Amt Left:
157.14%
$322,230.00
Delta:
-18.12%
-$80,883.00
Bid Items & Bid Tabulations
10
Total
0 of 10