HARRIS US0290 (6382-11-001)

Items: 10

County: HARRIS
Length: N/A
Highway: US0290
District: HOUSTON
Control Number: 6382-11-001
DBE Goal: N/A
Project: RMC - 638211001
Guaranty: N/A
Time: 53 W
Engineer's Estimate: $471,145.00
Date: 11/03/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$471,145.00
$400,000.00
Over/Under Est: -15.1% -$71,145.00
Over/Under Est: 24.2% $114,040.00
Amt Left: 46.3% $185,185.00
Over/Under Est: 25.89% $121,967.50
Amt Left: 48.28% $193,112.50
Delta: -1.35% -$7,927.50
Over/Under Est: 28.14% $132,565.00
Amt Left: 50.93% $203,710.00
Delta: -1.79% -$10,597.50
Over/Under Est: 44.88% $211,455.00
Amt Left: 70.65% $282,600.00
Delta: -13.07% -$78,890.00
Over/Under Est: 61.09% $287,830.00
Amt Left: 89.74% $358,975.00
Delta: -11.19% -$76,375.00

Bid Items & Bid Tabulations

10 Total 0 of 10
HARRIS  |  US0290  |  HOUSTON  |  6382-11-001  |  11/03/2021  |  $471,145.00  |  RMC - 638211001  |  BRIDGE PREVENT MAINT  |  53 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAGLE CONSTRUCTION, INC.
STRUCTURAL INTEGRITY GROUP LLC
B & MS CONSTRUCTION, INC.
NBG CONSTRUCTORS, INC.
FORDE CONSTRUCTION COMPANY, INC.
SCR CIVIL CONSTRUCTION, LLC
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 33.000 $350.000 $820.000 $800.000 $1,092.500 $700.000 $900.000 $700.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 28.000 $200.000 $320.000 $170.000 $201.250 $250.000 $200.000 $250.000
CLEANING AND SEALING EXISTING JOINTS
LF 430.000 $40.000 $52.000 $15.000 $28.750 $40.000 $20.000 $40.000
MOBILIZATION
LS 1.000 $38,595.000 $40,000.000 $50,000.000 $17,250.000 $58,000.000 $35,000.000 $77,100.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $15,000.000 $32,405.000 $37,000.000 $8,625.000 $32,000.000 $25,000.000 $38,550.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 240.000 $40.000 $10.000 $60.000 $40.250 $40.000 $25.000 $80.000
BRIDGE JOINT REPLACEMENT (SEJ)
LF 285.000 $600.000 $250.000 $815.000 $368.000 $870.000 $950.000 $995.000
REPLACE ELASTOMERIC BEARING PADS
EA 38.000 $4,500.000 $4,000.000 $4,200.000 $9,430.000 $4,400.000 $7,000.000 $4,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $100.000 $80.000 $200.000 $172.500 $55.000 $50.000 $600.000
TMA (STATIONARY)
DAY 53.000 $200.000 $120.000 $100.000 $402.500 $120.000 $150.000 $900.000
Totals: $471,145.000 $400,000.000 $585,185.000 $593,112.500 $603,710.000 $682,600.000 $758,975.000