HARRIS SL0008 (6377-83-001)

Items: 28

County: HARRIS
Length: N/A
Highway: SL0008
District: HOUSTON
Control Number: 6377-83-001
DBE Goal: N/A
Project: RMC - 637783001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $1,836,987.01
Date: 07/02/2021 (4 years ago)
Contract Number: N/A
Type: CONCRETE SPALL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$1,836,987.01
$1,600,650.00
Over/Under Est: -12.87% -$236,337.01
Over/Under Est: -11.25% -$206,637.01
Amt Left: 1.86% $29,700.00
$1,788,800.00
Over/Under Est: -2.62% -$48,187.01
Amt Left: 11.75% $188,150.00
Delta: -9.72% -$158,450.00

Bid Items & Bid Tabulations

28 Total 0 of 28
HARRIS  |  SL0008  |  HOUSTON  |  6377-83-001  |  07/02/2021  |  $1,836,987.01  |  RMC - 637783001  |  CONC SPALL REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
MAIN LANE INDUSTRIES LTD.
DBI SERVICES, LLC
REMOVING CONC (CURB)
LF 2,000.000 $4.830 $3.000 $3.000 $5.000
FULL - DEPTH REPAIR CRCP (10")
SY 1,000.000 $285.630 $232.000 $265.000 $260.000
FULL - DEPTH REPAIR CRCP (12")
SY 500.000 $306.730 $290.000 $280.000 $280.000
FULL - DEPTH REPAIR CRCP (14")
SY 100.000 $300.000 $325.000 $290.000 $300.000
FULL - DEPTH REPAIR CRCP (15")
SY 1,000.000 $315.000 $330.000 $310.000 $350.000
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 100.000 $293.180 $350.000 $280.000 $325.000
CEM STABIL BKFL
CY 20.000 $50.000 $70.000 $40.000 $100.000
CONC STR REPAIR (EPOXY MORTAR)
SF 50.000 $80.000 $70.000 $90.000 $120.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 1,500.000 $150.000 $100.000 $110.000 $120.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 1,000.000 $231.250 $150.000 $165.000 $160.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 30.000 $80.000 $80.000 $80.000 $80.000
RIPRAP (CONC)(FLUME)
CY 10.000 $1,000.000 $600.000 $650.000 $800.000
CLEANING AND SEALING EXISTING JOINTS
LF 5,000.000 $12.000 $15.000 $5.000 $15.000
INLET (COMPL)(EXT TY C)
EA 2.000 $1,257.140 $3,000.000 $1,500.000 $2,000.000
INLET (STG II)(TY C)
EA 2.000 $1,833.330 $1,700.000 $2,500.000 $3,000.000
MANH (STG II)(TY A)
EA 2.000 $1,342.860 $1,800.000 $2,000.000 $2,200.000
REMOV STR (INLET)
EA 3.000 $250.000 $1,000.000 $250.000 $500.000
MOBILIZATION (CALLOUT)
EA 24.000 $500.000 $500.000 $50.000 $500.000
MOBILIZATION (EMERGENCY)
EA 8.000 $1,250.000 $1,200.000 $1,500.000 $2,000.000
CONC CURB (U-TURN)
LF 500.000 $48.000 $79.000 $50.000 $50.000
CONC CURB (DOWEL)
LF 5,000.000 $16.100 $11.000 $18.000 $20.000
CONC SIDEWALKS (5")
SY 500.000 $90.000 $60.000 $60.000 $80.000
CURB RAMPS (TY 1)
EA 1.000 $2,000.000 $1,800.000 $1,500.000 $3,000.000
CURB RAMPS (TY 2)
EA 1.000 $3,500.000 $1,800.000 $1,700.000 $5,000.000
FIBER REINFORCED POLYMER PATCHING MATLS
LB 100,000.000 $2.300 $2.300 $2.300 $2.500
BRIDGE JOINT REPLACEMENT (SEJ)
LF 50.000 $186.590 $325.000 $650.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 30.000 $97.470 $80.000 $150.000 $200.000
TMA (STATIONARY)
DAY 175.000 $294.250 $100.000 $240.000 $200.000
Totals: $1,836,987.010 $1,600,650.000 $1,630,350.000 $1,788,800.000