HARRIS IH0010 (6351-83-001)

Items: 39

County: HARRIS
Length: N/A
Highway: IH0010
District: HOUSTON
Control Number: 6351-83-001
DBE Goal: N/A
Project: RMC - 635183001
Guaranty: N/A
Time: 366 CALENDAR DAYS
Engineer's Estimate: $1,591,060.00
Date: 05/08/2020 (6 years ago)
Contract Number: N/A
Type: TRAFFIC CONTROL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,591,060.00
$1,426,510.00
Over/Under Est: -10.34% -$164,550.00
Over/Under Est: -2.21% -$35,200.00
Amt Left: 9.07% $129,350.00
Over/Under Est: 0.35% $5,562.46
Amt Left: 11.93% $170,112.46
Delta: -2.62% -$40,762.46
$2,150,020.00
Over/Under Est: 35.13% $558,960.00
Amt Left: 50.72% $723,510.00
Delta: -34.66% -$553,397.54
$2,875,972.00
Over/Under Est: 80.76% $1,284,912.00
Amt Left: 101.61% $1,449,462.00
Delta: -33.76% -$725,952.00

Bid Items & Bid Tabulations

39 Total 0 of 39
HARRIS  |  IH0010  |  HOUSTON  |  6351-83-001  |  05/08/2020  |  $1,591,060.00  |  RMC - 635183001  |  TRAF CONTROL  |  366 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BATTERSON, LLP
PROFESSIONAL TRAFFIC CONTROL LLC
ALTUS TRAFFIC MANAGEMENT LLC
ISI CONTRACTING, INC.
NIXON ENGINEERING
MOBILIZATION (CALLOUT)
EA 52.000 $900.000 $650.000 $900.000 $169.900 $850.000 $1,000.000
MOBILIZATION (EMERGENCY)
EA 24.000 $1,000.000 $1,000.000 $725.000 $234.670 $1,500.000 $2,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 30.000 $105.000 $300.000 $180.000 $54.510 $100.000 $200.000
TMA (STATIONARY)
EA 150.000 $190.000 $400.000 $325.000 $904.830 $450.000 $1,000.000
TMA (MOBILE OPERATION)
HR 11,300.000 $85.000 $75.000 $74.000 $83.780 $85.000 $150.000
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 36.000 $600.000 $900.000 $1,200.000 $475.090 $1,000.000 $1,520.000
LANE CLOSURE (SETUP AND REMOV)(TY 2)
EA 41.000 $500.000 $900.000 $1,200.000 $475.090 $1,000.000 $1,520.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 22.000 $575.000 $1,000.000 $1,200.000 $475.090 $1,000.000 $2,400.000
LANE CLOSURE (SETUP AND REMOV)(TY 4)
EA 14.000 $500.000 $1,200.000 $1,800.000 $422.310 $1,200.000 $2,400.000
LANE CLOSURE (SETUP AND REMOV)(TY 5)
EA 27.000 $900.000 $1,250.000 $1,600.000 $475.090 $2,600.000 $2,400.000
LANE CLOSURE (SETUP AND REMOV)(TY 6)
EA 22.000 $1,000.000 $1,750.000 $1,400.000 $590.490 $2,800.000 $2,400.000
LANE CLOSURE (SETUP AND REMOV)(TY 7)
EA 14.000 $1,050.000 $2,300.000 $1,400.000 $675.300 $3,400.000 $3,200.000
LANE CLOSURE (SETUP AND REMOV)(TY 8)
EA 7.000 $1,100.000 $3,600.000 $2,000.000 $730.040 $2,800.000 $4,800.000
LANE CLOSURE (SETUP AND REMOV)(TY 9)
EA 46.000 $900.000 $1,400.000 $1,100.000 $584.730 $2,000.000 $2,080.000
LANE CLOSURE (SETUP AND REMOV)(TY 10)
EA 3.000 $110.000 $1,500.000 $2,500.000 $1,080.260 $3,000.000 $3,104.000
LANE CLOSURE (SETUP AND REMOV)(TY 11)
EA 4.000 $1,100.000 $10,000.000 $2,500.000 $1,095.060 $4,000.000 $5,600.000
LANE CLOSURE (SETUP AND REMOV)(TY 12)
EA 12.000 $800.000 $1,000.000 $1,200.000 $542.960 $2,500.000 $1,200.000
LANE CLOSURE (SETUP AND REMOV)(TY 13)
EA 4.000 $380.000 $1,500.000 $900.000 $584.730 $2,500.000 $2,000.000
LANE CLOSURE (SETUP AND REMOV)(TY 14)
EA 8.000 $500.000 $1,500.000 $1,000.000 $584.730 $2,500.000 $2,400.000
LANE CLOSURE (SETUP AND REMOV)(TY 15)
EA 3.000 $500.000 $1,800.000 $800.000 $584.730 $2,900.000 $3,200.000
LANE CLOSURE (SETUP AND REMOV)(TY 17)
EA 4.000 $450.000 $1,300.000 $800.000 $1,327.690 $1,200.000 $2,400.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 208.000 $120.000 $20.000 $85.000 $109.060 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 258.000 $110.000 $20.000 $85.000 $125.950 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 182.000 $115.000 $20.000 $85.000 $136.540 $220.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 4)
HR 112.000 $125.000 $20.000 $85.000 $175.010 $240.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 270.000 $150.000 $20.000 $85.000 $136.960 $175.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 6)
HR 230.000 $150.000 $20.000 $100.000 $166.850 $225.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 7)
HR 160.000 $210.000 $20.000 $150.000 $262.130 $230.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 8)
HR 70.000 $200.000 $20.000 $200.000 $229.690 $300.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 9)
HR 300.000 $175.000 $20.000 $85.000 $90.030 $280.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 10)
HR 24.000 $20.000 $20.000 $200.000 $244.130 $400.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 11)
HR 39.000 $300.000 $20.000 $200.000 $292.370 $500.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 12)
HR 92.000 $120.000 $20.000 $85.000 $162.920 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 13)
HR 32.000 $135.000 $20.000 $100.000 $163.040 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 14)
HR 60.000 $125.000 $20.000 $85.000 $158.210 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 15)
HR 24.000 $160.000 $20.000 $85.000 $176.180 $200.000 $100.000
LANE CLOSURE (MAINTENANCE) (TY 17)
HR 32.000 $130.000 $20.000 $100.000 $136.670 $200.000 $100.000
MOBILE OPERATIONS
HR 300.000 $85.000 $75.000 $135.000 $100.000 $180.000 $388.000
LANE CLOSURE (SETUP AND REMOV)(TY 21)
HR 30.000 $40.000 $20.000 $50.000 $135.380 $50.000 $388.000
Totals: $1,591,060.000 $1,426,510.000 $1,555,860.000 $1,596,622.460 $2,150,020.000 $2,875,972.000