HARRIS IH0045 (6332-04-001)

Items: 222

County: HARRIS
Length: N/A
Highway: IH0045
District: HOUSTON
Control Number: 6332-04-001
DBE Goal: N/A
Project: RMC - 633204001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $2,780,553.75
Date: 04/02/2019 (7 years ago)
Contract Number: N/A
Type: GENERAL MAINTENANCE OF IH 45
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$2,780,553.75
$2,894,122.02
Over/Under Est: 4.08% $113,568.27
$3,921,302.50
Over/Under Est: 41.03% $1,140,748.75
Amt Left: 35.49% $1,027,180.48
$4,643,214.60
Over/Under Est: 66.99% $1,862,660.85
Amt Left: 60.44% $1,749,092.58
Delta: -18.41% -$721,912.10

Bid Items & Bid Tabulations

222 Total 0 of 222
HARRIS  |  IH0045  |  HOUSTON  |  6332-04-001  |  04/02/2019  |  $2,780,553.75  |  RMC - 633204001  |  GENERAL MAINT OF IH 45  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROY JORGENSEN ASSOCIATES, INC.
ISI CONTRACTING, INC.
DBI SERVICES, LLC
REMOVING CONC (CURB)
LF 50.000 $6.600 $10.000 $1.000 $21.000
REMOVING CONC (CTB)
LF 10.000 $43.100 $20.000 $17.000 $82.000
BLADING
STA 100.000 $87.500 $95.000 $205.000 $115.000
BLADING
LF 5,000.000 $4.800 $2.000 $5.000 $4.600
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 250.000 $49.900 $47.000 $80.000 $65.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 9,000.000 $23.000 $27.500 $40.000 $24.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 100.000 $26.000 $44.000 $70.000 $45.000
FLEX PAVEMENT STRUCTURE REPAIR (7"-13")
SY 20.000 $95.000 $150.000 $120.000 $100.000
FULL - DEPTH REPAIR CRCP (10")
SY 500.000 $298.900 $210.000 $268.000 $230.000
FULL - DEPTH REPAIR CRCP (12")
SY 250.000 $261.000 $214.000 $316.000 $250.000
FULL - DEPTH REPAIR CRCP (14")
SY 250.000 $248.300 $244.000 $322.000 $265.000
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 250.000 $412.600 $345.000 $395.000 $260.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 75.000 $70.300 $90.000 $90.000 $200.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 75.000 $128.200 $125.000 $115.000 $360.000
RIPRAP (MOW STRIP)(5 IN)
CY 10.000 $419.700 $700.000 $450.000 $475.000
MOBILIZATION (CALLOUT)
EA 48.000 $382.900 $2,650.000 $300.000 $1,250.000
MOBILIZATION (EMERGENCY)
EA 12.000 $454.300 $3,000.000 $2,500.000 $1,875.000
PORT CTB (MOVE) (SAFETY SH) (TY 2)
LF 1,000.000 $7.900 $10.000 $6.000 $5.000
PORT CTB (REMOVE) (SAFETY SH) (TY 2)
LF 30.000 $17.400 $20.000 $16.000 $38.000
PORT CTB (DES SOURCE) (SAFETY SH)(TY 2)
LF 30.000 $15.000 $30.000 $35.000 $38.000
CONC CURB (U-TURN)
LF 200.000 $19.700 $25.000 $75.000 $44.000
CONC CURB (DOWEL)
LF 100.000 $15.200 $25.000 $10.500 $45.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $688.400 $1,700.000 $2,400.000 $2,260.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $987.700 $2,000.000 $1,250.000 $1,400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,489.100 $2,400.000 $2,900.000 $3,550.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $114.100 $500.000 $240.000 $490.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $11,376.800 $20,000.000 $29,000.000 $25,000.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $785.800 $5,000.000 $550.000 $950.000
CHAIN LINK FENCE (INSTALL) (6')
LF 20.000 $19.000 $20.000 $28.000 $50.000
CHAIN LINK FENCE (REPAIR) (6')
LF 20.000 $8.200 $20.000 $23.000 $50.000
GATE (INSTALL) (DOUBLE) (6' X 14')
EA 1.000 $1,359.300 $1,000.000 $1,200.000 $1,700.000
ALUMINUM SIGNS (TY A)
SF 100.000 $18.300 $14.500 $18.000 $25.000
ALUMINUM SIGNS (TY G)
SF 150.000 $25.400 $29.000 $18.000 $28.000
ALUMINUM SIGNS (TY O)
SF 30.000 $28.700 $35.000 $18.000 $36.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 100.000 $25.400 $14.500 $30.000 $26.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 200.000 $23.000 $14.500 $36.000 $29.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 30.000 $28.600 $38.000 $48.000 $37.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $470.200 $400.000 $305.000 $775.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 1.000 $800.000 $600.000 $480.000 $865.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $578.700 $600.000 $460.000 $820.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $650.000 $700.000 $440.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $888.000 $950.000 $640.000 $900.000
IN SM RD SN SUP&AM TYS80(2)SA(P)
EA 1.000 $675.000 $1,000.000 $590.000 $1,000.000
INSTALL LRSS (STRUCT STEEL)
LB 1,000.000 $4.600 $3.500 $4.000 $6.250
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 15.000 $3.150 $20.000 $4.000 $26.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 25.000 $6.700 $20.000 $4.000 $25.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 300.000 $0.900 $0.309 $0.350 $2.400
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,500.000 $0.800 $0.876 $1.000 $1.100
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 5,000.000 $2.500 $2.060 $2.200 $3.200
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 2,000.000 $3.700 $3.090 $3.300 $6.600
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 35.000 $91.000 $87.550 $95.000 $160.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 25.000 $130.000 $144.200 $152.000 $150.000
REFL PAV MRK TY I(W)(TPL ARRW)(100MIL)
EA 1.000 $150.700 $231.750 $248.000 $120.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 20.000 $146.700 $144.200 $150.000 $135.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 50.000 $113.800 $128.750 $136.000 $120.000
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 8.000 $324.800 $463.500 $490.000 $635.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 8.000 $339.400 $463.500 $490.000 $570.000
REFL PAV MRK TY I (W) (ISLAND) (100MIL)
SF 1.000 $5.000 $206.000 $220.000 $4.000
REF PAV MRK TY I (W)(MED NOSE)(100MIL)
EA 10.000 $124.500 $360.500 $380.000 $345.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 1.000 $361.200 $515.000 $540.000 $600.000
REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
EA 1.000 $124.400 $128.750 $140.000 $260.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 5,000.000 $0.800 $0.721 $0.800 $1.250
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 1,000.000 $2.200 $2.050 $2.200 $3.250
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 100.000 $4.100 $4.120 $4.400 $6.500
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 5.000 $180.100 $309.000 $325.000 $180.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 1,000.000 $0.400 $0.876 $1.000 $1.200
PAVEMENT SEALER 6"
LF 261,800.000 $0.100 $0.031 $0.030 $0.110
PAVEMENT SEALER 8"
LF 9,500.000 $0.200 $0.052 $0.050 $0.180
PAVEMENT SEALER 12"
LF 6,000.000 $0.400 $0.124 $0.150 $0.450
PAVEMENT SEALER 24"
LF 2,100.000 $0.400 $0.247 $0.250 $0.750
PAVEMENT SEALER (ARROW)
EA 35.000 $10.900 $5.150 $5.500 $58.000
PAVEMENT SEALER (WORD)
EA 50.000 $15.900 $5.150 $6.000 $58.000
PAVEMENT SEALER (MED NOSE)
EA 15.000 $6.600 $10.300 $11.000 $61.000
PAVEMENT SEALER (DBL ARROW)
EA 25.000 $19.000 $10.300 $11.000 $65.000
PAVEMENT SEALER (TPL ARROW)
EA 1.000 $18.500 $15.450 $16.000 $66.000
PAVEMENT SEALER (UTURN ARROW)
EA 20.000 $19.200 $10.300 $11.000 $58.000
PAVEMENT SEALER (ENTR GORE)
EA 8.000 $86.700 $41.200 $44.000 $200.000
PAVEMENT SEALER (EXIT GORE)
EA 8.000 $96.800 $41.200 $44.000 $300.000
PAVEMENT SEALER (SYMBOL)
EA 1.000 $16.000 $10.300 $11.000 $61.000
PAVEMENT SEALER (RR XING)
EA 1.000 $60.200 $51.500 $55.000 $91.000
PAVEMENT SEALER (ISLAND)
SF 1.000 $6.700 $25.750 $30.000 $56.000
PAVEMENT SEALER (NUMBER)
EA 1.000 $8.400 $25.750 $30.000 $44.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 60,000.000 $0.400 $0.433 $0.500 $0.640
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 100,000.000 $0.400 $0.412 $0.450 $0.640
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 500.000 $0.400 $0.618 $0.650 $0.640
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 100,000.000 $0.400 $0.412 $0.450 $0.640
PREFAB PAV MRK TY C (W) (NUMBER)
EA 2.000 $123.100 $2,250.000 $2,450.000 $175.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $222.900 $360.500 $380.000 $225.000
REFL PAV MRKR TY I-A
EA 25.000 $2.600 $4.635 $5.000 $4.200
REFL PAV MRKR TY I-C
EA 50.000 $2.800 $4.635 $5.000 $4.200
REFL PAV MRKR TY I-R
EA 25.000 $3.500 $5.150 $5.400 $4.200
REFL PAV MRKR TY II-A-A
EA 50.000 $2.500 $4.635 $4.900 $4.200
REFL PAV MRKR TY II-C-R
EA 1,000.000 $3.000 $4.120 $4.400 $4.200
ELIM EXT PAV MRK & MRKS (4")
LF 100.000 $0.300 $0.155 $0.200 $0.380
ELIM EXT PAV MRK & MRKS (6")
LF 261,800.000 $0.200 $0.185 $0.200 $0.410
ELIM EXT PAV MRK & MRKS (8")
LF 950.000 $0.500 $0.258 $0.300 $0.480
ELIM EXT PAV MRK & MRKS (12")
LF 6,000.000 $0.800 $0.618 $0.650 $0.610
ELIM EXT PAV MRK & MRKS (24")
LF 2,100.000 $1.300 $1.288 $1.400 $0.800
ELIM EXT PAV MRK & MRKS (ARROW)
EA 35.000 $29.600 $20.600 $22.000 $70.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 25.000 $34.600 $46.350 $50.000 $70.000
ELIM EXT PAV MRK & MRKS (TPL ARROW)
EA 1.000 $37.800 $61.800 $65.000 $70.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 52.000 $35.500 $25.750 $27.000 $70.000
ELIM EXT PAV MRK & MRKS (ENTR GORE)
EA 8.000 $125.600 $125.000 $135.000 $135.000
ELIM EXT PAV MRK & MRKS (EXIT GORE)
EA 8.000 $137.200 $125.000 $135.000 $140.000
ELIM EXT PAV MRK & MRKS (RR XING)
EA 1.000 $116.200 $154.500 $163.000 $220.000
ELIM EXT PAV MRK & MRKS (SYMBOL)
EA 1.000 $44.200 $51.500 $55.000 $55.000
ELIM EXT PAV MRK & MRKS (MED NOSE)
EA 15.000 $9.700 $90.000 $108.000 $175.000
ELIM EXT PAV MRK & MRKS (UTURN ARROW)
EA 20.000 $32.300 $51.500 $55.000 $70.000
PAV SURF PREP FOR MRK (6")
LF 261,800.000 $0.100 $0.021 $0.020 $0.030
PAV SURF PREP FOR MRK (8")
LF 9,500.000 $0.100 $0.062 $0.070 $0.060
PAV SURF PREP FOR MRK (12")
LF 6,000.000 $0.100 $0.124 $0.150 $0.070
PAV SURF PREP FOR MRK (24")
LF 2,100.000 $0.100 $0.247 $0.250 $0.160
PAV SURF PREP FOR MRK (ARROW)
EA 35.000 $2.200 $5.150 $5.500 $10.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 25.000 $1.700 $10.300 $11.000 $12.000
PAV SURF PREP FOR MRK (TPL ARROW)
EA 1.000 $9.500 $10.300 $11.000 $10.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 20.000 $1.000 $10.300 $11.000 $10.000
PAV SURF PREP FOR MRK (NUMBER)
EA 3.000 $13.400 $10.300 $11.000 $10.000
PAV SURF PREP FOR MRK (WORD)
EA 52.000 $2.200 $10.300 $11.000 $10.000
PAV SURF PREP FOR MRK (ENTR GORE)
EA 8.000 $25.000 $25.750 $27.000 $160.000
PAV SURF PREP FOR MRK (EXIT GORE)
EA 8.000 $25.000 $25.750 $27.000 $250.000
PAV SURF PREP FOR MRK (RR XING)
EA 1.000 $5.000 $25.750 $27.000 $250.000
PAV SURF PREP FOR MRK (SYMBOL)
EA 1.000 $1.800 $25.750 $27.000 $10.000
PAV SURF PREP FOR MRK (MED NOSE)
EA 15.000 $4.600 $25.750 $27.000 $16.000
POTHOLE REPAIR (STANDARD)
SY 100.000 $96.100 $150.000 $150.000 $140.000
FIBER REINFORCED POLYMER PATCHING MATLS
LB 15,000.000 $2.200 $1.350 $2.200 $4.500
SPOT MOWING
AC 100.000 $4.000 $36.000 $34.000 $58.000
FULL - WIDTH MOWING - TRACT (1)
AC 10,800.000 $12.000 $3.000 $34.000 $46.700
FULL - WIDTH MOWING - TRACT (2)
AC 10,098.000 $12.000 $3.000 $34.000 $46.700
PAVEMENT EDGES, STRUCTURES & FIXTURES
MI 200.000 $99.000 $150.000 $200.000 $260.000
LITTER REMOVAL (SPOT)
AC 50.000 $9.900 $20.000 $28.000 $36.500
LITTER REMOVAL - TRACT (1)
CYC 12.000 $10,800.000 $5,500.000 $8,500.000 $11,825.000
LITTER REMOVAL - TRACT (2)
CYC 12.000 $10,098.000 $5,500.000 $8,500.000 $10,990.000
DEBRIS REMOVAL (SPOT DEBRIS)
MI 1,000.000 $36.100 $1.000 $180.000 $36.500
CLEANING / SWEEPING (SPOT)
MI 20.000 $110.300 $325.000 $350.000 $440.000
CLEANING / SWEEPING (HANDWORK)
SY 100,000.000 $0.300 $0.250 $0.200 $0.070
CLEAN / SWEEP - CENTER MEDIAN - AREA(1)
CYC 24.000 $2,808.000 $4,500.000 $4,900.000 $5,980.000
CLEAN / SWEEP - CENTER MEDIAN - AREA(2)
CYC 24.000 $2,136.000 $3,500.000 $3,700.000 $4,550.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(1)
CYC 24.000 $2,808.000 $4,500.000 $4,900.000 $5,975.000
CLEAN / SWEEP-OUTSIDE MAIN LANE-AREA(2)
CYC 24.000 $2,136.000 $3,500.000 $3,700.000 $4,550.000
CLEAN / SWEEP - FRONTAGE ROAD - AREA(1)
CYC 12.000 $3,468.000 $4,500.000 $5,900.000 $7,385.000
CLEAN / SWEEP - FRONTAGE ROAD - AREA(2)
CYC 12.000 $2,952.000 $4,000.000 $5,000.000 $6,285.000
CLEAN / SWEEP - (ENTR /EXT RMP)(AREA 1)
CYC 12.000 $2,318.400 $4,500.000 $3,400.000 $4,290.000
CLEAN / SWEEP - (ENTR /EXT RMP)(AREA 2)
CYC 12.000 $1,876.800 $4,000.000 $2,800.000 $3,475.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(1)
CYC 12.000 $456.000 $1,200.000 $800.000 $970.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(4)
CYC 12.000 $324.000 $850.000 $550.000 $670.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(6)
CYC 12.000 $216.000 $600.000 $370.000 $460.000
CLEAN/SWEEPING-DIRECT CONNECT-AREA(7)
CYC 12.000 $732.000 $2,000.000 $1,300.000 $1,560.000
TREE TRIMMING / BRUSH REMOVAL
MI 10.000 $1,764.900 $2,000.000 $1,000.000 $2,050.000
TREE REMOVAL (4" - 12" DIA)
EA 15.000 $49.500 $200.000 $195.000 $170.000
TREE REMOVAL (12" - 18" DIA)
EA 15.000 $79.100 $200.000 $330.000 $205.000
TREE REMOVAL (18" - 24" DIA)
EA 15.000 $109.900 $200.000 $330.000 $250.000
TREE REMOVAL (24" - 30" DIA)
EA 15.000 $156.200 $200.000 $450.000 $340.000
TREE REMOVAL (30" - 36" DIA)
EA 6.000 $238.900 $200.000 $530.000 $500.000
TREE REMOVAL (36" - 42" DIA)
EA 6.000 $376.100 $200.000 $930.000 $1,100.000
TREE REMOVAL (42" - 48" DIA)
EA 6.000 $484.200 $200.000 $950.000 $2,000.000
DRAIN INLET CLEANING
EA 400.000 $80.000 $85.000 $75.000 $95.000
STORM SEWER CLEANING (PIPE) (<12" DIA)
LF 150.000 $3.300 $3.000 $2.200 $3.000
STORM SEWER CLEANING (PIPE)(12"-18"DIA)
LF 7,000.000 $4.100 $5.000 $3.300 $4.400
STORM SEWER CLEANING (PIPE)(19"-24"DIA)
LF 2,500.000 $5.000 $6.500 $3.850 $5.250
STORM SEWER CLEANING (PIPE)(25"-30"DIA)
LF 3,000.000 $5.800 $7.000 $4.400 $5.500
STORM SEWER CLEANING (PIPE)(31"-36"DIA)
LF 500.000 $7.600 $8.000 $5.000 $6.500
STORM SEWER CLEANING (PIPE)(37"-42"DIA)
LF 20.000 $8.600 $8.000 $5.500 $7.000
STORM SEWER CLEANING (PIPE)(43"-54"DIA)
LF 1,000.000 $10.600 $14.000 $8.300 $11.000
STORM SEWER CLEAN (BOX CULV) (<6 SF)
LF 25.000 $8.000 $15.000 $13.300 $17.000
STORM SEWER CLEAN (BOX CULV) (6-<12 SF)
LF 25.000 $9.800 $16.000 $16.500 $20.000
STORM SEWER CLEAN (BOX CULV)(12-<24 SF)
LF 500.000 $12.800 $17.000 $17.500 $24.000
STORM SEWER CLEAN (BOX CULV)(24-<48 SF)
LF 500.000 $17.100 $25.000 $22.100 $30.000
STORM SEWER CLEAN (BOX CULV)(48-<96 SF)
LF 300.000 $22.600 $26.000 $24.000 $32.000
STORM SEWER CLEAN (BOX CULV) (>96 SF)
LF 25.000 $66.000 $36.000 $36.000 $50.000
SLOTTED DRAIN CLEANING
LF 25.000 $4.500 $10.000 $10.000 $13.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 2,500.000 $14.000 $15.000 $15.500 $18.500
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 1.000 $20.400 $125.000 $100.000 $70.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 1.000 $21.500 $125.000 $100.000 $75.000
RAISE RAIL ELEMENT
LF 300.000 $2.000 $20.000 $6.000 $20.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 100.000 $36.800 $75.000 $38.000 $130.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 75.000 $33.900 $100.000 $41.000 $165.000
REPAIR STEEL POST WITH BASE PLATE
EA 1.000 $136.900 $180.000 $230.000 $100.000
REALIGN POSTS
EA 150.000 $9.900 $40.000 $6.000 $40.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 1,500.000 $21.900 $25.000 $24.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 200.000 $32.500 $55.000 $40.000 $160.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 1.000 $2,624.800 $3,000.000 $3,100.000 $3,200.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 40.000 $870.000 $1,000.000 $1,025.000 $1,200.000
REM & RESET SGT IMPACT HEAD
EA 25.000 $53.700 $100.000 $110.000 $450.000
REPLACE SGT CABLE ASSEMBLY
EA 20.000 $60.200 $250.000 $112.000 $470.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $34.900 $200.000 $90.000 $460.000
REPLACE SGT STRUT
EA 15.000 $51.000 $126.000 $60.000 $440.000
REPLACE SGT OBJECT MARKER
EA 1.000 $29.900 $50.000 $35.000 $65.000
REPAIR STEEL POST WITH BASE PLATE
EA 3.000 $100.000 $90.000 $150.000 $100.000
REMOVE AND REPLACE (NARROW REACT 350)
EA 1.000 $9,312.500 $18,500.000 $21,500.000 $28,000.000
REMOVE AND REPLACE (WIDE REACT 350)
EA 1.000 $19,083.400 $25,000.000 $42,000.000 $52,000.000
REPAIR (TRACC)
EA 1.000 $2,000.000 $2,500.000 $3,000.000 $7,295.000
REPAIR (WIDE TRACC)
EA 1.000 $778.200 $4,300.000 $3,000.000 $8,750.000
REPAIR (CATCB - FRNT SECT)
EA 1.000 $484.400 $450.000 $800.000 $3,600.000
REPAIR (CATCB - REAR SECT)
EA 1.000 $362.000 $450.000 $800.000 $1,850.000
REPAIR (WIDE QUAD)
EA 1.000 $500.000 $1,350.000 $2,800.000 $1,800.000
REPAIR REACT (N) (MISC HARDWARE)
EA 4.000 $845.000 $900.000 $950.000 $1,920.000
REPAIR REACT (N) (REAR SEC "S")
EA 3.000 $242.200 $315.000 $100.000 $1,050.000
REPAIR REACT (N) (REAR SEC "B")
EA 2.000 $130.000 $225.000 $100.000 $1,050.000
REPAIR REACT (N) (FRONT SECTION)
EA 2.000 $466.000 $450.000 $500.000 $1,300.000
REPAIR REACT (N) (CYLINDERS)
EA 2.000 $1,756.200 $1,800.000 $2,900.000 $3,100.000
REPAIR REACT (W) (MISC) (HARDWARE)
EA 4.000 $459.600 $2,000.000 $900.000 $1,900.000
REPAIR REACT (W) (CYLINDERS)
EA 4.000 $1,179.000 $2,600.000 $2,900.000 $3,700.000
REPAIR TAU II (N) (MISC HARDWARE)
EA 1.000 $1,418.200 $1,500.000 $3,000.000 $2,900.000
REPAIR TAU II (N)
LF 35.000 $211.100 $250.000 $430.000 $420.000
REPAIR TAU II (W)
LF 5.000 $205.000 $180.000 $600.000 $730.000
REPAIR TAU II (W) (MISC HARDWARE)
EA 1.000 $2,700.000 $1,800.000 $3,000.000 $4,400.000
REMOVE & REPLACE REACT 350(TXDOT FRNSH)
EA 1.000 $2,571.500 $3,150.000 $4,000.000 $4,700.000
REPAIR (STL PIPE PEDESTRIAN RAIL - PR1)
LF 15.000 $111.000 $70.000 $130.000 $225.000
REPAIR (STL PIPE PED RAILW/PARAPET-PR2)
LF 15.000 $48.000 $90.000 $100.000 $520.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $100.000 $90.000 $90.000 $195.000
REPAIR LG RDSD SIGN SUPT & ASSEMBLIES
EA 15.000 $750.000 $800.000 $1,000.000 $1,050.000
REMV LARGE RDSD SIGN SUPP & ASSEM
EA 1.000 $100.000 $250.000 $330.000 $490.000
REPAIR SMALL RDSD SIGN SUPT & ASSEM
EA 200.000 $500.000 $320.000 $260.000 $232.000
REMV SMALL RDSD SIGN SUPP & ASSEM
EA 1.000 $50.800 $225.000 $60.000 $196.000
TMA (STATIONARY)
EA 200.000 $145.100 $200.000 $250.000 $385.000
TMA (MOBILE OPERATION)
HR 2,000.000 $52.700 $40.000 $49.000 $62.000
STORM SEWER (TELEVISION INSPECTION)
LF 25.000 $4.500 $9.000 $3.500 $4.400
SNOW AND ICE CONTROL (TRUCK)
HR 50.000 $65.300 $95.000 $57.000 $170.000
SNOW AND ICE CONTROL (SHADOW VEHICLE)
HR 200.000 $52.900 $95.000 $46.000 $115.000
SNOW AND ICE CONTROL (LOADER)
HR 5.000 $63.000 $200.000 $100.000 $340.000
SNOW AND ICE CONTROL (SEASON)
MO 3.000 $30,666.700 $39,000.000 $35,000.000 $50,700.000
SNOW AND ICE CONTROL (SPRAY RIG)
HR 200.000 $78.100 $95.000 $35.000 $156.000
Totals: $2,780,553.750 $2,894,122.025 $3,921,302.500 $4,643,214.600