Show Job Controls
Bid Cobra

HARRIS SH 99 (3510-06-025)

Items: 23

County: HARRIS
Length: N/A
Highway: SH 99
District: HOUSTON
Control Number: 3510-06-025
DBE Goal: N/A
Project: C 3510-6-25
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $4,364,513.90
Date: 07/09/2020 (5 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$4,364,513.90
$3,179,979.15
Over/Under Est: -27.14% -$1,184,534.75
Over/Under Est: -24.7% -$1,078,040.60
Amt Left: 3.35% $106,494.15
Over/Under Est: -22.24% -$970,767.18
Amt Left: 6.72% $213,767.57
Delta: -3.26% -$107,273.42
$3,956,327.15
Over/Under Est: -9.35% -$408,186.75
Amt Left: 24.41% $776,348.00
Delta: -16.58% -$562,580.43
$4,940,121.30
Over/Under Est: 13.19% $575,607.40
Amt Left: 55.35% $1,760,142.15
Delta: -24.87% -$983,794.15

Bid Items & Bid Tabulations

23 Total 0 of 23
HARRIS  |  SH 99  |  HOUSTON  |  3510-06-025  |  07/09/2020  |  $4,364,513.90  |  C 3510-6-25  |  LANDSCAPE DEVELOPMENT  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTRAL NORTH CONSTRUCTION, LLC
APEX LANDSCAPE & IRRIGATION, LLC
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
BOYER, INC.
TEXAS WALL & LANDSCAPE
PREP ROW (TREE) (2" TO 12" DIA)
EA 1.000 $500.000 $2,500.000 $500.000 $290.625 $1,188.000 $2,000.000
EROSION CONTROL COMPOST
CY 33,993.000 $25.000 $19.000 $16.000 $18.386 $20.000 $16.000
GENERAL USE COMPOST
CY 20,709.000 $30.000 $21.000 $20.200 $21.126 $23.000 $18.000
FERTILIZER
AC 11.410 $1,250.000 $700.000 $1,000.000 $1,558.087 $4,105.750 $1,050.000
VEGETATIVE WATERING
MG 1,465.000 $45.000 $15.000 $0.100 $70.094 $216.000 $6.000
WILDFLOWER SEEDING
AC 13.000 $1,500.000 $550.000 $555.000 $750.000 $1,974.000 $1,200.000
WILDFLOWER SEEDING (MIX 1)
AC 11.410 $1,250.000 $550.000 $415.000 $694.444 $1,978.000 $1,750.000
WILDFLOWER SEEDING (MIX 2)
AC 63.000 $1,250.000 $325.000 $225.000 $694.444 $1,419.500 $1,200.000
PLANT MATERIAL (3-GAL)
EA 3,675.000 $15.000 $18.000 $17.250 $11.054 $14.850 $18.000
PLANT MATERIAL (5 GAL) (TREE)
EA 38,578.000 $20.000 $19.000 $17.000 $12.151 $19.750 $19.000
PLANT MATERIAL (15 GAL) (TREE)
EA 2,642.000 $100.000 $90.000 $97.000 $42.581 $66.000 $100.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 859.000 $20.000 $15.000 $12.500 $14.552 $20.000 $15.000
PLANT BED PREP (TYPE II)
SY 372,010.000 $0.400 $0.310 $0.300 $0.294 $1.000 $0.500
PLANT MAINTENANCE
MO 18.000 $35,000.000 $14,000.000 $20,000.000 $36,315.595 $15,000.000 $72,500.000
MOBILIZATION
LS 1.000 $390,000.000 $177,777.200 $322,564.600 $339,062.500 $160,000.000 $485,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $5,000.000 $1,800.000 $2,850.000 $2,120.536 $4,297.000 $10,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 10,000.000 $4.000 $1.900 $1.250 $4.063 $5.000 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 10,000.000 $1.000 $0.250 $0.250 $0.469 $1.000 $0.750
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 372,010.000 $0.200 $0.300 $0.350 $0.176 $0.340 $0.300
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 372,010.000 $0.150 $0.250 $0.300 $0.143 $0.270 $0.250
LANDSCAPE TREATMENT(TY 1)
EA 44,895.000 $1.500 $0.750 $1.150 $1.114 $0.700 $1.500
LANDSCAPE TREATMENT(TY 2)
EA 224,475.000 $0.400 $0.600 $0.650 $0.265 $0.400 $1.500
LANDSCAPE TREATMENT (TY 5)
EA 45,754.000 $0.350 $0.400 $0.250 $2.391 $0.430 $0.200
Totals: $4,364,513.900 $3,179,979.150 $3,286,473.300 $3,393,746.779 $3,956,327.158 $4,940,121.300