Job Info for 3510-05-045

County: HARRIS Highway: SH 99 Date: 08/06/2019 (5 years ago) Engineer's Estimate: $4,059,577 Control Number: 3510-05-045
Project: C 3510-5-45 District: HOUSTON Time: 210 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,059,577.25
APEX LANDSCAPE & IRRIGATION, LLC   $3,484,500.00 1
-14.17% | -$575,077.25
CENTRAL NORTH CONSTRUCTION, LLC   $3,557,013.57 2
-12.38% | -$502,563.68
2.08% | $72,513.57
TEXAS WALL & LANDSCAPE   $3,803,764.00 3
-6.3% | -$255,813.25
9.16% | $319,264.00
6.94% | $246,750.43
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $3,856,112.37 4
-5.01% | -$203,464.88
10.66% | $371,612.37
1.38% | $52,348.37

Bid Items

Items: 26, 0 filtered
HARRIS SH 99  |  HOUSTON  |  3510-05-045  |  08/06/2019  |  $4,059,577  |  C 3510-5-45  |  LANDSCAPE DEVELOPMENT  |  210 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC CENTRAL NORTH CONSTRUCTION, LLC TEXAS WALL & LANDSCAPE YELLOWSTONE LANDSCAPE - CENTRAL, INC.
100 6013 PREP ROW (TREE) (2" TO 12" DIA) EA 1.000 $500.000 $500.000 $10,000.000 $4,500.000 $2,500.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 345.000 $30.000 $40.000 $50.000 $60.000 $58.439
161 6009 EROSION CONTROL COMPOST CY 28,628.000 $27.000 $17.250 $18.700 $20.000 $23.945
161 6012 GENERAL USE COMPOST CY 14,235.000 $29.000 $20.250 $19.000 $20.000 $23.228
166 6001 FERTILIZER AC 22.500 $650.000 $1,000.000 $750.000 $900.000 $1,577.061
168 6001 VEGETATIVE WATERING MG 441.000 $25.000 $0.100 $18.000 $65.000 $34.745
180 6001 WILDFLOWER SEEDING AC 22.500 $1,200.000 $595.000 $1,250.000 $2,600.000 $1,146.953
180 6002 WILDFLOWER SEEDING (MIX 1) AC 51.000 $750.000 $315.000 $1,250.000 $2,600.000 $917.141
192 6003 PLANT MATERIAL (3-GAL) EA 5,549.000 $12.500 $17.250 $10.900 $20.500 $12.208
192 6012 MULCH CY 9,993.000 $12.000 $12.000 $17.000 $24.000 $17.754
192 6021 PLANT MATERIAL (5 GAL) (TREE) EA 25,886.000 $15.000 $20.250 $12.300 $21.000 $13.850
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 5,534.000 $100.000 $91.000 $64.700 $70.000 $92.682
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 228.000 $15.000 $16.000 $11.600 $20.500 $9.904
192 6064 PLANT BED PREP (TYPE II) SY 254,812.000 $0.800 $0.300 $0.270 $0.900 $0.329
192 6065 PLANT BED PREP (TYPE III) SY 904.000 $2.000 $1.550 $0.500 $10.000 $0.321
193 6001 PLANT MAINTENANCE MO 18.000 $25,000.000 $20,000.000 $18,500.000 $8,000.000 $34,310.036
193 6002 PLANT MAINTENANCE CYC 11.000 $5,500.000 $18,500.000 $52,500.000 $7,500.000 $14,662.757
500 6001 MOBILIZATION LS 1.000 $381,300.000 $341,521.050 $430,000.000 $375,000.000 $385,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $5,000.000 $2,850.000 $1,675.800 $5,500.000 $806.452
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 15,000.000 $6.000 $1.250 $3.200 $4.500 $3.387
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 15,000.000 $2.000 $0.250 $0.280 $2.000 $0.323
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 264,328.000 $0.500 $0.350 $0.130 $0.200 $0.146
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 264,328.000 $0.300 $0.300 $0.125 $0.090 $0.132
1006 6003 LANDSCAPE SOIL AMENDMENT (TYPE III) SY 36,969.000 $1.500 $1.150 $0.810 $2.750 $0.803
1006 6004 LANDSCAPE SOIL AMENDMENT (TYPE IV) SY 184,845.000 $0.350 $0.650 $0.230 $1.000 $0.423
1006 6005 LANDSCAPE SOIL AMENDMENT (TYPE V) SY 37,197.000 $0.500 $0.250 $1.950 $0.390 $2.118
Totals: $4,059,577.25 $3,484,500.00 $3,557,013.57 $3,803,764.00 $3,856,112.47