Bid Cobra

HARRIS SL 8 (3256-03-106)

Items: 58

County: HARRIS
Length: 0.0000 MILES
Highway: SL 8
District: HOUSTON
Control Number: 3256-03-106
DBE Goal: 0.0%
Project: STP 2B25(014)MM
Guaranty: $28,000.00
Time: 75 WORKING DAYS
Engineer's Estimate: $1,092,183.78
Date: 07/01/2025 (11 months ago)
Contract Number: 7253021
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00197546
Contract Type: Federal
Project Description: REMOVE AND REPLACE PAVEMENT MARKINGS WITH MPM (FRONTAGE ROADS)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PHILLIP GARLIN
NYEMB NYEMB
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,092,183.78
Over/Under Est: -19.8% -$216,225.39
Over/Under Est: -15.64% -$170,771.19
Amt Left: 5.19% $45,454.20
$998,776.57
Over/Under Est: -8.55% -$93,407.21
Amt Left: 14.02% $122,818.18
Delta: -8.40% -$77,363.98
$1,360,933.92
Over/Under Est: 24.61% $268,750.14
Amt Left: 55.37% $484,975.53
Delta: -36.26% -$362,157.35

Bid Items & Bid Tabulations

58 Total 0 of 58
HARRIS  |  SL 8  |  HOUSTON  |  3256-03-106  |  07/01/2025  |  $1,092,183.78  |  STP 2B25(014)MM  |  SURF/ROADWAY RESTOR  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PROFESSIONAL TRAFFIC CONTROL LLC
TRP INFRASTRUCTURE SERVICES, LLC
BATTERSON, LLP
STRIPE LINES, INC.
MOBILIZATION
LS 1.000 $60,000.000 $25,000.000 $18,000.000 $13,000.000 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,400.000 $2,500.000 $1,500.000 $3,500.000 $750.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 47.000 $115.000 $20.000 $55.000 $100.000 $10.000
TMA (STATIONARY)
DAY 12.000 $255.480 $200.000 $1,500.000 $1,000.000 $10.000
TMA (MOBILE OPERATION)
DAY 188.000 $202.920 $20.000 $100.000 $25.000 $10.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 134.000 $11.100 $15.000 $11.000 $20.000 $28.790
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 24.000 $28.430 $40.000 $11.000 $30.000 $45.980
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 127.000 $14.020 $15.000 $11.000 $25.000 $28.790
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 131.000 $63.230 $40.000 $11.000 $30.000 $45.980
RE PM TY II (Y) 12" (SLD)
LF 3,686.000 $2.250 $2.000 $1.750 $2.500 $3.260
RE PM TY III (W)(12")(SLD)
LF 5,124.000 $1.960 $3.500 $3.000 $5.000 $5.780
RE PM TY III (W)(12")(DOT)
LF 1,028.000 $1.980 $3.750 $4.000 $5.000 $5.780
RE PM TY III (W)(24")(SLD)
LF 12,531.000 $8.240 $7.500 $8.100 $10.000 $9.560
RE PM TY III (Y)(12")(SLD)
LF 4,790.000 $3.700 $3.500 $3.950 $5.000 $5.780
RE PM TY III (BLK)(6")(SHADOW)
LF 84,710.000 $1.000 $0.800 $0.820 $0.900 $0.850
PAVEMENT SLER (ARROW)
EA 241.000 $22.790 $10.000 $4.000 $25.000 $64.080
PAVEMENT SLER (WORD)
EA 281.000 $29.810 $18.000 $6.000 $25.000 $64.900
PAVEMENT SLER (DBL ARROW)
EA 81.000 $32.570 $28.000 $5.000 $30.000 $66.430
PAVEMENT SLER (UTURN ARROW)
EA 40.000 $32.350 $30.000 $6.000 $35.000 $60.400
PAVEMENT SLER (U-L ARROW)
EA 23.000 $40.000 $35.000 $7.000 $35.000 $60.400
PAVEMENT SLER (YLD TRI)
EA 227.000 $5.000 $4.000 $2.000 $5.000 $60.400
PREFAB PM TY C (W)(ARROW)
EA 241.000 $268.790 $220.000 $196.000 $230.000 $239.080
PREFAB PM TY C (W)(DBL ARROW)
EA 81.000 $437.410 $300.000 $314.000 $435.000 $302.380
PREFAB PM TY C (W)(UTURN ARROW)
EA 40.000 $387.870 $320.000 $324.000 $375.000 $310.030
PREFAB PM TY C (W)(U-LT ARROW)
EA 15.000 $450.000 $350.000 $324.000 $585.000 $310.030
PREFAB PM TY C (W)(WORD)
EA 281.000 $320.110 $260.000 $286.000 $300.000 $279.410
PREFAB PM TY C (W)(36")(YLD TRI)
EA 227.000 $46.820 $40.000 $65.000 $45.000 $127.970
REFL PAV MRKR TY I-A
EA 324.000 $6.560 $5.500 $5.550 $6.000 $6.390
REFL PAV MRKR TY I-C
EA 160.000 $6.540 $5.500 $6.350 $6.000 $6.390
REFL PAV MRKR TY II-A-A
EA 166.000 $6.670 $5.000 $5.500 $6.000 $6.390
REFL PAV MRKR TY II-C-R
EA 6,608.000 $6.650 $4.500 $4.700 $6.000 $6.390
ELIM EXT PM & MRKS (6")
LF 208,691.000 $0.400 $0.480 $0.360 $0.400 $0.560
ELIM EXT PM & MRKS (8")
LF 49,770.000 $0.980 $0.500 $1.200 $0.600 $1.050
ELIM EXT PM & MRKS (12")
LF 12,694.000 $1.560 $1.000 $1.200 $1.500 $3.510
ELIM EXT PM & MRKS (24")
LF 12,531.000 $3.470 $2.000 $2.750 $3.000 $6.570
ELIM EXT PM & MRKS (ARROW)
EA 241.000 $43.080 $50.000 $40.000 $70.000 $100.220
ELIM EXT PM & MRKS (DBL ARROW)
EA 81.000 $52.150 $65.000 $55.000 $70.000 $120.620
ELIM EXT PM & MRKS (UTURN ARROW)
EA 40.000 $44.800 $75.000 $69.000 $80.000 $100.220
ELIM EXT PM & MRKS (UTRN/LT ARR)
EA 15.000 $70.200 $75.000 $69.000 $80.000 $118.220
ELIM EXT PM & MRKS (WORD)
EA 281.000 $51.220 $60.000 $46.000 $70.000 $100.220
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 227.000 $15.000 $25.000 $33.000 $30.000 $52.220
PAV SURF PREP FOR MRK (6")
LF 208,691.000 $0.030 $0.010 $0.020 $0.010 $0.120
PAV SURF PREP FOR MRK (8")
LF 49,773.000 $0.050 $0.050 $0.080 $0.020 $0.230
PAV SURF PREP FOR MRK (12")
LF 14,628.000 $0.170 $0.150 $0.280 $0.250 $1.630
PAV SURF PREP FOR MRK (24")
LF 12,531.000 $0.690 $0.500 $0.490 $0.500 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 241.000 $15.870 $10.000 $11.750 $10.000 $28.150
PAV SURF PREP FOR MRK (DBL ARROW)
EA 81.000 $10.770 $20.000 $16.500 $10.000 $28.150
PAV SURF PREP FOR MRK (UTURN ARR)
EA 40.000 $10.930 $25.000 $16.500 $10.000 $28.150
PAV SURF PREP FOR MRK (U/LT ARROW)
EA 15.000 $35.000 $25.000 $16.500 $10.000 $28.150
PAV SURF PREP FOR MRK (WORD)
EA 281.000 $15.990 $15.000 $13.750 $10.000 $28.150
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 227.000 $5.250 $4.000 $5.550 $10.000 $18.770
MLTPLY PV MK W/WTY (W) (6") (SLD)
LF 15,627.000 $0.840 $0.700 $0.620 $0.800 $1.100
MLTPLY PV MK W/WTY (W) (6") (BRK)
LF 84,710.000 $0.840 $0.750 $0.820 $0.800 $1.100
MLTPLY PV MK W/WTY (W) (6") (DOT)
LF 4,069.000 $1.680 $0.950 $1.550 $1.050 $1.100
MLTPLY PV MK W/WTY (Y) (6") (SLD)
LF 19,575.000 $0.840 $0.700 $0.620 $0.800 $1.100
MLTPLY PV MK W/WTY (W) (8") (SLD)
LF 41,325.000 $1.480 $1.450 $1.050 $1.200 $2.000
MLTPLY PV MK W/WTY (W) (8") (DOT)
LF 1,780.000 $3.000 $1.800 $1.350 $1.800 $2.000
MLTPLY PV MK W/WTY (Y) (8") (SLD)
LF 6,665.000 $1.480 $1.450 $3.000 $1.250 $2.000
Totals: $1,092,183.780 $875,958.390 $921,412.590 $998,776.570 $1,360,933.920
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (PART) $2,200.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
Total: $23,200.00