HARRIS FM 1959 (1844-01-029)

Items: 101

County: HARRIS
Length: N/A
Highway: FM 1959
District: HOUSTON
Control Number: 1844-01-029
DBE Goal: 500.0%
Project: STP 2B24(354)VRU
Guaranty: N/A
Time: 130 WORKING DAYS
Engineer's Estimate: $2,958,919.00
Date: 08/02/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$2,958,919.00
$2,826,450.12
Over/Under Est: -4.48% -$132,468.88
Over/Under Est: -3.02% -$89,312.25
Amt Left: 1.53% $43,156.63
Subcontractor Percentage Amount
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC 14.91% $423,378.95
A. SANCHEZ TRUCKING 5.28% $149,928.96
TRAFFIC SIGNS & LINES, LLC 3.75% $106,483.64
D. SOLIS TRUCKING, INC. 2.85% $80,927.57
C & C TRAFFIC CONTROL 0.49% $13,913.86
SEMARCK LANDSCAPE SERVICES, INC. 0.48% $13,629.91
PRV SERVICES, INC. 0.25% $7,098.91
CURB PLANET INC. 0.13% $3,691.43
Total: 28.14% $799,053.23

Bid Items & Bid Tabulations

101 Total 0 of 101
HARRIS  |  FM 1959  |  HOUSTON  |  1844-01-029  |  08/02/2024  |  $2,958,919.00  |  STP 2B24(354)VRU  |  HAZARD ELIM & SAFETY  |  130 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SER CONSTRUCTION PARTNERS, LLC
ENVIRONMENTAL ALLIES, INC.
PREPARING ROW
STA 55.000 $1,600.000 $3,000.000 $6,000.000
REMOVING CONC (DRIVEWAYS)
SY 711.000 $40.000 $17.600 $25.000
REMOVING CONC (CURB)
LF 502.000 $10.000 $15.500 $5.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 452.000 $33.000 $11.800 $8.000
REMOVING CONC (PAVERS)
SY 54.000 $50.000 $17.900 $40.000
REMOVING STAB BASE & ASPH PAV (10"-12")
SY 4,587.000 $25.000 $23.100 $8.000
EXCAVATION (ROADWAY)
CY 1,574.000 $40.000 $21.900 $32.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 787.000 $38.000 $43.400 $35.000
BLOCK SODDING
SY 2,012.000 $8.000 $6.200 $9.000
BROADCAST SEED (TEMP) (WARM)
SY 156.000 $5.000 $0.200 $1.000
FERTILIZER
AC 0.450 $3,000.000 $977.500 $1,750.000
VEGETATIVE WATERING
MG 52.000 $50.000 $31.600 $100.000
SALV, HAUL & STKPL RCL APH PV (2 TO 4")
SY 4,587.000 $5.000 $13.900 $4.000
STRUCT EXCAV
CY 127.000 $90.000 $15.500 $75.000
CEM STABIL BKFL
CY 1,236.000 $190.000 $62.100 $100.000
CUT & RESTORING PAV
SY 16.000 $65.000 $425.900 $250.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 101.000 $250.000 $339.300 $400.000
DRILL SHAFT (TRF SIG POLE) (42 IN)
LF 22.000 $300.000 $488.800 $500.000
RETAINING WALL (CAST - IN - PLACE)
SF 1,946.000 $75.000 $66.300 $115.000
RIPRAP (CONC) (CL B) (4")
CY 25.000 $100.000 $600.900 $900.000
STR STEEL (MISC NON - BRIDGE)
LB 1,435.000 $25.000 $22.100 $20.000
RAIL (HANDRAIL)(TY D)
LF 208.000 $140.000 $157.800 $140.000
RAIL (HANDRAIL)(TY F)
LF 117.000 $140.000 $157.000 $190.000
RC PIPE (CL III)(18 IN)
LF 14.000 $200.000 $200.600 $150.000
RC PIPE (CL III)(24 IN)
LF 150.000 $235.000 $160.200 $150.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $8,500.000 $3,151.000 $8,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $5,500.000 $2,329.000 $3,000.000
REMOV STR (PIPE)
LF 71.000 $60.000 $31.700 $45.000
MOBILIZATION
LS 1.000 $269,500.000 $280,000.000 $221,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $20,500.000 $5,490.900 $15,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 152.000 $50.000 $27.500 $33.000
CONSTRUCTION EXITS (REMOVE)
SY 152.000 $35.000 $7.500 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 444.000 $6.000 $4.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 444.000 $3.000 $1.200 $1.500
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 48.000 $10.000 $6.200 $12.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 268.000 $10.000 $7.200 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 316.000 $5.000 $3.000 $5.000
CONC CURB (MONO) (TY II)
LF 166.000 $12.000 $10.000 $7.500
DRIVEWAYS (CONC)
SY 470.000 $100.000 $100.000 $60.000
DRIVEWAYS (ACP)
SY 4,233.000 $70.000 $85.000 $58.000
DRIVEWAYS (CONC) (FAST TRACK)
SY 240.000 $120.000 $120.000 $165.000
CONC SIDEWALKS (4")
SY 5,281.000 $90.000 $94.250 $60.000
CURB RAMPS (TY 1)
EA 4.000 $2,800.000 $2,803.300 $2,000.000
CURB RAMPS (TY 5)
EA 6.000 $3,600.000 $4,363.100 $2,400.000
CURB RAMPS (TY 7)
EA 10.000 $2,800.000 $2,822.800 $2,100.000
CURB RAMPS (TY 10)
EA 6.000 $3,300.000 $2,765.200 $1,500.000
CURB RAMPS (TY 21)
EA 3.000 $3,250.000 $2,930.500 $3,000.000
CONDT (PVC) (SCH 80) (2")
LF 510.000 $11.000 $15.800 $25.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 165.000 $17.000 $23.900 $42.000
CONDT (PVC) (SCH 80) (3")
LF 275.000 $17.000 $28.200 $40.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 450.000 $20.000 $28.200 $40.000
CONDT (PVC) (SCH 80) (4")
LF 45.000 $22.000 $46.900 $38.000
ELEC CONDR (NO.8) BARE
LF 1,435.000 $2.000 $2.400 $2.250
ELEC CONDR (NO.4) INSULATED
LF 740.000 $3.000 $3.500 $3.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 1,180.000 $3.000 $3.700 $3.500
GROUND BOX TY D (162922)W/APRON
EA 13.000 $1,080.000 $1,420.300 $1,800.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 2.000 $5,800.000 $5,951.300 $10,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 37.000 $635.000 $522.900 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $885.000 $693.000 $950.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $975.000 $856.200 $1,250.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,150.000 $804.900 $1,300.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,175.000 $973.000 $2,000.000
REMOVE SM RD SN SUP&AM
EA 49.000 $160.000 $69.000 $150.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,404.000 $7.500 $9.500 $12.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $260.000 $316.300 $400.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $325.000 $437.000 $425.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 10.000 $60.000 $74.800 $100.000
ELIM EXT PAV MRK & MRKS (12")
LF 662.000 $1.500 $1.200 $2.750
ELIM EXT PAV MRK & MRKS (24")
LF 418.000 $3.000 $2.300 $4.000
PAV SURF PREP FOR MRK (24")
LF 2,048.000 $1.000 $1.200 $1.250
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $25.000 $10.400 $40.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $30.000 $10.400 $40.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 10.000 $5.000 $11.500 $15.000
INSTALL HWY TRF SIG (SYSTEM)
EA 2.000 $31,000.000 $46,804.400 $52,000.000
VEH SIG SEC (12")LED(GRN)
EA 16.000 $210.000 $339.300 $315.000
VEH SIG SEC (12")LED(GRN ARW)
EA 8.000 $220.000 $339.300 $350.000
VEH SIG SEC (12")LED(YEL)
EA 16.000 $210.000 $339.300 $325.000
VEH SIG SEC (12")LED(YEL ARW)
EA 8.000 $227.000 $339.300 $350.000
VEH SIG SEC (12")LED(RED)
EA 16.000 $210.000 $339.300 $325.000
VEH SIG SEC (12")LED(RED ARW)
EA 8.000 $210.000 $339.300 $365.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 24.000 $187.000 $270.300 $175.000
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
LF 2,780.000 $2.000 $2.100 $3.500
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 2,780.000 $2.500 $2.400 $3.750
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 5,100.000 $3.000 $2.900 $4.000
INS TRF SIG PL AM (S)1 ARM(24')
EA 1.000 $8,900.000 $10,459.300 $13,000.000
INS TRF SIG PL AM (S)1 ARM(28')
EA 1.000 $10,000.000 $11,183.800 $12,500.000
INS TRF SIG PL AM(S)1 ARM(36')
EA 2.000 $10,500.000 $12,937.500 $15,000.000
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 2.000 $12,500.000 $15,007.500 $20,000.000
INS TRF SIG PL AM(S)1 ARM(44')LUM
EA 1.000 $13,700.000 $15,640.000 $21,000.000
INS TRF SIG PL AM(S)1 ARM(50')LUM
EA 1.000 $22,250.000 $37,921.300 $37,500.000
PED POLE ASSEMBLY
EA 12.000 $1,500.000 $2,788.800 $3,000.000
PED DETECT PUSH BUTTON (APS)
EA 16.000 $900.000 $1,017.800 $1,000.000
PED DETECTOR CONTROLLER UNIT
EA 2.000 $2,300.000 $4,019.300 $4,250.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 6,736.000 $20.000 $8.600 $8.250
TREE PROTECTION
EA 5.000 $1,000.000 $575.000 $900.000
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 644.000 $8.500 $12.700 $15.000
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 2.000 $7,400.000 $10,114.300 $9,250.000
TMA (STATIONARY)
DAY 130.000 $340.000 $398.100 $450.000
VIVDS PROSR SYS (INSTALL ONLY)
EA 2.000 $730.000 $776.300 $1,650.000
VIVDS CAM ASSY (INSTALL ONLY)
EA 8.000 $300.000 $776.300 $1,650.000
VIVDS CABLING (INSTALL ONLY)
LF 1,720.000 $2.000 $2.100 $2.250
Totals: $2,958,919.000 $2,826,450.125 $2,869,606.750