HARRIS FM 529 (1006-01-080)

Items: 31

County: HARRIS
Length: N/A
Highway: FM 529
District: HOUSTON
Control Number: 1006-01-080
DBE Goal: N/A
Project: C 1006-1-80
Guaranty: N/A
Time: 30 WORKING DAYS
Engineer's Estimate: $300,600.56
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENT
Mail/Deliver Bids To: N/A
HAMOON BAHRAMI
BRETT MCLEOD
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$300,600.56
$355,217.20
Over/Under Est: 18.17% $54,616.64
Over/Under Est: 23.01% $69,163.39
Amt Left: 4.1% $14,546.75
Over/Under Est: 36.42% $109,469.89
Amt Left: 15.44% $54,853.25
Delta: -10.90% -$40,306.50

Bid Items & Bid Tabulations

31 Total 0 of 31
HARRIS  |  FM 529  |  HOUSTON  |  1006-01-080  |  02/02/2023  |  $300,600.56  |  C 1006-1-80  |  INTERS IMPRV  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MAIN LANE INDUSTRIES LTD.
FORDE CONSTRUCTION COMPANY, INC.
TEXAS MATERIALS GROUP, INC.
REMOVING STAB BASE AND ASPH PAV (13")
SY 125.000 $13.000 $20.000 $50.000 $82.000
SUBGRADE WIDENING (DENS CONT)
STA 11.400 $1,250.000 $3,000.000 $1,600.000 $2,300.000
BACKFILL (TY A)
STA 11.400 $207.000 $500.000 $1,200.000 $1,400.000
ASPHALT STAB BASE (GR 2)(PG 64)
TON 489.000 $128.000 $150.000 $140.000 $148.000
ASPH (AC-20-5TR)
GAL 204.000 $5.000 $9.000 $21.000 $4.200
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 5.000 $133.000 $400.000 $1,070.000 $990.000
RC PIPE (CL III)(18 IN)
LF 7.000 $165.000 $500.000 $1,260.000 $551.000
MOBILIZATION
LS 1.000 $27,304.940 $35,000.000 $31,000.000 $72,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $7,500.000 $7,800.000 $850.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $186.550 $900.000 $940.000 $602.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $5,263.400 $6,000.000 $7,400.000 $7,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $850.000 $905.000 $1,025.000
REMOVE SM RD SN SUP&AM
EA 2.000 $100.000 $125.000 $133.000 $150.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 55.000 $8.000 $9.000 $10.000 $11.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 3,270.000 $0.600 $1.000 $1.050 $1.200
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 3,115.000 $0.550 $1.000 $1.050 $1.200
REFL PAV MRKR TY II-A-A
EA 38.000 $6.000 $8.000 $8.500 $9.650
ELIM EXT PAV MRK & MRKS (6")
LF 5,245.000 $0.450 $0.350 $0.400 $0.450
ELIM EXT PAV MRK & MRKS (24")
LF 45.000 $3.000 $1.000 $1.100 $1.200
PAV SURF PREP FOR MRK (6")
LF 6,385.000 $0.050 $0.020 $0.020 $0.020
PAV SURF PREP FOR MRK (24")
LF 55.000 $0.300 $0.250 $0.300 $0.300
REMOVING TRAFFIC SIGNALS
EA 1.000 $2,650.000 $2,500.000 $3,900.000 $2,700.000
TEMP TRAF SIGNALS
EA 1.000 $45,000.000 $59,000.000 $50,000.000 $70,500.000
REMOVE RDSD FLASH BEACON ASSEMBLY
EA 4.000 $766.780 $400.000 $340.000 $422.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 4.000 $7,500.000 $6,000.000 $8,700.000 $6,900.000
D-GR HMA TY-D SAC-A PG76-22
TON 87.500 $185.000 $250.000 $194.000 $215.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 70.000 $220.000 $250.000 $238.000 $238.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $80.000 $60.000 $170.000 $164.000
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 1.000 $6,500.000 $8,500.000 $9,700.000 $9,600.000
TMA (MOBILE OPERATION)
DAY 60.000 $270.000 $100.000 $170.000 $6.000
VIVDS TEMPORARY
EA 1.000 $15,000.000 $19,500.000 $24,000.000 $23,000.000
Totals: $300,600.560 $355,217.200 $369,763.950 $410,070.450