County: HARRIS Highway: FM 865 Date: 08/07/2019 (5 years ago) Engineer's Estimate: $148,345 Control Number: 0976-01-040
Project: STP 1902(324)HES District: HOUSTON Time: 40 WORKING DAYS Type: ADD LEFT TURN LANE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $148,344.64
MAIN LANE INDUSTRIES LTD.   $189,822.20 1
27.96% | $41,477.56
FNH CONSTRUCTION, LLC   $227,662.00 2
53.47% | $79,317.36
19.93% | $37,839.80

Bid Items

Items: 37, 0 filtered
HARRIS FM 865  |  HOUSTON  |  0976-01-040  |  08/07/2019  |  $148,345  |  STP 1902(324)HES  |  ADD LEFT TURN LANE  |  40 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MAIN LANE INDUSTRIES LTD. FNH CONSTRUCTION, LLC
100 6008 PREPARING ROW (TREE) (0" TO 6" DIA) EA 5.000 $1,000.000 $750.000 $2,000.000
104 6011 REMOVING CONC (MEDIANS) SY 7.000 $30.000 $50.000 $30.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 91.000 $40.000 $50.000 $30.000
104 6021 REMOVING CONC (CURB) LF 430.000 $10.000 $5.000 $30.000
104 6036 REMOVING CONC (SIDEWALK OR RAMP) SY 38.000 $25.000 $20.000 $30.000
105 6026 REMOVE STAB BASE & ASPH PAV (13"-18") SY 93.000 $20.000 $20.000 $30.000
105 6044 REMOVING STAB BASE AND ASPH PAV (10") SY 104.000 $15.000 $20.000 $30.000
110 6001 EXCAVATION (ROADWAY) CY 60.000 $75.000 $100.000 $30.000
260 6006 LIME TRT (EXST MATL) (6") SY 267.000 $10.000 $8.000 $10.000
260 6012 LIME(HYD,COM OR QK)(SLRY)OR QK(DRY) TON 4.500 $300.000 $200.000 $250.000
276 6093 CM TRT(PT MX)(CL N)(TYA)(GR1-2)(FN POS) CY 100.000 $150.000 $250.000 $100.000
316 6405 ASPH (AC-20-5TR OR AC-20XP) GAL 95.000 $20.000 $5.000 $10.000
316 6434 AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B) CY 2.500 $500.000 $200.000 $1,000.000
340 6135 D-GR HMA(SQ) TY-D SAC-A PG76-22 TON 20.000 $400.000 $500.000 $200.000
340 6138 D-GR HMA(SQ) TY-D PG76-22 TON 20.000 $300.000 $500.000 $200.000
500 6001 MOBILIZATION LS 1.000 $9,122.240 $19,000.000 $25,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $8,000.000 $15,000.000 $8,500.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 49.000 $30.000 $10.000 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 49.000 $10.000 $2.000 $9.000
530 6004 DRIVEWAYS (CONC) SY 91.000 $81.000 $300.000 $125.000
531 6001 CONC SIDEWALKS (4") SY 32.000 $75.000 $250.000 $60.000
531 6010 CURB RAMPS (TY 7) EA 2.000 $2,500.000 $4,000.000 $2,500.000
536 6001 CONC MEDIAN LF 261.000 $50.000 $75.000 $125.000
644 6076 REMOVE SM RD SN SUP&AM EA 1.000 $400.000 $200.000 $650.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 108.000 $2.200 $3.000 $6.000
666 6178 REFL PAV MRK TY II (W) 8" (SLD) LF 108.000 $1.000 $1.000 $6.000
666 6214 REFL PAV MRK TY II (Y) 24" (SLD) LF 261.000 $3.000 $3.000 $20.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 1.000 $500.000 $255.000 $350.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 $500.000 $295.000 $350.000
672 6007 REFL PAV MRKR TY I-C EA 6.000 $9.000 $25.000 $15.000
678 6004 PAV SURF PREP FOR MRK (8") LF 108.000 $0.850 $0.500 $6.000
678 6008 PAV SURF PREP FOR MRK (24") LF 259.000 $2.000 $0.800 $20.000
678 6009 PAV SURF PREP FOR MRK (ARROW) EA 1.000 $25.000 $30.000 $350.000
678 6016 PAV SURF PREP FOR MRK (WORD) EA 1.000 $28.000 $30.000 $350.000
678 6033 PAV SURF PREP FOR MRK (RPM) EA 6.000 $1.000 $2.000 $500.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 80.000 $100.000 $50.000 $150.000
6185 6002 TMA (STATIONARY) DAY 80.000 $300.000 $5.000 $550.000
Totals: $148,344.64 $189,822.20 $227,662.00