County: HARRIS Highway: CS Date: 09/06/2023 (1 year ago) Engineer's Estimate: $800,384 Control Number: 0912-72-405
Project: BR 2021(347) District: HOUSTON Time: 142 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $800,384.35
JOHN REED AND COMPANY, LLC   $745,291.25 1
-6.88% | -$55,093.10
ISI CONTRACTING, INC.   $812,315.55 2
1.49% | $11,931.20
8.99% | $67,024.30
MAIN LANE INDUSTRIES LTD.   $859,095.00 3
7.34% | $58,710.65
15.27% | $113,803.75
5.76% | $46,779.45
HARPER BROTHERS CONSTRUCTION LLC   $1,209,712.50 4
51.14% | $409,328.15
62.31% | $464,421.25
40.81% | $350,617.50
Subcontractor Percentage Amount
TRAFFIC SIGNS & LINES, LLC 1.68% $12,520.89
MESA ROD BUSTERS, INC. 0.81% $6,036.86
Total: 2.49% $18,557.75

Bid Items

Items: 62, 0 filtered
HARRIS CS  |  HOUSTON  |  0912-72-405  |  09/06/2023  |  $800,384  |  BR 2021(347)  |  BRIDGE REPL  |  142 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JOHN REED AND COMPANY, LLC ISI CONTRACTING, INC. MAIN LANE INDUSTRIES LTD. HARPER BROTHERS CONSTRUCTION LLC
100 6002 PREPARING ROW STA 1.950 $21,000.000 $8,000.000 $1,000.000 $12,000.000 $9,500.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 105.000 $16.000 $6.000 $8.000 $15.000 $5.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 250.000 $10.000 $5.000 $4.000 $5.000 $3.000
105 6008 REMOVING STAB BASE AND ASPH PAV (6") SY 374.000 $8.000 $5.000 $21.000 $13.000 $5.000
110 6001 EXCAVATION (ROADWAY) CY 213.000 $30.000 $40.000 $18.000 $22.000 $25.000
110 6002 EXCAVATION (CHANNEL) CY 140.000 $29.000 $30.000 $18.000 $40.000 $50.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 117.000 $32.000 $60.000 $30.000 $15.000 $25.000
132 6035 EMBANK(FINAL)(DC)(TY E)(CSBE) CY 164.000 $95.000 $70.000 $84.000 $90.000 $100.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 22.000 $30.000 $40.000 $49.000 $80.000 $25.000
162 6002 BLOCK SODDING SY 299.000 $5.000 $4.000 $15.000 $6.000 $10.000
166 6001 FERTILIZER AC 0.070 $1,500.000 $500.000 $1,840.000 $800.000 $3,000.000
168 6001 VEGETATIVE WATERING MG 9.000 $35.000 $30.000 $32.000 $35.000 $100.000
260 6006 LIME TRT (EXST MATL) (6") SY 304.000 $5.000 $8.000 $29.000 $8.000 $1.000
260 6012 LIME(HYD,COM OR QK)(SLRY)OR QK(DRY) TON 5.000 $285.000 $400.000 $335.000 $300.000 $100.000
400 6005 CEM STABIL BKFL CY 20.000 $213.000 $70.000 $55.000 $80.000 $80.000
400 6009 CEMENT STAB BACKFILL (INLET OR MH) CY 35.000 $50.000 $70.000 $55.000 $80.000 $80.000
402 6001 TRENCH EXCAVATION PROTECTION LF 50.000 $6.000 $2.000 $25.000 $2.000 $5.000
416 6003 DRILL SHAFT (30 IN) LF 360.000 $210.000 $264.000 $365.000 $560.000 $615.000
420 6013 CL C CONC (ABUT) CY 31.600 $1,400.000 $1,500.000 $1,550.000 $1,500.000 $2,750.000
422 6005 REINF CONC SLAB (BOX BEAM) SF 1,971.000 $25.000 $25.000 $23.000 $20.000 $40.000
422 6013 BRIDGE SIDEWALK SF 342.000 $58.000 $28.000 $66.000 $20.000 $35.000
422 6015 APPROACH SLAB CY 57.000 $755.000 $800.000 $900.000 $750.000 $1,250.000
422 6023 SHEAR KEY CY 11.000 $500.000 $200.000 $205.000 $250.000 $1,250.000
425 6001 PRESTR CONC BOX BEAM (4B20) LF 338.890 $235.000 $325.000 $215.000 $270.000 $400.000
425 6002 PRESTR CONC BOX BEAM (5B20) LF 112.960 $235.000 $325.000 $240.000 $270.000 $400.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 94.000 $200.000 $120.000 $265.000 $220.000 $250.000
442 6007 STR STEEL (MISC NON - BRIDGE) LB 178.000 $18.000 $25.000 $37.000 $35.000 $40.000
450 6006 RAIL (TY T223) LF 77.000 $150.000 $125.000 $164.000 $180.000 $350.000
450 6032 RAIL (TY C223) LF 67.000 $185.000 $145.000 $253.000 $210.000 $425.000
454 6021 TYPE A JOINT LF 58.000 $75.000 $25.000 $93.000 $5.000 $25.000
464 6003 RC PIPE (CL III)(18 IN) LF 50.000 $100.000 $90.000 $120.000 $140.000 $250.000
465 6173 MANH (COMPL)(TY A) EA 2.000 $8,750.000 $8,000.000 $9,100.000 $12,000.000 $25,000.000
465 6175 INLET (COMPL)(CURB)(TY C) EA 2.000 $6,600.000 $5,000.000 $5,000.000 $8,000.000 $15,000.000
465 6177 INLET (COMPL)(TY AZ2G) EA 1.000 $10,300.000 $6,000.000 $11,500.000 $13,000.000 $22,500.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $33,000.000 $70,000.000 $24,000.000 $40,000.000 $65,000.000
500 6001 MOBILIZATION LS 1.000 $68,281.000 $70,000.000 $77,000.000 $85,000.000 $50,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $8,000.000 $1,000.000 $800.000 $650.000 $5,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 105.000 $70.000 $50.000 $65.000 $40.000 $100.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 105.000 $20.000 $8.000 $22.000 $10.000 $15.000
506 6034 CONSTRUCTION PERIMETER FENCE LF 171.000 $7.000 $3.000 $27.000 $25.000 $10.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 340.000 $4.000 $3.000 $7.000 $3.000 $10.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 340.000 $1.000 $1.000 $2.000 $1.000 $2.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 51.000 $5.000 $10.000 $10.000 $7.000 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 51.000 $1.000 $2.000 $10.000 $1.000 $2.000
529 6008 CONC CURB & GUTTER (TY II) LF 141.000 $42.000 $36.000 $115.000 $35.000 $75.000
530 6004 DRIVEWAYS (CONC) SY 87.000 $105.000 $90.000 $302.000 $100.000 $200.000
531 6001 CONC SIDEWALKS (4") SY 61.000 $100.000 $95.000 $110.000 $75.000 $150.000
550 6003 CHAIN LINK FENCE (REMOVE) LF 40.000 $10.000 $10.000 $25.000 $10.000 $5.000
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $70.000 $100.000 $102.000 $150.000 $50.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 5.000 $30.000 $25.000 $25.000 $25.000 $20.000
658 6080 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND EA 6.000 $60.000 $29.000 $30.000 $30.000 $60.000
658 6102 INSTL OM ASSM (OM-3L)(WFLX)SRF)SRF EA 2.000 $225.000 $235.000 $240.000 $235.000 $195.000
658 6104 INSTL OM ASSM (OM-3R)(WFLX)SRF)SRF EA 1.000 $225.000 $235.000 $240.000 $235.000 $195.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 391.000 $0.600 $2.000 $2.000 $2.250 $2.250
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 391.000 $0.600 $2.000 $2.000 $2.250 $2.250
672 6009 REFL PAV MRKR TY II-A-A EA 10.000 $10.000 $20.000 $20.000 $20.000 $25.000
678 6002 PAV SURF PREP FOR MRK (6") LF 782.000 $0.200 $1.000 $1.000 $0.500 $0.500
3076 6007 D-GR HMA TY-B SAC-B PG70-22 TON 58.000 $220.000 $180.000 $306.000 $225.000 $250.000
3076 6066 TACK COAT GAL 54.000 $13.000 $5.000 $7.000 $5.500 $6.500
3076 6074 D-GR HMA TY-C SAC-B PG70-22 (EXEMPT) TON 58.000 $300.000 $180.000 $280.000 $225.000 $270.000
3076 6076 D-GR HMA TY-D SAC-A PG70-22 (EXEMPT) TON 29.000 $365.000 $180.000 $377.000 $300.000 $365.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 180.000 $65.000 $40.000 $90.000 $60.000 $75.000
Totals: $800,384.35 $745,291.25 $812,315.55 $859,095.00 $1,209,712.50