Show Job Controls
Bid Cobra

HARRIS CS (0912-72-352)

Items: 65

County: HARRIS
Length: N/A
Highway: CS
District: HOUSTON
Control Number: 0912-72-352
DBE Goal: N/A
Project: BR 2019(251)
Guaranty: N/A
Time: 101 WORKING DAYS
Engineer's Estimate: $509,882.40
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (2)
E
Engineer's Estimate
$509,882.40
Over/Under Est: 17.64% $89,918.10
Over/Under Est: 35.74% $182,211.23
Amt Left: 15.39% $92,293.13

Bid Items & Bid Tabulations

65 Total 0 of 65
HARRIS  |  CS  |  HOUSTON  |  0912-72-352  |  08/05/2021  |  $509,882.40  |  BR 2019(251)  |  REPLACE BRIDGE AND APPROACHES  |  101 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ARANDA BROTHERS CONSTRUCTION CO., INC.
MILLIS DEVELOPMENT AND CONSTRUCTION, LLC
PREPARING ROW
STA 3.450 $2,800.000 $2,000.000 $3,641.100
REMOVING STAB BASE AND ASPH PAV (6")
SY 884.000 $3.000 $10.000 $7.630
EXCAVATION (ROADWAY)
CY 288.000 $7.500 $8.000 $7.310
EXCAVATION (CHANNEL)
CY 92.000 $10.500 $8.000 $18.290
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 565.000 $8.500 $12.000 $18.020
EMBANK(FINAL)(DC)(TY E)(CSBE)
CY 308.000 $34.500 $60.000 $65.190
FURNISHING AND PLACING TOPSOIL
CY 52.000 $1.500 $10.000 $78.710
BLOCK SODDING
SY 926.000 $3.200 $5.500 $5.720
STRAW OR HAY MULCH
SY 926.000 $0.190 $0.500 $0.690
BROADCAST SEED (TEMP) (WARM)
SY 463.000 $0.140 $0.500 $0.690
DRILL SEED (TEMP)(WARM OR COOL)
SY 463.000 $0.100 $0.500 $2.540
FERTILIZER
AC 0.200 $650.000 $2,500.000 $1,143.740
VEGETATIVE WATERING
MG 23.000 $17.000 $80.000 $25.440
LIME (HYDRATED OR COMMERCIAL)(SLURRY)
TON 13.000 $180.000 $190.000 $222.070
LIME TRT (SUBGRADE)(6")
SY 959.000 $2.300 $5.000 $12.190
CONC PAV (JOINT REINF) (8")
SY 842.000 $50.000 $65.000 $74.470
CEM STABIL BKFL
CY 126.000 $50.000 $60.000 $71.820
CEMENT STAB BACKFILL (INLET OR MH)
CY 17.000 $50.000 $60.000 $71.820
DRILL SHAFT (24 IN)
LF 252.000 $110.000 $185.000 $159.000
CL C CONC (ABUT)
CY 22.400 $839.000 $950.000 $1,030.850
REINF CONC SLAB (SLAB BEAM)
SF 1,466.000 $14.000 $12.000 $21.730
BRIDGE SIDEWALK
SF 328.000 $9.500 $7.000 $11.400
APPROACH SLAB
CY 53.000 $450.000 $470.000 $526.820
PRESTR CONC SLAB BEAM (4SB15)
LF 133.500 $150.000 $230.000 $255.990
PRESTR CONC SLAB BEAM (5SB15)
LF 178.000 $150.000 $230.000 $340.260
RIPRAP (STONE PROTECTION)(18 IN)
CY 373.000 $89.000 $200.000 $134.620
RIPRAP (MOW STRIP)(4 IN)
CY 5.000 $450.000 $400.000 $520.990
STR STEEL (MISC NON - BRIDGE)
LB 172.000 $7.200 $30.000 $22.790
RAIL (TY T223)
LF 63.000 $120.000 $90.000 $141.510
RAIL (TY C223)
LF 63.000 $125.000 $150.000 $192.390
ARMOR JOINT
LF 57.000 $85.000 $120.000 $105.210
CMP (GAL STL 24 IN)
LF 40.000 $70.000 $75.000 $73.140
CMP (GAL STL 30 IN)
LF 20.000 $75.000 $85.000 $91.160
RC PIPE (CL III)(24 IN)
LF 108.000 $70.000 $90.000 $79.770
RC PIPE (CL III)(30 IN)
LF 136.000 $85.000 $120.000 $99.380
MANH (COMPL)(PRM)(48IN)
EA 3.000 $4,500.000 $4,100.000 $5,322.260
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $1,100.000 $1,850.000 $5,048.780
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $2,500.000 $2,150.000 $6,126.800
REMOV STR (PIPE)
LF 94.000 $17.500 $10.000 $18.020
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $18,000.000 $20,000.000 $13,589.200
MOBILIZATION
LS 1.000 $39,995.040 $45,000.000 $81,938.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $2,000.000 $1,659.960
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 95.000 $30.000 $30.000 $44.520
ROCK FILTER DAMS (REMOVE)
LF 95.000 $10.000 $10.000 $10.870
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $25.000 $25.000 $22.790
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $10.000 $10.000 $6.360
CONSTRUCTION PERIMETER FENCE
LF 120.000 $2.600 $25.000 $1.910
TEMP SEDMT CONT FENCE (INSTALL)
LF 517.000 $2.500 $4.000 $1.910
TEMP SEDMT CONT FENCE (REMOVE)
LF 517.000 $0.700 $1.500 $0.850
CONC CURB (TY II)
LF 726.000 $15.000 $6.000 $15.370
DRIVEWAYS (CONC)
SY 130.000 $69.000 $75.000 $78.710
CONC SIDEWALKS (6")
SY 30.000 $57.000 $70.000 $69.960
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $20.000 $35.000 $32.860
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,200.000 $1,800.000 $1,742.640
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,100.000 $1,800.000 $1,724.620
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,400.000 $3,100.000 $3,841.440
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $650.000 $300.000 $830.510
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $650.000 $510.000 $804.010
REMOVE SM RD SN SUP&AM
EA 3.000 $85.000 $90.000 $127.200
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 5.000 $22.000 $25.000 $25.440
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 4.000 $135.000 $50.000 $159.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 690.000 $0.300 $2.000 $1.590
REFL PAV MRK TY II (Y) 6" (SLD)
LF 690.000 $0.300 $2.000 $1.590
REFL PAV MRKR TY II-A-A
EA 9.000 $3.500 $11.000 $15.370
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 210.000 $45.000 $70.000 $65.460
Totals: $509,882.400 $599,800.500 $692,093.648