HARRIS VA (0912-00-710)
Items: 73
County: HARRIS
Length: N/A
Highway: VA
District: HOUSTON
Control Number: 0912-00-710
DBE Goal: 0.0%
Project: C 912-00-710
Guaranty: N/A
Time: 109 WORKING DAYS
Engineer's Estimate: $3,023,011.53
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,023,011.53 | |||
| $2,390,507.42 |
-20.92%
-$632,504.11
|
|||
| $2,438,899.93 |
-19.32%
-$584,111.60
|
2.02%
$48,392.51
|
||
| $2,750,310.32 |
-9.02%
-$272,701.21
|
15.05%
$359,802.90
|
-12.77%
-$311,410.39
|
|
| $2,941,543.95 |
-2.69%
-$81,467.58
|
23.05%
$551,036.53
|
-6.95%
-$191,233.63
|
|
| $3,161,639.62 |
4.59%
$138,628.09
|
32.26%
$771,132.20
|
-7.48%
-$220,095.67
|
E
Engineer's Estimate
$3,023,011.53
1
Awarded
$2,390,507.42
Over/Under Est:
-20.92%
-$632,504.11
$2,438,899.93
Over/Under Est:
-19.32%
-$584,111.60
Amt Left:
2.02%
$48,392.51
$2,750,310.32
Over/Under Est:
-9.02%
-$272,701.21
Amt Left:
15.05%
$359,802.90
Delta:
-12.77%
-$311,410.39
$2,941,543.95
Over/Under Est:
-2.69%
-$81,467.58
Amt Left:
23.05%
$551,036.53
Delta:
-6.95%
-$191,233.63
$3,161,639.62
Over/Under Est:
4.59%
$138,628.09
Amt Left:
32.26%
$771,132.20
Delta:
-7.48%
-$220,095.67
Bid Items & Bid Tabulations
73
Total
0 of 73