HARRIS SH 249 (0720-03-147)

Items: 39

County: HARRIS
Length: N/A
Highway: SH 249
District: HOUSTON
Control Number: 0720-03-147
DBE Goal: 0.0%
Project: C 720-3-147
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $832,681.00
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$832,681.00
$464,642.33
Over/Under Est: -44.2% -$368,038.67
$548,787.77
Over/Under Est: -34.09% -$283,893.23
Amt Left: 18.11% $84,145.44
Over/Under Est: -29.96% -$249,496.26
Amt Left: 25.51% $118,542.41
Delta: -6.27% -$34,396.97
$661,035.86
Over/Under Est: -20.61% -$171,645.14
Amt Left: 42.27% $196,393.53
Delta: -13.35% -$77,851.12
Over/Under Est: -10.54% -$87,726.62
Amt Left: 60.33% $280,312.05
Delta: -12.70% -$83,918.52

Bid Items & Bid Tabulations

39 Total 0 of 39
HARRIS  |  SH 249  |  HOUSTON  |  0720-03-147  |  08/01/2024  |  $832,681.00  |  C 720-3-147  |  SURF/ROADWAY RESTOR  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE LINES, INC.
BATTERSON, LLP
TRP INFRASTRUCTURE SERVICES, LLC
HIGHWAY 1 LLC
PROFESSIONAL TRAFFIC CONTROL LLC
MOBILIZATION
LS 1.000 $80,000.000 $5,000.000 $5,500.000 $15,000.000 $12,000.000 $124,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $12,449.150 $500.000 $2,500.000 $1,000.000 $100.000 $1.000
PAVEMENT SEALER 6"
LF 224,946.000 $0.100 $0.010 $0.050 $0.100 $0.020 $0.300
PAVEMENT SEALER 8"
LF 7,427.000 $0.300 $0.010 $0.100 $0.130 $0.030 $0.400
PAVEMENT SEALER 24"
LF 12,936.000 $0.730 $0.010 $0.400 $1.050 $0.040 $1.500
PAVEMENT SEALER (ARROW)
EA 138.000 $11.520 $1.000 $8.000 $26.000 $10.000 $30.000
PAVEMENT SEALER (WORD)
EA 73.000 $12.840 $1.000 $8.000 $31.000 $10.000 $40.000
PAVEMENT SEALER (DBL ARROW)
EA 1.000 $14.850 $1.000 $16.000 $37.000 $15.000 $50.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 138.000 $244.120 $225.890 $195.000 $238.000 $340.520 $180.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 1.000 $337.920 $327.320 $310.000 $394.000 $411.660 $320.000
PREFAB PAV MRK TY C (W) (WORD)
EA 73.000 $291.680 $273.910 $250.000 $320.000 $381.960 $300.000
REFL PAV MRKR TY I-C
EA 2,107.000 $6.200 $6.790 $5.500 $5.200 $7.000 $5.240
REFL PAV MRKR TY II-A-A
EA 2,601.000 $6.280 $6.790 $5.500 $5.200 $7.000 $5.240
REFL PAV MRKR TY II-C-R
EA 205.000 $5.510 $6.790 $5.500 $5.200 $7.000 $5.240
ELIM EXT PAV MRK & MRKS (6")
LF 224,946.000 $0.300 $0.190 $0.490 $0.370 $0.370 $0.450
ELIM EXT PAV MRK & MRKS (8")
LF 7,427.000 $0.720 $0.300 $0.810 $1.000 $0.560 $0.700
ELIM EXT PAV MRK & MRKS (12")
LF 11,634.000 $1.400 $1.500 $1.000 $1.600 $2.000 $1.400
ELIM EXT PAV MRK & MRKS (24")
LF 6,369.000 $2.550 $2.000 $2.000 $3.200 $4.000 $3.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 138.000 $52.570 $50.000 $40.000 $38.000 $75.000 $65.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 1.000 $74.300 $50.000 $45.000 $52.000 $75.000 $80.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 73.000 $50.880 $50.000 $40.000 $44.000 $75.000 $70.000
PAV SURF PREP FOR MRK (6")
LF 224,946.000 $0.030 $0.020 $0.010 $0.020 $0.010 $0.010
PAV SURF PREP FOR MRK (8")
LF 7,427.000 $0.070 $0.040 $0.200 $0.060 $0.010 $0.010
PAV SURF PREP FOR MRK (24")
LF 12,936.000 $0.480 $0.920 $0.400 $0.470 $0.010 $0.600
PAV SURF PREP FOR MRK (ARROW)
EA 138.000 $10.050 $20.000 $5.000 $11.500 $10.000 $15.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $37.610 $20.000 $5.000 $16.000 $10.000 $25.000
PAV SURF PREP FOR MRK (WORD)
EA 73.000 $13.740 $20.000 $5.000 $13.250 $10.000 $20.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $102.630 $10.000 $100.000 $52.000 $30.000 $70.000
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 66,600.000 $1.150 $0.620 $0.600 $0.700 $0.780 $0.850
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 35,305.000 $1.390 $0.620 $0.600 $0.820 $0.790 $0.950
MULTIPOLYMER PAV MRK (W)(6")(DOT)
LF 228.000 $3.080 $0.620 $1.000 $1.550 $4.000 $2.400
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 7,427.000 $2.040 $1.430 $2.000 $1.350 $3.000 $1.240
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 11,291.000 $10.550 $8.730 $10.000 $7.300 $10.900 $5.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 76,787.000 $1.250 $0.620 $0.600 $0.700 $0.780 $0.850
MULTIPOLYMER PAV MRK (Y)(6")(BRK)
LF 10,720.000 $1.370 $0.620 $0.600 $0.820 $0.790 $0.950
MULTIPOLYMER PAV MRK (Y)(24")(SLD)
LF 1,645.000 $9.840 $8.700 $10.000 $7.300 $10.900 $5.000
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 35,305.000 $1.470 $0.620 $0.600 $0.850 $0.790 $0.950
TMA (STATIONARY)
DAY 60.000 $209.400 $1.000 $1.000 $5.000 $450.000 $1.000
TMA (MOBILE OPERATION)
HR 30.000 $78.560 $10.000 $1.000 $400.000 $200.000 $124.000
Totals: $832,681.000 $464,642.330 $548,787.770 $583,184.740 $661,035.860 $744,954.380