HARRIS SH 249 (0720-03-147)
Items: 39
County: HARRIS
Length: N/A
Highway: SH 249
District: HOUSTON
Control Number: 0720-03-147
DBE Goal: 0.0%
Project: C 720-3-147
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $832,681.00
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$832,681.00 | |||
| $464,642.33 |
-44.2%
-$368,038.67
|
|||
| $548,787.77 |
-34.09%
-$283,893.23
|
18.11%
$84,145.44
|
||
| $583,184.74 |
-29.96%
-$249,496.26
|
25.51%
$118,542.41
|
-6.27%
-$34,396.97
|
|
| $661,035.86 |
-20.61%
-$171,645.14
|
42.27%
$196,393.53
|
-13.35%
-$77,851.12
|
|
| $744,954.38 |
-10.54%
-$87,726.62
|
60.33%
$280,312.05
|
-12.70%
-$83,918.52
|
E
Engineer's Estimate
$832,681.00
1
Awarded
$464,642.33
Over/Under Est:
-44.2%
-$368,038.67
$548,787.77
Over/Under Est:
-34.09%
-$283,893.23
Amt Left:
18.11%
$84,145.44
$583,184.74
Over/Under Est:
-29.96%
-$249,496.26
Amt Left:
25.51%
$118,542.41
Delta:
-6.27%
-$34,396.97
$661,035.86
Over/Under Est:
-20.61%
-$171,645.14
Amt Left:
42.27%
$196,393.53
Delta:
-13.35%
-$77,851.12
$744,954.38
Over/Under Est:
-10.54%
-$87,726.62
Amt Left:
60.33%
$280,312.05
Delta:
-12.70%
-$83,918.52