Show Job Controls
Bid Cobra

HARRIS IH 45 (0500-03-638)

Items: 42

County: HARRIS
Length: 0.0000 MILES
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-638
DBE Goal: 0.0%
Project: F 2025(373)
Guaranty: $20,000.00
Time: 69 WORKING DAYS
Engineer's Estimate: $1,014,216.21
Date: 01/07/2025 (1 year ago)
Contract Number: 1253029
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00131224
Contract Type: Federal
Project Description: INSTALL PAVEMENT MARKINGS (SL 8 TO ALMEDA GENOA MAINLANES ONLY) AND (ALMEDA GENOA TO IH 610(S) MAINLANES AND FRONTAGE ROADS)
Mail/Deliver Bids To: N/A
JAMAL ELAHI
GAURANG PANDIT
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,014,216.21
Over/Under Est: -7.67% -$77,743.66
$939,806.28
Over/Under Est: -7.34% -$74,409.93
Amt Left: 0.36% $3,333.73
$977,569.08
Over/Under Est: -3.61% -$36,647.13
Amt Left: 4.39% $41,096.53
Delta: -4.02% -$37,762.80
Over/Under Est: 4.2% $42,608.42
Amt Left: 12.85% $120,352.08
Delta: -8.11% -$79,255.55

Bid Items & Bid Tabulations

42 Total 0 of 42
HARRIS  |  IH 45  |  HOUSTON  |  0500-03-638  |  01/07/2025  |  $1,014,216.21  |  F 2025(373)  |  SURF/ROADWAY RESTOR  |  69 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRP INFRASTRUCTURE SERVICES, LLC
STRIPE LINES, INC.
BATTERSON, LLP
PROFESSIONAL TRAFFIC CONTROL LLC
MOBILIZATION
LS 1.000 $47,889.880 $6,500.000 $15,000.000 $10,000.000 $13,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,100.000 $1,000.000 $500.000 $3,500.000 $4,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 69.000 $45.500 $100.000 $15.000 $30.000 $30.000
TMA (STATIONARY)
DAY 69.000 $95.250 $100.000 $15.000 $30.000 $300.000
TMA (MOBILE OPERATION)
HR 60.000 $15.500 $100.000 $150.000 $30.000 $1.000
RE PM TY III (W)(6")(SLD)
LF 152,340.000 $0.650 $0.610 $0.600 $0.700 $0.850
RE PM TY III (W)(6")(BRK)
LF 79,111.000 $0.700 $0.810 $0.600 $0.700 $0.850
RE PM TY III (W)(6")(DOT)
LF 1,621.000 $1.300 $1.000 $0.600 $1.500 $1.030
RE PM TY III (W)(8")(SLD)
LF 37,601.000 $1.650 $0.940 $0.900 $1.250 $1.500
RE PM TY III (W)(12")(SLD)
LF 14,981.000 $3.450 $2.000 $3.200 $3.000 $1.800
RE PM TY III (W)(12")(DOT)
LF 6,636.000 $1.630 $2.150 $3.200 $3.000 $2.500
RE PM TY III (W)(24")(SLD)
LF 2,616.000 $6.200 $9.500 $9.640 $7.000 $8.000
RE PM TY III (Y)(6")(SLD)
LF 144,323.000 $0.650 $0.610 $0.600 $0.700 $0.850
RE PM TY III (BLK)(6")(SHADOW)
LF 79,111.000 $0.600 $0.810 $0.630 $0.800 $0.850
PREFAB PM TY C (W)(ARROW)
EA 105.000 $210.000 $223.000 $213.590 $230.000 $200.000
PREFAB PM TY C (W)(DBL ARROW)
EA 32.000 $350.000 $376.000 $305.860 $355.000 $300.000
PREFAB PM TY C (W)(UTURN ARROW)
EA 20.000 $275.000 $389.000 $317.160 $400.000 $360.000
PREFAB PM TY C (W)(NUMBER)
EA 17.000 $271.530 $295.000 $165.510 $250.000 $220.000
PREFAB PM TY C (W)(WORD)
EA 126.000 $276.000 $320.000 $262.840 $300.000 $260.000
PREFAB PM TY C (MULTI)(SHIELD)
EA 19.000 $2,550.000 $2,700.000 $2,308.500 $2,600.000 $2,600.000
REFL PAV MRKR TY II-C-R
EA 6,993.000 $5.990 $4.900 $4.990 $5.750 $5.500
ELIM EXT PM & MRKS (6")
LF 462,288.000 $0.380 $0.310 $0.380 $0.350 $0.300
ELIM EXT PM & MRKS (8")
LF 37,601.000 $0.770 $0.740 $0.660 $0.750 $0.650
ELIM EXT PM & MRKS (12")
LF 21,617.000 $1.740 $1.300 $0.720 $1.250 $1.500
ELIM EXT PM & MRKS (24")
LF 2,616.000 $2.850 $2.500 $1.510 $2.500 $3.000
ELIM EXT PM & MRKS (ARROW)
EA 105.000 $46.800 $36.000 $100.000 $45.000 $65.000
ELIM EXT PM & MRKS (DBL ARROW)
EA 32.000 $36.880 $50.000 $100.000 $50.000 $80.000
ELIM EXT PM & MRKS (UTURN ARROW)
EA 20.000 $58.530 $63.000 $100.000 $50.000 $90.000
ELIM EXT PM & MRKS (NUMBER)
EA 17.000 $35.420 $36.000 $100.000 $50.000 $70.000
ELIM EXT PM & MRKS (WORD)
EA 126.000 $46.870 $40.000 $100.000 $45.000 $100.000
ELIM EXT PM & MRKS (SHIELD)
EA 19.000 $298.150 $15.000 $100.000 $100.000 $130.000
PAV SURF PREP FOR MRK (6")
LF 462,288.000 $0.020 $0.020 $0.020 $0.010 $0.010
PAV SURF PREP FOR MRK (8")
LF 37,601.000 $0.090 $0.070 $0.020 $0.050 $0.020
PAV SURF PREP FOR MRK (12")
LF 21,617.000 $0.220 $0.210 $0.040 $0.250 $0.500
PAV SURF PREP FOR MRK (24")
LF 2,616.000 $0.460 $0.440 $0.050 $0.500 $1.000
PAV SURF PREP FOR MRK (ARROW)
EA 105.000 $6.180 $10.000 $20.000 $10.000 $20.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 32.000 $6.150 $35.000 $20.000 $10.000 $30.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 20.000 $8.000 $20.000 $20.000 $10.000 $30.000
PAV SURF PREP FOR MRK (NUMBER)
EA 17.000 $10.000 $30.000 $20.000 $10.000 $25.000
PAV SURF PREP FOR MRK (WORD)
EA 126.000 $10.000 $15.000 $20.000 $10.000 $30.000
PAV SURF PREP FOR MRK (SHIELD)
EA 19.000 $20.000 $12.500 $20.000 $10.000 $50.000
PREFB PV MK W/WNTY TY B(W)6"(BRK)CNTST
LF 5,782.000 $9.000 $13.100 $14.650 $10.000 $13.000
Totals: $1,016,527.650 $936,472.550 $939,806.280 $977,569.080 $1,056,824.630