HARRIS IH 45 (0500-03-635)
Items: 86
County: HARRIS
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-635
DBE Goal: 0.0%
Project: C 500-3-635
Guaranty: N/A
Time: 118 WORKING DAYS
Engineer's Estimate: $5,144,475.90
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,144,475.90 | |||
| $4,137,770.75 |
-19.57%
-$1,006,705.15
|
|||
| $4,180,362.03 |
-18.74%
-$964,113.87
|
1.03%
$42,591.28
|
||
| $4,877,904.80 |
-5.18%
-$266,571.10
|
17.89%
$740,134.05
|
-16.69%
-$697,542.77
|
|
| $5,122,605.42 |
-0.43%
-$21,870.48
|
23.8%
$984,834.67
|
-5.02%
-$244,700.62
|
E
Engineer's Estimate
$5,144,475.90
1
Awarded
$4,137,770.75
Over/Under Est:
-19.57%
-$1,006,705.15
$4,180,362.03
Over/Under Est:
-18.74%
-$964,113.87
Amt Left:
1.03%
$42,591.28
$4,877,904.80
Over/Under Est:
-5.18%
-$266,571.10
Amt Left:
17.89%
$740,134.05
Delta:
-16.69%
-$697,542.77
$5,122,605.42
Over/Under Est:
-0.43%
-$21,870.48
Amt Left:
23.8%
$984,834.67
Delta:
-5.02%
-$244,700.62
| Subcontractor | Percentage | Amount |
|---|---|---|
| BATTERSON, LLP | 6.13% | $253,645.47 |
| CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | 3.21% | $132,822.51 |
| PRIMATE CONSTRUCTION, LP | 1.82% | $75,307.46 |
| TRAFFIC SIGNS & LINES, LLC | 0.80% | $33,102.18 |
| THIRD COAST SERVICES LLC | 0.70% | $28,964.41 |
| INTERSTATE BARRICADES & MARKINGS, INC. | 0.44% | $18,206.20 |
| Total: | 13.10% | $542,048.23 |
Bid Items & Bid Tabulations
86
Total
0 of 86