Show Job Controls
Bid Cobra

HARRIS IH 45 (0500-03-629)

Items: 82

County: HARRIS
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0500-03-629
DBE Goal: N/A
Project: BR 2022(927)
Guaranty: N/A
Time: 199 WORKING DAYS
Engineer's Estimate: $2,254,018.91
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$2,254,018.91
$2,552,371.96
Over/Under Est: 13.24% $298,353.05
Over/Under Est: 32.81% $739,501.22
Amt Left: 17.28% $441,148.17
Over/Under Est: 58.17% $1,311,234.78
Amt Left: 39.68% $1,012,881.73
Delta: -19.10% -$571,733.56
Subcontractor Percentage Amount
AVILES CONSTRUCTION SERVICE, INC 10.52% $282,592.95
BON'S BARRICADES, INC. 4.76% $127,865.25
QMF STEEL, INC. 4.12% $110,673.28
THIRD COAST SERVICES LLC 3.45% $92,675.44
HIGHWAY 1 LLC 1.10% $29,548.69
TEXOP CONSTRUCTION 1.09% $29,280.07
WILLOW CITY SIGN & RAIL, INC. 0.63% $16,923.34
NELSON INDUSTRIAL SERVICES, INC. 0.48% $12,893.97
HOUSTON SAWING & DRILLING 0.07% $1,880.37
CURB PLANET INC. 0.05% $1,343.12
Total: 26.27% $705,676.48

Bid Items & Bid Tabulations

82 Total 0 of 82
HARRIS  |  IH 45  |  HOUSTON  |  0500-03-629  |  08/04/2022  |  $2,254,018.91  |  BR 2022(927)  |  BRIDGE REPL  |  199 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRUCTURAL INTEGRITY GROUP LLC
RAGLE CONSTRUCTION, INC.
FORDE CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 2.600 $10,000.000 $13,000.000 $115,000.000 $100,000.000
REMOVING CONC (PAV)
SY 986.000 $6.500 $38.000 $16.000 $60.000
REMOVING CONC (MEDIANS)
SY 100.000 $18.000 $58.000 $18.000 $94.000
REMOVING CONC (SIDEWALKS)
SY 75.000 $15.000 $42.000 $24.000 $123.000
REMOVING CONC (CURB)
LF 505.000 $8.000 $23.000 $10.000 $17.000
EXCAVATION (ROADWAY)
CY 20.000 $8.000 $80.000 $300.000 $120.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 20.000 $12.500 $260.000 $300.000 $120.000
CONC PVMT (CONT REINF)(FAST TRK)(12")
SY 462.000 $115.000 $252.000 $200.000 $277.000
REINF CONC SLAB (SLAB BEAM)
SF 3,923.000 $20.000 $42.000 $40.000 $34.000
BRIDGE MEDIAN
SF 652.000 $10.000 $25.000 $11.000 $110.000
BRIDGE SIDEWALK
SF 502.000 $10.000 $30.000 $12.000 $72.000
APPROACH SLAB
CY 212.000 $600.000 $714.000 $1,067.000 $877.000
PRESTR CONC SLAB BEAM (4SB15)
LF 965.400 $165.000 $235.000 $200.000 $260.000
CONC STR REPR(RAPID VERT AND OVERHEAD)
SF 410.000 $350.000 $205.000 $72.000 $200.000
CONC STR REPAIR (STANDARD)
SF 340.000 $650.000 $175.000 $125.000 $200.000
CONC STR REP(DECK REP(PAR DEPTH))(ABC)
SF 200.000 $300.000 $160.000 $150.000 $210.000
RIPRAP (CONC)(4 IN)
CY 2.400 $420.000 $2,288.000 $5,000.000 $15,000.000
RAIL (TY C1W)
LF 511.600 $230.000 $480.000 $275.000 $380.000
MICROMILLING CONCRETE SLAB (3/4 IN)
SY 2,254.000 $16.000 $23.000 $13.000 $20.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $50,000.000 $96,215.000 $400,000.000 $175,000.000
REMOVE STR (RAIL)
LF 534.000 $25.000 $42.000 $13.000 $40.000
MOBILIZATION
LS 1.000 $204,680.410 $285,000.000 $290,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $8,000.000 $15,205.000 $30,750.000 $30,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 80.000 $5.000 $14.000 $7.500 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 80.000 $1.000 $8.000 $2.500 $5.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 520.000 $55.000 $56.000 $50.000 $60.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 60.000 $66.000 $80.000 $50.000 $85.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 80.000 $6.000 $41.000 $10.000 $87.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $9.000 $31.000 $12.000 $87.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 520.000 $12.500 $30.000 $12.000 $33.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 60.000 $11.000 $50.000 $16.000 $58.000
CONC CURB (DOWEL)
LF 587.000 $8.500 $21.000 $18.000 $30.000
CONC SIDEWALKS (4")
SY 79.000 $58.000 $100.000 $64.000 $260.000
CURB RAMPS (TY 7)
EA 1.000 $3,000.000 $2,400.000 $2,400.000 $4,000.000
CURB RAMPS (TY 10)
EA 1.000 $1,700.000 $2,500.000 $2,000.000 $4,000.000
CONC MEDIAN
SY 127.000 $75.000 $109.000 $70.000 $138.000
MTL W-BEAM GD FEN (TIM POST)
LF 25.000 $30.000 $53.000 $40.160 $53.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $1,300.000 $2,200.000 $1,670.000 $2,200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,100.000 $4,700.000 $3,565.000 $4,700.000
CONDT (PVC) (SCH 80) (2")
LF 75.000 $13.000 $27.500 $20.400 $45.000
ELEC CONDR (NO.6) BARE
LF 75.000 $1.900 $2.500 $2.350 $4.400
ALUMINUM SIGNS (TY A)
SF 60.400 $35.000 $29.000 $22.000 $28.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $600.000 $900.000 $685.000 $868.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $600.000 $1,200.000 $910.000 $1,150.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 1.000 $1,800.000 $2,550.000 $1,935.000 $2,450.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 1,463.000 $0.800 $2.000 $1.550 $2.200
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 84.000 $8.500 $13.000 $10.000 $14.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 4.000 $175.000 $330.000 $250.000 $360.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,588.000 $0.800 $2.000 $1.550 $2.200
PAVEMENT SEALER 4"
LF 992.000 $0.150 $0.080 $0.060 $0.100
PAVEMENT SEALER 6"
LF 1,232.000 $0.200 $0.100 $0.080 $0.110
PAVEMENT SEALER 8"
LF 231.000 $0.250 $0.130 $0.100 $0.140
PAVEMENT SEALER 12"
LF 150.000 $0.700 $0.160 $0.120 $0.170
PAVEMENT SEALER 24"
LF 123.000 $1.500 $30.000 $0.240 $0.350
ELIM EXT PAV MRK & MRKS (4")
LF 1,323.000 $0.300 $60.000 $0.450 $0.640
PAV SURF PREP FOR MRK (4")
LF 992.000 $0.050 $0.160 $0.120 $0.170
PAV SURF PREP FOR MRK (6")
LF 1,232.000 $0.100 $0.250 $0.180 $0.260
PAV SURF PREP FOR MRK (8")
LF 231.000 $0.050 $0.300 $0.240 $0.300
PAV SURF PREP FOR MRK (12")
LF 150.000 $0.300 $0.500 $0.360 $0.500
PAV SURF PREP FOR MRK (24")
LF 123.000 $0.700 $0.950 $0.720 $1.000
TEMP TRAF SIGNALS
EA 1.000 $30,000.000 $81,875.000 $49,295.580 $45,000.000
TRF SIG CBL (TY A)(14 AWG)(2 CONDR)
LF 170.000 $1.400 $3.150 $1.700 $4.400
TRF SIG CBL (TY A)(14 AWG)(4 CONDR)
LF 170.000 $2.000 $3.600 $2.350 $4.400
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 255.000 $2.500 $4.250 $2.900 $4.400
TRF SIG CBL (TY A)(16 AWG)(3 CONDR)
LF 170.000 $3.000 $3.000 $3.000 $4.400
BRIDGE JOINT REPLACEMENT (SEJ)
LF 200.000 $650.000 $430.000 $500.000 $500.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 2,254.000 $200.000 $120.000 $130.000 $292.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $19,000.000 $100.000 $12,000.000 $7,500.000
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 960.000 $0.800 $3.250 $2.500 $3.500
MULTIPOLYMER PAV MRK (W)(4")(DOT)
LF 32.000 $2.000 $5.250 $4.000 $5.700
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 436.000 $1.200 $3.600 $2.750 $4.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 360.000 $0.520 $3.600 $2.750 $4.000
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 231.000 $1.000 $5.750 $4.400 $6.300
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 150.000 $3.000 $9.150 $7.000 $10.000
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 123.000 $6.000 $18.500 $14.000 $20.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 436.000 $1.500 $3.600 $2.750 $4.000
MULTIYPOLYMER PAV MRK (W) (ARROW)
EA 1.000 $100.000 $395.000 $300.000 $430.000
MULTIPOLYMER PAV MRK (W) (WORD)
EA 1.000 $250.000 $450.000 $350.000 $500.000
COAXIAL CABLE
LF 170.000 $2.500 $4.600 $1.260 $4.400
TMA (STATIONARY)
DAY 188.000 $250.000 $150.000 $275.000 $200.000
TMA (MOBILE OPERATION)
DAY 6.000 $300.000 $395.000 $700.000 $250.000
VIVDS TEMPORARY
EA 1.000 $11,500.000 $27,000.000 $22,945.000 $25,000.000
Totals: $2,254,018.910 $2,552,371.960 $2,993,520.130 $3,565,253.690