PREPARING ROW
|
STA
|
2.600
|
$10,000.000
|
$13,000.000
|
$115,000.000
|
$100,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
986.000
|
$6.500
|
$38.000
|
$16.000
|
$60.000
|
|
|
REMOVING CONC (MEDIANS)
|
SY
|
100.000
|
$18.000
|
$58.000
|
$18.000
|
$94.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
75.000
|
$15.000
|
$42.000
|
$24.000
|
$123.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
505.000
|
$8.000
|
$23.000
|
$10.000
|
$17.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
20.000
|
$8.000
|
$80.000
|
$300.000
|
$120.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY D)
|
CY
|
20.000
|
$12.500
|
$260.000
|
$300.000
|
$120.000
|
|
|
CONC PVMT (CONT REINF)(FAST TRK)(12")
|
SY
|
462.000
|
$115.000
|
$252.000
|
$200.000
|
$277.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
3,923.000
|
$20.000
|
$42.000
|
$40.000
|
$34.000
|
|
|
BRIDGE MEDIAN
|
SF
|
652.000
|
$10.000
|
$25.000
|
$11.000
|
$110.000
|
|
|
BRIDGE SIDEWALK
|
SF
|
502.000
|
$10.000
|
$30.000
|
$12.000
|
$72.000
|
|
|
APPROACH SLAB
|
CY
|
212.000
|
$600.000
|
$714.000
|
$1,067.000
|
$877.000
|
|
|
PRESTR CONC SLAB BEAM (4SB15)
|
LF
|
965.400
|
$165.000
|
$235.000
|
$200.000
|
$260.000
|
|
|
CONC STR REPR(RAPID VERT AND OVERHEAD)
|
SF
|
410.000
|
$350.000
|
$205.000
|
$72.000
|
$200.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
340.000
|
$650.000
|
$175.000
|
$125.000
|
$200.000
|
|
|
CONC STR REP(DECK REP(PAR DEPTH))(ABC)
|
SF
|
200.000
|
$300.000
|
$160.000
|
$150.000
|
$210.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
2.400
|
$420.000
|
$2,288.000
|
$5,000.000
|
$15,000.000
|
|
|
RAIL (TY C1W)
|
LF
|
511.600
|
$230.000
|
$480.000
|
$275.000
|
$380.000
|
|
|
MICROMILLING CONCRETE SLAB (3/4 IN)
|
SY
|
2,254.000
|
$16.000
|
$23.000
|
$13.000
|
$20.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$50,000.000
|
$96,215.000
|
$400,000.000
|
$175,000.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
534.000
|
$25.000
|
$42.000
|
$13.000
|
$40.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$204,680.410
|
$285,000.000
|
$290,000.000
|
$350,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
10.000
|
$8,000.000
|
$15,205.000
|
$30,750.000
|
$30,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
80.000
|
$5.000
|
$14.000
|
$7.500
|
$12.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
80.000
|
$1.000
|
$8.000
|
$2.500
|
$5.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$55.000
|
$56.000
|
$50.000
|
$60.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
60.000
|
$66.000
|
$80.000
|
$50.000
|
$85.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
80.000
|
$6.000
|
$41.000
|
$10.000
|
$87.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$9.000
|
$31.000
|
$12.000
|
$87.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
520.000
|
$12.500
|
$30.000
|
$12.000
|
$33.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
60.000
|
$11.000
|
$50.000
|
$16.000
|
$58.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
587.000
|
$8.500
|
$21.000
|
$18.000
|
$30.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
79.000
|
$58.000
|
$100.000
|
$64.000
|
$260.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
1.000
|
$3,000.000
|
$2,400.000
|
$2,400.000
|
$4,000.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
1.000
|
$1,700.000
|
$2,500.000
|
$2,000.000
|
$4,000.000
|
|
|
CONC MEDIAN
|
SY
|
127.000
|
$75.000
|
$109.000
|
$70.000
|
$138.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
25.000
|
$30.000
|
$53.000
|
$40.160
|
$53.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
1.000
|
$1,300.000
|
$2,200.000
|
$1,670.000
|
$2,200.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$3,100.000
|
$4,700.000
|
$3,565.000
|
$4,700.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
75.000
|
$13.000
|
$27.500
|
$20.400
|
$45.000
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
75.000
|
$1.900
|
$2.500
|
$2.350
|
$4.400
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
60.400
|
$35.000
|
$29.000
|
$22.000
|
$28.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
2.000
|
$600.000
|
$900.000
|
$685.000
|
$868.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$600.000
|
$1,200.000
|
$910.000
|
$1,150.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
1.000
|
$1,800.000
|
$2,550.000
|
$1,935.000
|
$2,450.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
1,463.000
|
$0.800
|
$2.000
|
$1.550
|
$2.200
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
84.000
|
$8.500
|
$13.000
|
$10.000
|
$14.000
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
4.000
|
$175.000
|
$330.000
|
$250.000
|
$360.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
4,588.000
|
$0.800
|
$2.000
|
$1.550
|
$2.200
|
|
|
PAVEMENT SEALER 4"
|
LF
|
992.000
|
$0.150
|
$0.080
|
$0.060
|
$0.100
|
|
|
PAVEMENT SEALER 6"
|
LF
|
1,232.000
|
$0.200
|
$0.100
|
$0.080
|
$0.110
|
|
|
PAVEMENT SEALER 8"
|
LF
|
231.000
|
$0.250
|
$0.130
|
$0.100
|
$0.140
|
|
|
PAVEMENT SEALER 12"
|
LF
|
150.000
|
$0.700
|
$0.160
|
$0.120
|
$0.170
|
|
|
PAVEMENT SEALER 24"
|
LF
|
123.000
|
$1.500
|
$30.000
|
$0.240
|
$0.350
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
1,323.000
|
$0.300
|
$60.000
|
$0.450
|
$0.640
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
992.000
|
$0.050
|
$0.160
|
$0.120
|
$0.170
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
1,232.000
|
$0.100
|
$0.250
|
$0.180
|
$0.260
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
231.000
|
$0.050
|
$0.300
|
$0.240
|
$0.300
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
150.000
|
$0.300
|
$0.500
|
$0.360
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
123.000
|
$0.700
|
$0.950
|
$0.720
|
$1.000
|
|
|
TEMP TRAF SIGNALS
|
EA
|
1.000
|
$30,000.000
|
$81,875.000
|
$49,295.580
|
$45,000.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(2 CONDR)
|
LF
|
170.000
|
$1.400
|
$3.150
|
$1.700
|
$4.400
|
|
|
TRF SIG CBL (TY A)(14 AWG)(4 CONDR)
|
LF
|
170.000
|
$2.000
|
$3.600
|
$2.350
|
$4.400
|
|
|
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
|
LF
|
255.000
|
$2.500
|
$4.250
|
$2.900
|
$4.400
|
|
|
TRF SIG CBL (TY A)(16 AWG)(3 CONDR)
|
LF
|
170.000
|
$3.000
|
$3.000
|
$3.000
|
$4.400
|
|
|
BRIDGE JOINT REPLACEMENT (SEJ)
|
LF
|
200.000
|
$650.000
|
$430.000
|
$500.000
|
$500.000
|
|
|
POLYESTER POLYMER CONC OVERLAY (3/4")
|
SY
|
2,254.000
|
$200.000
|
$120.000
|
$130.000
|
$292.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
5.000
|
$19,000.000
|
$100.000
|
$12,000.000
|
$7,500.000
|
|
MULTIPOLYMER PAV MRK (W)(4")(BRK)
|
LF
|
960.000
|
$0.800
|
$3.250
|
$2.500
|
$3.500
|
|
MULTIPOLYMER PAV MRK (W)(4")(DOT)
|
LF
|
32.000
|
$2.000
|
$5.250
|
$4.000
|
$5.700
|
|
MULTIPOLYMER PAV MRK (W)(6")(SLD)
|
LF
|
436.000
|
$1.200
|
$3.600
|
$2.750
|
$4.000
|
|
MULTIPOLYMER PAV MRK (W)(6")(BRK)
|
LF
|
360.000
|
$0.520
|
$3.600
|
$2.750
|
$4.000
|
|
MULTIPOLYMER PAV MRK (W)(8")(SLD)
|
LF
|
231.000
|
$1.000
|
$5.750
|
$4.400
|
$6.300
|
|
MULTIPOLYMER PAV MRK (W)(12")(SLD)
|
LF
|
150.000
|
$3.000
|
$9.150
|
$7.000
|
$10.000
|
|
MULTIPOLYMER PAV MRK (W)(24")(SLD)
|
LF
|
123.000
|
$6.000
|
$18.500
|
$14.000
|
$20.000
|
|
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
|
LF
|
436.000
|
$1.500
|
$3.600
|
$2.750
|
$4.000
|
|
MULTIYPOLYMER PAV MRK (W) (ARROW)
|
EA
|
1.000
|
$100.000
|
$395.000
|
$300.000
|
$430.000
|
|
MULTIPOLYMER PAV MRK (W) (WORD)
|
EA
|
1.000
|
$250.000
|
$450.000
|
$350.000
|
$500.000
|
|
|
COAXIAL CABLE
|
LF
|
170.000
|
$2.500
|
$4.600
|
$1.260
|
$4.400
|
|
|
TMA (STATIONARY)
|
DAY
|
188.000
|
$250.000
|
$150.000
|
$275.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
6.000
|
$300.000
|
$395.000
|
$700.000
|
$250.000
|
|
|
VIVDS TEMPORARY
|
EA
|
1.000
|
$11,500.000
|
$27,000.000
|
$22,945.000
|
$25,000.000
|
|
Totals: |
$2,254,018.910
|
$2,552,371.960
|
$2,993,520.130
|
$3,565,253.690
|