Job Info for 0271-16-144

County: HARRIS Highway: IH 610 Date: 08/08/2018 (6 years ago) Engineer's Estimate: $495,517 Control Number: 0271-16-144
Project: NH 1802(607) District: HOUSTON Time: 45 WORKING DAYS Type: LANDSCAPE ENHANCEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $495,517.20
CHAMPION INFRASTRUCTURE, LLC   $614,672.00 1
24.05% | $119,154.80
CENTRAL NORTH CONSTRUCTION, LLC   $799,358.30 2
61.32% | $303,841.10
30.05% | $184,686.30
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $965,996.87 3
94.95% | $470,479.67
57.16% | $351,324.87
20.85% | $166,638.57

Bid Items

Items: 20, 0 filtered
HARRIS IH 610  |  HOUSTON  |  0271-16-144  |  08/08/2018  |  $495,517  |  NH 1802(607)  |  LANDSCAPE ENHANS  |  45 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CHAMPION INFRASTRUCTURE, LLC CENTRAL NORTH CONSTRUCTION, LLC YELLOWSTONE LANDSCAPE - CENTRAL, INC.
160 6005 FURNISHING AND PLACING TOPSOIL CY 10.000 $180.000 $60.000 $150.000 $122.807
161 6009 EROSION CONTROL COMPOST CY 111.000 $24.000 $28.000 $50.000 $79.026
162 6002 BLOCK SODDING SY 150.000 $3.180 $2.800 $25.000 $7.018
170 6002 IRRIGATION SYSTEM (TY I) LS 1.000 $10,000.000 $220,000.000 $293,000.000 $96,491.228
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 4.000 $180.000 $50.000 $85.000 $100.877
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 25.000 $300.000 $160.000 $125.000 $247.018
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 3,276.000 $20.000 $15.000 $18.000 $28.705
193 6002 PLANT MAINTENANCE CYC 9.000 $25,000.000 $21,000.000 $2,800.000 $33,138.402
500 6001 MOBILIZATION LS 0.910 $40,000.000 $42,000.000 $260,000.000 $98,245.614
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $1,500.000 $3,500.000 $3,000.000 $3,567.251
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 200.000 $4.000 $4.000 $10.000 $12.281
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 200.000 $1.000 $2.000 $10.000 $0.239
751 6011 PRUNING CYC 1.020 $105,000.000 $45,000.000 $50,000.000 $241,562.491
1000 6006 PRUNING AND TRIMMING TREES AND SHRUBS CYC 1.010 $24,000.000 $36,000.000 $65,000.000 $103,508.772
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 2,398.000 $0.500 $1.000 $2.220 $0.278
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 2,398.000 $0.400 $1.000 $1.250 $0.278
1006 6003 LANDSCAPE SOIL AMENDMENT (TYPE III) SY 206.000 $3.000 $3.000 $5.000 $1.277
1006 6004 LANDSCAPE SOIL AMENDMENT (TYPE IV) SY 206.000 $4.000 $3.000 $5.000 $0.247
1006 6005 LANDSCAPE SOIL AMENDMENT (TYPE V) SY 9,592.000 $0.500 $1.000 $2.220 $0.409
6185 6002 TMA (STATIONARY) DAY 1.000 $200.000 $400.000 $10,000.000 $473.684
Totals: $495,517.20 $614,672.00 $799,358.30 $965,996.95