Show Job Controls
Bid Cobra

HARRIS IH 610 (0271-14-236)

Items: 21

County: HARRIS
Length: N/A
Highway: IH 610
District: HOUSTON
Control Number: 0271-14-236
DBE Goal: N/A
Project: NH 1802(605)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $572,928.00
Date: 08/08/2018 (7 years ago)
Contract Number: N/A
Type: LANDSCAPE ENHANCEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$572,928.00
$566,852.65
Over/Under Est: -1.06% -$6,075.35
$575,532.95
Over/Under Est: 0.45% $2,604.95
Amt Left: 1.53% $8,680.30
Over/Under Est: 22.54% $129,147.35
Amt Left: 23.86% $135,222.70
Delta: -21.99% -$126,542.40
Over/Under Est: 32.9% $188,514.50
Amt Left: 34.33% $194,589.85
Delta: -8.46% -$59,367.15
Over/Under Est: 42.23% $241,919.41
Amt Left: 43.75% $247,994.76
Delta: -7.01% -$53,404.91

Bid Items & Bid Tabulations

21 Total 0 of 21
HARRIS  |  IH 610  |  HOUSTON  |  0271-14-236  |  08/08/2018  |  $572,928.00  |  NH 1802(605)  |  LANDSCAPE ENHANS  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CROSBY RD CONSTRUCTION INC
BOYER, INC.
CENTRAL NORTH CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 14.000 $75.000 $800.000 $476.000 $1,500.000 $150.000 $375.940
PREP ROW (TREE) (2" TO 12" DIA)
EA 5.000 $100.000 $400.000 $2,031.000 $600.000 $150.000 $652.632
EROSION CONTROL COMPOST
CY 3,777.000 $28.000 $19.000 $28.500 $18.000 $22.000 $39.482
GENERAL USE COMPOST
CY 1,881.000 $30.000 $26.000 $29.500 $18.000 $20.000 $45.308
PLANT MATERIAL (5 GAL) (TREE)
EA 3,785.000 $20.000 $19.000 $15.700 $18.000 $15.000 $16.792
PLANT MATERIAL (15 GAL) (TREE)
EA 665.000 $105.000 $90.000 $78.000 $62.000 $45.000 $106.700
PLANT BED PREP (TYPE III)
SY 33,991.000 $1.000 $0.750 $0.150 $1.300 $0.500 $0.619
PLANT MAINTENANCE
MO 18.000 $1,800.000 $5,000.000 $3,503.000 $1,500.000 $8,000.000 $4,385.965
PLANT MAINTENANCE
CYC 9.000 $9,000.000 $4,000.000 $9,430.000 $5,000.000 $18,000.000 $12,670.565
MOBILIZATION
LS 1.000 $27,500.000 $42,000.000 $57,250.000 $150,333.750 $50,000.000 $78,947.368
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $1,500.000 $4,000.000 $540.000 $1,250.000 $4,200.000 $2,706.433
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2.000 $6.000 $20.000 $5.000 $25.000 $1.000 $117.895
BIODEG EROSN CONT LOGS (REMOVE)
LF 2.000 $1.000 $3.000 $3.000 $25.000 $1.000 $30.175
PRUNING
CYC 1.000 $25,000.000 $14,000.000 $10,001.000 $50,000.000 $48,000.000 $49,122.807
PRUNING AND TRIMMING TREES AND SHRUBS
CYC 1.000 $12,000.000 $14,000.000 $10,400.000 $35,000.000 $60,000.000 $50,008.772
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 33,991.000 $0.250 $0.400 $0.450 $0.650 $0.500 $0.280
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 33,991.000 $0.250 $0.600 $0.350 $0.650 $0.500 $0.291
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 4,819.000 $3.000 $1.800 $1.400 $2.000 $1.500 $1.278
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 23,900.000 $0.500 $0.600 $0.550 $0.650 $0.500 $0.251
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 4,819.000 $0.500 $1.800 $0.600 $2.000 $0.500 $0.624
TMA (STATIONARY)
DAY 5.000 $290.000 $400.000 $400.000 $6,500.000 $400.000 $473.860
Totals: $572,928.000 $566,852.650 $575,532.950 $702,075.350 $761,442.500 $814,847.471