Show Job Controls
Bid Cobra

HARRIS IH 10 (0271-06-120)

Items: 24

County: HARRIS
Length: N/A
Highway: IH 10
District: HOUSTON
Control Number: 0271-06-120
DBE Goal: N/A
Project: NH 1802(603)
Guaranty: N/A
Time: 80 WORKING DAYS
Engineer's Estimate: $2,119,850.00
Date: 08/07/2018 (7 years ago)
Contract Number: N/A
Type: EROSION REP AND CHANNEL PROTECTION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$2,119,850.00
$1,785,427.00
Over/Under Est: -15.78% -$334,423.00
$1,851,531.00
Over/Under Est: -12.66% -$268,319.00
Amt Left: 3.7% $66,104.00
$1,989,598.53
Over/Under Est: -6.14% -$130,251.47
Amt Left: 11.44% $204,171.53
Delta: -7.46% -$138,067.53
$2,235,580.60
Over/Under Est: 5.46% $115,730.60
Amt Left: 25.21% $450,153.60
Delta: -12.36% -$245,982.07
$2,324,205.00
Over/Under Est: 9.64% $204,355.00
Amt Left: 30.18% $538,778.00
Delta: -3.96% -$88,624.40
$2,439,501.00
Over/Under Est: 15.08% $319,651.00
Amt Left: 36.63% $654,074.00
Delta: -4.96% -$115,296.00

Bid Items & Bid Tabulations

24 Total 0 of 24
HARRIS  |  IH 10  |  HOUSTON  |  0271-06-120  |  08/07/2018  |  $2,119,850.00  |  NH 1802(603)  |  EROSION REP AND CHANNEL PROTECTION  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SJ&J CONSTRUCTION, LLC
TEXAS WALL & LANDSCAPE
ALTUS CONSTRUCTION LLC
EARTH BUILDERS, L.P.
FNH CONSTRUCTION, LLC
ISI CONTRACTING, INC.
REMOVING CONC (RIPRAP)
SY 2,953.000 $10.000 $16.000 $13.500 $9.049 $30.000 $30.000 $40.000
REMOVING CONC (SIDEWALKS)
SY 50.000 $30.000 $16.000 $20.000 $11.357 $10.000 $30.000 $30.000
REMOVING CONC (CURB)
LF 100.000 $15.000 $8.000 $10.000 $5.070 $10.000 $30.000 $2.000
EXCAVATION (CHANNEL)
CY 9,069.000 $35.000 $8.000 $30.000 $43.267 $35.000 $20.000 $29.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 4,823.000 $35.000 $25.000 $29.000 $35.326 $65.000 $35.000 $49.000
BLOCK SODDING
SY 220.000 $5.000 $6.000 $6.000 $8.403 $15.000 $10.000 $5.000
FERTILIZER
AC 0.050 $2,000.000 $500.000 $20,000.000 $1,839.134 $3,000.000 $25,000.000 $780.000
VEGETATIVE WATERING
MG 6.000 $80.000 $40.000 $100.000 $49.044 $200.000 $1,000.000 $15.000
CEM STABIL BKFL
CY 10.000 $200.000 $150.000 $75.000 $269.740 $250.000 $450.000 $60.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 4,060.000 $125.000 $28.000 $70.000 $6.062 $0.010 $80.000 $12.000
RIPRAP (CONC)(CL B)
CY 396.000 $410.000 $700.000 $585.000 $411.884 $700.000 $650.000 $575.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 4,314.000 $150.000 $180.000 $163.000 $210.207 $220.000 $225.000 $300.000
MOBILIZATION
LS 1.000 $188,400.000 $333,999.000 $86,000.000 $183,913.362 $245,000.000 $230,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $8,000.000 $4,000.000 $3,000.000 $12,260.890 $2,000.000 $8,500.000 $1,500.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 90.000 $100.000 $18.000 $100.000 $95.635 $40.000 $30.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 90.000 $15.000 $8.000 $50.000 $10.893 $10.000 $15.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 177.000 $30.000 $16.000 $22.000 $36.839 $30.000 $40.000 $22.000
CONSTRUCTION EXITS (REMOVE)
SY 177.000 $10.000 $8.000 $7.500 $12.255 $10.000 $20.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,660.000 $4.500 $2.000 $4.500 $3.413 $2.000 $4.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,660.000 $1.000 $1.000 $1.250 $1.218 $1.000 $2.000 $2.000
CONC CURB (MONO) (TY II)
LF 100.000 $30.000 $12.000 $30.000 $6.654 $10.000 $40.000 $8.000
CONC SIDEWALKS (4")
SY 50.000 $100.000 $70.000 $160.000 $101.110 $65.000 $75.000 $75.000
TREE AND BRUSH REMOVAL
AC 0.020 $500,000.000 $10,000.000 $1,300,000.000 $589,558.787 $15,000.000 $150,000.000 $280,000.000
TMA (STATIONARY)
DAY 25.000 $300.000 $100.000 $350.000 $434.350 $200.000 $250.000 $300.000
Totals: $2,119,850.000 $1,785,427.000 $1,851,531.000 $1,989,598.586 $2,235,580.600 $2,324,205.000 $2,439,501.000