Job Info for 0271-06-120

County: HARRIS Highway: IH 10 Date: 08/07/2018 (6 years ago) Engineer's Estimate: $2,119,850 Control Number: 0271-06-120
Project: NH 1802(603) District: HOUSTON Time: 80 WORKING DAYS Type: EROSION REP AND CHANNEL PROTECTION

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,119,850.00
SJ&J CONSTRUCTION, LLC   $1,785,427.00 1
-15.78% | -$334,423.00
TEXAS WALL & LANDSCAPE   $1,851,531.00 2
-12.66% | -$268,319.00
3.7% | $66,104.00
ALTUS CONSTRUCTION LLC   $1,989,598.53 3
-6.14% | -$130,251.47
11.44% | $204,171.53
7.46% | $138,067.53
EARTH BUILDERS, L.P.   $2,235,580.60 4
5.46% | $115,730.60
25.21% | $450,153.60
12.36% | $245,982.07
FNH CONSTRUCTION, LLC   $2,324,205.00 5
9.64% | $204,355.00
30.18% | $538,778.00
3.96% | $88,624.40
ISI CONTRACTING, INC.   $2,439,501.00 6
15.08% | $319,651.00
36.63% | $654,074.00
4.96% | $115,296.00

Bid Items

Items: 24, 0 filtered
HARRIS IH 10  |  HOUSTON  |  0271-06-120  |  08/07/2018  |  $2,119,850  |  NH 1802(603)  |  EROSION REP AND CHANNEL PROTECTION  |  80 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SJ&J CONSTRUCTION, LLC TEXAS WALL & LANDSCAPE ALTUS CONSTRUCTION LLC EARTH BUILDERS, L.P. FNH CONSTRUCTION, LLC ISI CONTRACTING, INC.
104 6009 REMOVING CONC (RIPRAP) SY 2,953.000 $10.000 $16.000 $13.500 $9.049 $30.000 $30.000 $40.000
104 6015 REMOVING CONC (SIDEWALKS) SY 50.000 $30.000 $16.000 $20.000 $11.357 $10.000 $30.000 $30.000
104 6021 REMOVING CONC (CURB) LF 100.000 $15.000 $8.000 $10.000 $5.070 $10.000 $30.000 $2.000
110 6002 EXCAVATION (CHANNEL) CY 9,069.000 $35.000 $8.000 $30.000 $43.267 $35.000 $20.000 $29.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 4,823.000 $35.000 $25.000 $29.000 $35.326 $65.000 $35.000 $49.000
162 6002 BLOCK SODDING SY 220.000 $5.000 $6.000 $6.000 $8.403 $15.000 $10.000 $5.000
166 6001 FERTILIZER AC 0.050 $2,000.000 $500.000 $20,000.000 $1,839.134 $3,000.000 $25,000.000 $780.000
168 6001 VEGETATIVE WATERING MG 6.000 $80.000 $40.000 $100.000 $49.044 $200.000 $1,000.000 $15.000
400 6005 CEM STABIL BKFL CY 10.000 $200.000 $150.000 $75.000 $269.740 $250.000 $450.000 $60.000
403 6006 TEMPORARY SPL SHORING (COFFERDAM) SF 4,060.000 $125.000 $28.000 $70.000 $6.062 $0.010 $80.000 $12.000
432 6006 RIPRAP (CONC)(CL B) CY 396.000 $410.000 $700.000 $585.000 $411.884 $700.000 $650.000 $575.000
432 6027 RIPRAP (STONE COMMON)(DRY)(24 IN) CY 4,314.000 $150.000 $180.000 $163.000 $210.207 $220.000 $225.000 $300.000
500 6001 MOBILIZATION LS 1.000 $188,400.000 $333,999.000 $86,000.000 $183,913.362 $245,000.000 $230,000.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $8,000.000 $4,000.000 $3,000.000 $12,260.890 $2,000.000 $8,500.000 $1,500.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 90.000 $100.000 $18.000 $100.000 $95.635 $40.000 $30.000 $55.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 90.000 $15.000 $8.000 $50.000 $10.893 $10.000 $15.000 $15.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 177.000 $30.000 $16.000 $22.000 $36.839 $30.000 $40.000 $22.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 177.000 $10.000 $8.000 $7.500 $12.255 $10.000 $20.000 $10.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,660.000 $4.500 $2.000 $4.500 $3.413 $2.000 $4.000 $4.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,660.000 $1.000 $1.000 $1.250 $1.218 $1.000 $2.000 $2.000
529 6005 CONC CURB (MONO) (TY II) LF 100.000 $30.000 $12.000 $30.000 $6.654 $10.000 $40.000 $8.000
531 6001 CONC SIDEWALKS (4") SY 50.000 $100.000 $70.000 $160.000 $101.110 $65.000 $75.000 $75.000
752 6015 TREE AND BRUSH REMOVAL AC 0.020 $500,000.000 $10,000.000 $1,300,000.000 $589,558.787 $15,000.000 $150,000.000 $280,000.000
6185 6002 TMA (STATIONARY) DAY 25.000 $300.000 $100.000 $350.000 $434.350 $200.000 $250.000 $300.000
Totals: $2,119,850.00 $1,785,427.00 $1,851,531.00 $1,989,598.59 $2,235,580.60 $2,324,205.00 $2,439,501.00