HARRIS US 290 (0050-06-090)

Items: 16

County: HARRIS
Length: N/A
Highway: US 290
District: HOUSTON
Control Number: 0050-06-090
DBE Goal: N/A
Project: NH 1802(600)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $1,393,781.00
Date: 08/08/2018 (7 years ago)
Contract Number: N/A
Type: LANDSCAPE ENHANCEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,393,781.00
$1,140,000.00
Over/Under Est: -18.21% -$253,781.00
$1,212,768.80
Over/Under Est: -12.99% -$181,012.20
Amt Left: 6.38% $72,768.80
$1,249,552.26
Over/Under Est: -10.35% -$144,228.74
Amt Left: 9.61% $109,552.26
Delta: -3.03% -$36,783.46
Over/Under Est: -8.96% -$124,845.10
Amt Left: 11.31% $128,935.90
Delta: -1.55% -$19,383.64
Over/Under Est: -8.81% -$122,788.93
Amt Left: 11.49% $130,992.07
Delta: -0.16% -$2,056.17
Over/Under Est: 20.33% $283,400.85
Amt Left: 47.12% $537,181.85
Delta: -31.96% -$406,189.78

Bid Items & Bid Tabulations

16 Total 0 of 16
HARRIS  |  US 290  |  HOUSTON  |  0050-06-090  |  08/08/2018  |  $1,393,781.00  |  NH 1802(600)  |  LANDSCAPE ENHANS  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
BOYER, INC.
TEXAS WALL & LANDSCAPE
CHAMPION INFRASTRUCTURE, LLC
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
CENTRAL NORTH CONSTRUCTION, LLC
EROSION CONTROL COMPOST
CY 14,858.000 $30.000 $17.750 $19.430 $22.000 $22.000 $21.819 $18.000
GENERAL USE COMPOST
CY 7,429.000 $32.000 $21.750 $20.730 $26.000 $20.000 $24.562 $18.000
PLANT MATERIAL (3-GAL)
EA 2,300.000 $10.000 $20.000 $15.820 $11.500 $9.000 $14.078 $18.000
PLANT BED PREPARATION
SY 133,468.000 $0.500 $0.300 $0.250 $1.220 $2.000 $0.215 $1.500
PLANT MATERIAL (5 GAL) (TREE)
EA 8,764.000 $15.000 $20.000 $27.090 $11.500 $15.000 $15.594 $18.000
PLANT MATERIAL (15 GAL) (TREE)
EA 429.000 $200.000 $105.000 $59.940 $50.000 $45.000 $108.763 $85.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 1,387.000 $11.000 $20.000 $11.870 $11.500 $12.000 $19.046 $18.000
PLANT MAINTENANCE
MO 18.000 $6,006.000 $6,500.000 $9,470.000 $5,000.000 $1,800.000 $13,711.060 $2,500.000
MOBILIZATION
LS 1.000 $101,637.000 $114,754.950 $113,800.000 $123,000.000 $120,000.000 $129,032.258 $553,282.800
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $8,000.000 $2,850.000 $302.450 $3,500.000 $4,200.000 $1,996.371 $1,500.000
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 133,468.000 $0.300 $0.350 $0.440 $0.300 $0.400 $0.255 $0.500
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 133,468.000 $0.300 $0.300 $0.310 $0.300 $0.400 $0.265 $0.500
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 11,463.000 $1.150 $1.150 $0.720 $3.500 $1.500 $1.163 $1.350
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 57,315.000 $0.250 $0.350 $0.330 $0.500 $0.400 $0.228 $0.500
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 12,850.000 $0.500 $0.450 $0.470 $0.560 $0.400 $0.376 $1.350
TMA (STATIONARY)
DAY 1.000 $300.000 $250.000 $739.570 $5,000.000 $400.000 $1,080.806 $10,000.000
Totals: $1,393,781.000 $1,140,000.000 $1,212,768.800 $1,249,552.260 $1,268,935.900 $1,270,992.126 $1,677,181.850