HARDIN FM3513 (6361-46-001)

Items: 22

County: HARDIN
Length: N/A
Highway: FM3513
District: BEAUMONT
Control Number: 6361-46-001
DBE Goal: N/A
Project: RMC - 636146001
Guaranty: N/A
Time: 25 W
Engineer's Estimate: $157,911.01
Date: 09/22/2020 (5 years ago)
Contract Number: N/A
Type: MILL & OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$157,911.01
$223,049.69
Over/Under Est: 41.25% $65,138.68
Over/Under Est: 81.52% $128,734.39
Amt Left: 28.51% $63,595.71
Over/Under Est: 101.34% $160,033.99
Amt Left: 42.54% $94,895.31
Delta: -10.92% -$31,299.60

Bid Items & Bid Tabulations

22 Total 0 of 22
HARDIN  |  FM3513  |  BEAUMONT  |  6361-46-001  |  09/22/2020  |  $157,911.01  |  RMC - 636146001  |  MILL & OVERLAY  |  25 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
PTSS INVESTMENTS, LLC
FNH CONSTRUCTION, LLC
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 200.000 $73.110 $115.000 $100.000 $150.000
PLANE ASPH CONC PAV (2")
SY 2,675.000 $1.680 $3.550 $8.000 $10.000
PLAN ASPH CONC PAV (1" TO 2 1/2")
SY 5,188.000 $2.510 $3.550 $8.000 $10.000
MOBILIZATION
LS 1.000 $1.000 $16,800.000 $25,000.000 $30,000.000
MOBILIZATION (CALLOUT 1)
EA 1.000 $1.000 $5,300.000 $7,500.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,000.000 $2,200.000 $5,000.000 $8,500.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 489.000 $0.170 $15.100 $10.000 $8.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 152.000 $3.340 $1.680 $3.000 $5.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 88.000 $1.120 $1.680 $8.000 $5.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 539.000 $0.750 $6.550 $7.500 $8.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 370.000 $0.360 $3.510 $4.100 $4.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 840.000 $0.220 $3.510 $4.100 $4.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 20.000 $0.370 $3.510 $4.100 $4.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,599.000 $0.280 $3.510 $4.100 $4.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 154.000 $10.570 $20.100 $23.000 $25.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 5.000 $194.150 $236.000 $270.000 $250.000
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $226.020 $305.000 $345.000 $350.000
REFL PAV MRKR TY I-C
EA 52.000 $2.930 $6.100 $7.000 $5.000
REFL PAV MRKR TY II-A-A
EA 51.000 $3.670 $6.100 $7.000 $5.000
SP MIXES SP-D SAC-A PG76-22
TON 722.000 $141.000 $148.000 $150.000 $140.000
TACK COAT
GAL 473.000 $4.250 $8.000 $9.000 $10.000
TMA (STATIONARY)
DAY 25.000 $250.000 $305.000 $800.000 $350.000
Totals: $157,911.010 $223,049.690 $286,645.400 $317,945.000