Show Job Controls
Bid Cobra

HARDIN FM 943 (1194-02-020)

Items: 69

County: HARDIN
Length: 8.3080 MILES (7.6981 MILES)
Highway: FM 943
District: BEAUMONT
Control Number: 1194-02-020
DBE Goal: 0.0%
Project: C 1194-2-20
Guaranty: $100,000.00
Time: 116 WORKING DAYS
Engineer's Estimate: $5,913,739.66
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263007
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00187963
Project Description: FM 943-(3.6 MILES SOUTH OF POLK COUNTY LINE, SOUTH TO FM 1003) FULL DEPTH BASE REPAIR, LU AND SMA-D
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$5,913,739.66
Over/Under Est: 17.94% $1,060,979.72
Over/Under Est: 22.34% $1,321,338.79
Amt Left: 3.73% $260,359.07
$8,177,811.90
Over/Under Est: 38.28% $2,264,072.24
Amt Left: 17.25% $1,203,092.52
Delta: -13.03% -$942,733.45

Bid Items & Bid Tabulations

69 Total 0 of 69
HARDIN  |  FM 943  |  BEAUMONT  |  1194-02-020  |  07/01/2026 1:00 PM CDT  |  $5,913,739.66  |  C 1194-2-20  |  REHAB EXIST ROADWAY  |  116 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DURWOOD GREENE CONSTRUCTION CO.
TEXAS MATERIALS GROUP, INC.
HAYDEN PAVING, INC.
PREPARING ROW
STA 159.820 $850.000 $825.000 $669.000 $1,000.000
EMBANK (FNL)(OC)(TY C)
CY 81.000 $15.000 $90.000 $206.250 $175.000
BACKFILL (TY A OR B)
STA 438.720 $180.000 $350.000 $340.000 $450.000
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 48,746.000 $0.510 $0.500 $0.500 $1.000
HYDRO MULCH SEED (TEMP_WARM)
SY 12,187.000 $0.350 $0.350 $0.500 $1.000
VEGETATIVE WATERING
TGL 513.000 $5.500 $25.000 $13.500 $140.000
D-GR HMA TY-D PG70-22
TON 10,884.000 $125.000 $140.000 $155.750 $170.000
TACK COAT
GAL 7,916.000 $3.000 $4.000 $4.250 $2.500
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 14,513.000 $150.000 $220.000 $224.000 $270.000
TACK COAT
GAL 7,916.000 $4.000 $4.000 $4.250 $2.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 659.000 $137.000 $97.000 $166.250 $85.000
PLANE ASPH PAV (0" TO 3.5")
SY 2,100.000 $15.000 $10.000 $9.000 $7.500
CUT & RESTORING PAV
SY 218.000 $250.000 $200.000 $314.000 $280.000
CEM STABIL BKFL
CY 1,071.000 $200.000 $80.000 $136.250 $185.000
TRENCH EXCAVATION PROTECTION
LF 562.000 $7.000 $10.000 $115.250 $12.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 91.000 $200.000 $265.000 $146.750 $275.000
HEADWALL (CH - FW - 0) (DIA= 60 IN)
EA 2.000 $9,000.000 $19,000.000 $25,000.000 $20,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 12.000 $1,050.000 $1,400.000 $1,200.000 $1,000.000
SET (TY II) (18 IN) (TP) (6: 1) (C)
EA 8.000 $1,050.000 $1,400.000 $1,467.000 $1,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 12.000 $1,850.000 $1,800.000 $2,093.000 $2,200.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 22.000 $2,450.000 $2,000.000 $1,988.500 $2,700.000
SET (TY II) (24 IN) (TP) (4: 1) (C)
EA 2.000 $1,850.000 $1,800.000 $2,093.000 $2,200.000
SET (TY II) (24 IN) (TP) (6: 1) (P)
EA 2.000 $2,000.000 $2,000.000 $2,930.250 $2,700.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 3.000 $3,000.000 $2,900.000 $2,616.250 $3,200.000
SET (TY II) (30 IN) (TP) (4: 1) (C)
EA 6.000 $3,000.000 $2,900.000 $3,379.000 $3,200.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 6.000 $4,000.000 $3,200.000 $3,505.750 $4,250.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 2.000 $5,210.000 $5,500.000 $7,116.250 $5,300.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 4.000 $9,440.000 $4,200.000 $7,745.000 $6,300.000
SET (TY II) (60 IN) (RCP) (4: 1) (C)
EA 5.000 $10,000.000 $8,500.000 $10,465.000 $9,500.000
SET (TY II) (48 IN) (TP) (4:1) (C)
EA 12.000 $9,440.000 $6,000.000 $7,953.500 $6,900.000
SET (TY II) (60 IN) (TP) (4:1) (C)
EA 6.000 $10,000.000 $8,500.000 $10,465.000 $9,500.000
THERMOPLASTIC PIPE (PP) (18")
LF 130.000 $62.000 $80.000 $146.750 $62.000
THERMOPLASTIC PIPE (PP) (24")
LF 112.000 $140.000 $120.000 $162.250 $150.000
THERMOPLASTIC PIPE (PP) (30")
LF 156.000 $160.000 $130.000 $199.000 $197.000
THERMOPLASTIC PIPE (PP) (48")
LF 366.000 $200.000 $190.000 $220.000 $234.000
THERMOPLASTIC PIPE (PP) (60")
LF 146.000 $250.000 $320.000 $366.500 $304.000
REMOV STR (PIPE)
LF 910.000 $46.000 $80.000 $31.500 $68.000
MOBILIZATION
LS 1.000 $560,000.000 $460,000.000 $170,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $7,500.000 $890.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,000.000 $12,000.000 $15,600.000 $8,000.000
TMA (STATIONARY)
DAY 113.000 $260.000 $300.000 $314.000 $500.000
TMA (MOBILE OPERATION)
DAY 3.000 $178.000 $500.000 $523.250 $500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 320.000 $50.000 $55.000 $44.500 $220.000
ROCK FILTER DAMS (REMOVE)
LF 320.000 $4.000 $10.000 $10.500 $53.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,180.000 $13.800 $10.000 $5.250 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,180.000 $2.000 $1.000 $1.100 $1.650
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $6,985.000 $6,700.000 $4,762.000 $6,000.000
INTERSECTIONS (ACP)
SY 572.000 $40.000 $55.000 $175.000 $105.000
DRIVEWAYS (ACP)
SY 68.000 $54.000 $120.000 $70.000 $105.000
DRIVEWAYS (BASE)
SY 1,003.000 $46.000 $35.000 $71.500 $43.000
TURNOUTS (ACP)
SY 805.000 $80.000 $100.000 $175.000 $105.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 43,872.000 $0.220 $0.240 $0.190 $0.200
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 27.000 $355.000 $325.000 $288.000 $300.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 5.000 $400.000 $360.000 $288.000 $325.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 12.000 $825.000 $800.000 $623.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $757.000 $425.000 $356.000 $600.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 2.000 $830.000 $1,100.000 $863.500 $750.000
REMOVE SM RD SN SUP&AM
EA 20.000 $126.000 $130.000 $146.750 $90.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 72.000 $175.000 $120.000 $100.000 $100.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 9,750.000 $0.530 $0.300 $0.750 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 20,703.000 $0.530 $0.300 $0.750 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,926.000 $2.380 $2.000 $0.850 $1.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 87,196.000 $0.620 $1.050 $1.000 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 9,750.000 $0.580 $0.650 $0.740 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 20,703.000 $0.580 $0.650 $0.740 $1.000
PREFAB PM TY C (W)(24")(SLD)
LF 51.000 $15.500 $24.000 $18.500 $20.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 112.000 $51.700 $50.000 $57.750 $32.000
REFL PAV MRKR TY II-A-A
EA 760.000 $4.600 $7.000 $7.000 $5.500
LITTER REMOVAL
AC 32.230 $16.000 $500.000 $184.000 $500.000
Totals: $5,913,739.660 $6,974,719.380 $7,235,078.450 $8,177,811.900
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $10,000.00