HARDIN FM 770 (1096-01-068)

Items: 44

County: HARDIN
Length: N/A
Highway: FM 770
District: BEAUMONT
Control Number: 1096-01-068
DBE Goal: N/A
Project: F 2024(036)
Guaranty: N/A
Time: 88 WORKING DAYS
Engineer's Estimate: $5,134,746.10
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$5,134,746.10
Over/Under Est: -19.69% -$1,011,003.21
Over/Under Est: 5.51% $282,963.05
Amt Left: 31.38% $1,293,966.26
$6,351,786.50
Over/Under Est: 23.7% $1,217,040.40
Amt Left: 54.03% $2,228,043.61
Delta: -17.24% -$934,077.35
Subcontractor Percentage Amount
J & M CONTRACTING, COMPANY 10.99% $453,199.34
BATTERSON, LLP 4.94% $203,712.90
MURRAY CONSTRUCTION 1.02% $42,062.18
SUPERIOR TRAFFIC CONTROL, LLC 0.21% $8,659.86
PROFESSIONAL TRAFFIC CONTROL LLC 0.17% $7,010.36
AWP SAFETY 0.08% $3,298.99
SOUTHWEST ENVIRONMENT SERVICES LLC 0.05% $2,061.87
Total: 17.46% $720,005.50

Bid Items & Bid Tabulations

44 Total 0 of 44
HARDIN  |  FM 770  |  BEAUMONT  |  1096-01-068  |  09/06/2023  |  $5,134,746.10  |  F 2024(036)  |  SURF/ROADWAY RESTOR  |  88 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
FNH CONSTRUCTION, LLC
BACKFILL (TY B)
STA 60.000 $325.000 $358.580 $525.000 $450.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 4,083.000 $0.500 $0.780 $0.400 $1.000
VEGETATIVE WATERING
MG 5.800 $16.000 $696.060 $440.000 $1,000.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 250.000 $120.000 $112.450 $218.000 $100.000
PLANE ASPH CONC PAV(0" TO 2")
SY 11,191.000 $3.700 $2.670 $3.350 $7.000
PLANE ASPH CONC PAV (2")
SY 110,555.000 $4.200 $1.620 $2.770 $6.500
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,173.000 $2.500 $4.230 $3.350 $10.000
PLANE ASPH CONC PAV(1" TO 2")
SY 898.000 $4.000 $3.510 $3.350 $10.000
FULL - DEPTH REPAIR CPCD (6"-9")
SY 900.000 $500.000 $450.300 $545.000 $450.000
CLEANING AND SEALING EXISTING JOINTS
LF 2,000.000 $5.500 $9.540 $13.000 $100.000
MOBILIZATION
LS 1.000 $467,294.000 $82,144.620 $415,000.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,000.000 $24,930.940 $3,500.000 $8,500.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 300.000 $1.700 $2.840 $1.000 $4.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 300.000 $11.000 $4.780 $10.000 $2.000
DRIVEWAYS (CONC)
SY 122.000 $170.000 $264.880 $187.000 $85.000
DRIVEWAYS (ACP)
SY 4,977.000 $50.000 $33.030 $56.000 $55.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 40,286.000 $0.600 $0.070 $0.650 $0.500
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 47.000 $270.000 $196.010 $309.000 $1,000.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $270.000 $254.290 $309.000 $1,000.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 1.000 $520.000 $529.760 $618.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 37.000 $600.000 $635.710 $798.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 3.000 $1,100.000 $821.130 $103.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SB(U)
EA 3.000 $1,350.000 $874.110 $1,086.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SB(U)
EA 1.000 $1,175.000 $1,006.550 $1,189.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 44.000 $110.000 $105.950 $154.000 $100.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 810.000 $0.850 $0.410 $0.400 $2.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 88,305.000 $0.500 $0.410 $0.400 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 9,010.000 $0.850 $0.410 $0.400 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 52,760.000 $0.800 $0.410 $0.400 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 242.000 $2.000 $0.880 $3.200 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,340.000 $2.600 $0.780 $2.300 $6.000
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
LF 88,305.000 $1.200 $1.170 $1.130 $2.000
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 810.000 $0.750 $0.640 $0.620 $1.500
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 9,010.000 $0.750 $0.640 $0.620 $1.500
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 52,760.000 $0.750 $0.640 $0.620 $1.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 252.000 $13.000 $14.830 $14.000 $25.000
REFL PAV MRKR TY I-C
EA 32.000 $5.000 $6.890 $6.700 $7.000
REFL PAV MRKR TY II-A-A
EA 991.000 $5.500 $6.890 $6.700 $7.000
D-GR HMA TY-D SAC-B PG64-22
TON 981.000 $150.000 $126.220 $177.250 $165.000
TACK COAT
GAL 596.000 $6.000 $6.340 $8.000 $8.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 15,351.000 $180.000 $164.130 $205.000 $200.000
TACK COAT
GAL 7,305.000 $6.000 $6.180 $7.000 $8.000
TMA (STATIONARY)
DAY 80.000 $350.000 $424.400 $326.000 $250.000
TMA (MOBILE OPERATION)
DAY 8.000 $350.000 $59.600 $1,378.000 $550.000
Totals: $5,134,746.100 $4,123,742.898 $5,417,709.150 $6,351,786.500