Job Info for 0920-03-081

County: HARDIN Highway: CR Date: 10/05/2023 (1 year ago) Engineer's Estimate: $812,357 Control Number: 0920-03-081
Project: BR 2021(530) District: BEAUMONT Time: 75 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $812,356.76
C. E. BARKER, LTD.   $775,736.52 1
-4.51% | -$36,620.24
PROJECT ALLIED RESOURCES, LLC   $941,075.60 2
15.85% | $128,718.84
21.31% | $165,339.08
TEXAS MATERIALS GROUP, INC.   $966,492.00 3
18.97% | $154,135.24
24.59% | $190,755.48
2.70% | $25,416.40
BLACKSMITH VENTURES LLC   $1,173,361.75 4
44.44% | $361,004.99
51.26% | $397,625.23
21.40% | $206,869.75
ISI CONTRACTING, INC.   $1,393,881.40 5
71.58% | $581,524.64
79.68% | $618,144.88
18.79% | $220,519.65
Subcontractor Percentage Amount
GUERRA CONCRETE CONTRACTORS, LLC 12.18% $94,484.71
HEMPHILL WBE PILE DRIVING CO. 9.59% $74,393.13
HAZMAT INTERNATIONAL, INC. 3.40% $26,375.04
TSTAR DRILLING & SAWING INC 2.83% $21,953.34
BARRICADES UNLIMITED 0.70% $5,430.16
SEMARCK LANDSCAPE SERVICES, INC. 0.64% $4,964.71
HOUSTON SAWING & DRILLING 0.42% $3,258.09
A1 EROSION CONTROL 0.25% $1,939.34
Total: 30.01% $232,798.52

Bid Items

Items: 32, 0 filtered
HARDIN CR  |  BEAUMONT  |  0920-03-081  |  10/05/2023  |  $812,357  |  BR 2021(530)  |  BRIDGE REPL  |  75 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate C. E. BARKER, LTD. PROJECT ALLIED RESOURCES, LLC TEXAS MATERIALS GROUP, INC. BLACKSMITH VENTURES LLC ISI CONTRACTING, INC.
100 6028 PREP ROW (TREE PRUNING) EA 5.000 $4,500.000 $703.800 $6,160.000 $3,400.000 $550.000 $4,500.000
110 6001 EXCAVATION (ROADWAY) CY 326.000 $35.000 $27.370 $40.300 $55.000 $33.000 $35.000
112 6001 SUBGRADE WIDENING (ORD COMP) STA 2.000 $3,200.000 $2,052.750 $4,510.000 $3,500.000 $2,750.000 $6,349.000
132 6007 EMBANKMENT (FINAL)(ORD COMP)(TY D) CY 31.000 $75.000 $273.700 $166.000 $158.000 $55.000 $30.000
216 6001 PROOF ROLLING HR 10.000 $125.000 $313.780 $580.000 $290.000 $192.500 $150.000
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 80.000 $110.000 $462.160 $188.000 $310.000 $275.000 $362.000
310 6005 PRIME COAT (AE-P) GAL 86.000 $22.000 $23.460 $25.000 $26.000 $27.500 $18.000
400 6005 CEM STABIL BKFL CY 25.000 $245.000 $199.410 $280.000 $332.000 $330.000 $113.000
409 6002 PRESTR CONC PIL (18 IN SQ) LF 676.000 $84.290 $172.190 $155.000 $195.000 $220.000 $693.000
420 6013 CL C CONC (ABUT) CY 17.600 $2,400.000 $2,789.880 $3,810.000 $3,700.000 $3,300.000 $2,558.000
420 6025 CL C CONC (BENT) CY 13.200 $2,400.000 $2,083.250 $3,880.000 $3,700.000 $5,500.000 $3,133.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 2,340.000 $30.000 $28.490 $43.800 $33.000 $33.000 $53.000
422 6015 APPROACH SLAB CY 38.500 $685.000 $513.770 $749.000 $1,000.000 $1,650.000 $2,047.000
425 6010 PRESTR CONC SLAB BEAM (5SB12) LF 442.500 $326.530 $149.100 $254.000 $120.000 $302.500 $81.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 683.000 $100.000 $134.800 $49.700 $240.000 $247.500 $248.000
450 6006 RAIL (TY T223) LF 204.000 $160.000 $305.970 $237.000 $280.000 $302.500 $250.000
454 6003 ARMOR JOINT LF 44.000 $195.000 $180.110 $323.000 $322.000 $150.000 $106.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $35,000.000 $26,392.500 $70,000.000 $52,000.000 $55,000.000 $26,308.000
500 6001 MOBILIZATION LS 1.000 $135,392.790 $66,157.200 $103,000.000 $93,000.000 $110,000.000 $130,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $6,000.000 $2,919.050 $5,240.000 $4,200.000 $5,500.000 $11,096.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 50.000 $60.000 $41.060 $146.000 $50.000 $330.000 $92.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 50.000 $20.000 $20.530 $41.500 $12.000 $11.000 $24.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 320.000 $5.000 $6.420 $12.400 $5.500 $16.500 $8.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 320.000 $1.500 $3.200 $3.910 $1.000 $5.500 $2.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 50.000 $45.000 $38.240 $91.000 $36.000 $44.000 $41.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,200.000 $2,193.510 $3,660.000 $2,060.000 $4,400.000 $3,731.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,100.000 $3,753.600 $5,320.000 $3,520.000 $5,500.000 $5,000.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $25.000 $23.460 $42.600 $55.000 $110.000 $17.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 8.000 $30.000 $46.920 $75.000 $55.000 $110.000 $35.000
3076 6066 TACK COAT GAL 43.000 $21.300 $29.330 $24.400 $50.000 $165.000 $60.000
3076 6071 D-GR HMA TY-D PG 64-22 (EXEMPT) TON 47.000 $402.000 $763.620 $461.000 $470.000 $330.000 $360.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $9,518.900 $5,890.000 $5,600.000 $22,000.000 $7,634.000
Totals: $812,356.76 $775,736.53 $941,075.60 $966,492.00 $1,173,361.75 $1,393,881.40