Show Job Controls
Bid Cobra

HARDIN CR (0920-03-081)

Items: 32

County: HARDIN
Length: N/A
Highway: CR
District: BEAUMONT
Control Number: 0920-03-081
DBE Goal: N/A
Project: BR 2021(530)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $496,529.00
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$496,529.00
Over/Under Est: 88.37% $438,782.00
Over/Under Est: 97.4% $483,639.00
Amt Left: 4.8% $44,857.00

Bid Items & Bid Tabulations

32 Total 0 of 32
HARDIN  |  CR  |  BEAUMONT  |  0920-03-081  |  03/04/2022  |  $496,529.00  |  BR 2021(530)  |  BRIDGE REPL  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PROJECT ALLIED RESOURCES, LLC
TEXAS MATERIALS GROUP, INC.
PREP ROW (TREE PRUNING)
EA 5.000 $300.000 $3,590.000 $1,700.000
EXCAVATION (ROADWAY)
CY 326.000 $16.000 $29.600 $27.000
SUBGRADE WIDENING (ORD COMP)
STA 2.000 $305.000 $2,240.000 $1,350.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 31.000 $22.000 $79.000 $103.000
PROOF ROLLING
HR 10.000 $92.000 $184.000 $95.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 80.000 $150.000 $218.000 $230.000
PRIME COAT (AE-P)
GAL 86.000 $22.000 $19.400 $15.000
CEM STABIL BKFL
CY 25.000 $165.000 $276.000 $200.000
PRESTR CONC PIL (18 IN SQ)
LF 676.000 $120.000 $182.000 $198.000
CL C CONC (ABUT)
CY 17.600 $950.000 $2,160.000 $2,900.000
CL C CONC (BENT)
CY 13.200 $1,045.000 $1,820.000 $3,250.000
REINF CONC SLAB (SLAB BEAM)
SF 2,340.000 $18.000 $37.300 $56.000
APPROACH SLAB
CY 38.500 $620.000 $834.000 $808.000
PRESTR CONC SLAB BEAM (5SB12)
LF 442.500 $173.000 $307.000 $276.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 683.000 $130.000 $226.000 $211.000
RAIL (TY T223)
LF 204.000 $105.000 $203.000 $240.000
ARMOR JOINT
LF 44.000 $70.000 $168.000 $250.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $37,400.000 $42,600.000
MOBILIZATION
LS 1.000 $27,000.000 $83,000.000 $97,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $1,500.000 $3,610.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $35.000 $75.000 $70.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $15.000 $17.700 $16.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 320.000 $3.000 $5.700 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 320.000 $1.500 $1.930 $1.500
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $29.000 $49.200 $38.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $2,580.000 $2,090.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,700.000 $3,700.000 $3,075.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $15.000 $33.500 $23.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $28.000 $55.000 $25.000
TACK COAT
GAL 43.000 $3.500 $17.300 $20.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 47.000 $139.000 $449.000 $410.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $16,900.000 $6,500.000
Totals: $496,529.000 $935,311.000 $980,168.000