Job Info for 0065-05-152

County: HARDIN Highway: US 96 Date: 08/06/2020 (4 years ago) Engineer's Estimate: $438,242 Control Number: 0065-05-152
Project: STP 2020(779)HES District: BEAUMONT Time: 31 WORKING DAYS Type: SFT - SAFETY IMPROVEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $438,242.25
CRABTREE BARRICADE SYSTEMS, INC.   $278,418.30 1
-36.47% | -$159,823.95
STRIPE-A-ZONE, INC.   $484,361.05 2
10.52% | $46,118.80
73.97% | $205,942.75
BATTERSON, LLP   $498,193.00 3
13.68% | $59,950.75
78.94% | $219,774.70
2.86% | $13,831.95
TRP CONSTRUCTION GROUP, LLC   $524,771.75 4
19.74% | $86,529.50
88.48% | $246,353.45
5.34% | $26,578.75

Bid Items

Items: 14, 0 filtered
HARDIN US 96  |  BEAUMONT  |  0065-05-152  |  08/06/2020  |  $438,242  |  STP 2020(779)HES  |  SFT - SAFETY IMPRVS  |  31 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CRABTREE BARRICADE SYSTEMS, INC. STRIPE-A-ZONE, INC. BATTERSON, LLP TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $39,476.570 $43,000.000 $35,000.000 $20,000.000 $40,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $2,000.000 $2,500.000 $2,750.000 $3,000.000 $25,000.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 3,178.000 $0.950 $0.850 $1.600 $1.000 $1.000
666 6146 REFL PAV MRK TY I (Y)24"(SLD)(090MIL) LF 3,329.000 $15.000 $5.000 $5.250 $6.000 $7.250
666 6155 REFL PAV MRK TY I(Y)(MED NOSE)(090MIL) EA 32.000 $250.000 $200.000 $570.000 $500.000 $300.000
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 16,631.000 $0.700 $0.800 $1.600 $2.000 $2.500
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 784.000 $15.000 $12.000 $18.450 $14.000 $16.250
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 29.000 $250.000 $210.000 $255.000 $350.000 $325.000
672 6007 REFL PAV MRKR TY I-C EA 172.000 $3.400 $4.000 $4.200 $5.000 $10.000
672 6009 REFL PAV MRKR TY II-A-A EA 850.000 $3.260 $4.000 $4.200 $5.000 $5.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 3,368.000 $0.310 $0.900 $1.400 $1.000 $2.000
6049 6001 LONG CHANNEL MOUNT CURB SYS (INSTALL) LF 3,640.000 $80.000 $45.000 $93.800 $100.000 $79.000
6185 6002 TMA (STATIONARY) DAY 31.000 $210.000 $150.000 $100.000 $175.000 $850.000
6185 6005 TMA (MOBILE OPERATION) DAY 3.000 $350.000 $100.000 $350.000 $250.000 $2,500.000
Totals: $438,242.25 $278,418.30 $484,361.05 $498,193.00 $524,771.75