Job Info for 1650-01-010

County: HALL Highway: FM 1619 Date: 08/04/2022 (2 years ago) Engineer's Estimate: $1,306,328 Control Number: 1650-01-010
Project: BR 2022(655) District: CHILDRESS Time: 115 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimate
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,306,327.65
EARTH BUILDERS, L.P.   $1,575,474.20 1
20.6% | $269,146.55
COPPELL CONSTRUCTION CO., INC.   $1,822,319.10 2
39.5% | $515,991.45
15.67% | $246,844.90
HODGES AND SON CONSTRUCTION COMPANY, INC.   $1,888,229.80 3
44.54% | $581,902.15
19.85% | $312,755.60
3.62% | $65,910.70
GILVIN-TERRILL, LTD.   $1,979,253.65 4
51.51% | $672,926.00
25.63% | $403,779.45
4.82% | $91,023.85
J. LEE MILLIGAN, INC.   $2,255,278.70 5
72.64% | $948,951.05
43.15% | $679,804.50
13.95% | $276,025.05

Bid Items

Items: 38, 0 filtered
HALL FM 1619  |  CHILDRESS  |  1650-01-010  |  08/04/2022  |  $1,306,328  |  BR 2022(655)  |  BRIDGE REPL  |  115 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate EARTH BUILDERS, L.P. COPPELL CONSTRUCTION CO., INC. HODGES AND SON CONSTRUCTION COMPANY, INC. GILVIN-TERRILL, LTD. J. LEE MILLIGAN, INC.
105 6041 REMOVING STAB BASE AND ASPH PAV(8") SY 1,222.000 $20.000 $9.000 $15.000 $20.000 $10.000 $14.000
110 6001 EXCAVATION (ROADWAY) CY 27.000 $30.000 $20.000 $135.000 $100.000 $25.000 $560.000
110 6002 EXCAVATION (CHANNEL) CY 464.000 $20.000 $20.000 $24.000 $40.000 $25.000 $29.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 5,557.000 $20.000 $30.000 $41.000 $35.000 $27.500 $33.350
150 6002 BLADING HR 5.000 $180.000 $125.000 $185.000 $100.000 $250.000 $540.000
164 6022 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) AC 2.400 $2,500.000 $2,500.000 $2,320.000 $2,500.000 $3,400.000 $2,010.000
168 6001 VEGETATIVE WATERING MG 94.000 $20.000 $60.000 $61.000 $1.000 $40.000 $60.000
216 6001 PROOF ROLLING HR 4.000 $85.000 $80.000 $450.000 $50.000 $400.000 $200.000
247 6511 FL BS(CMP IN PLC)(TYA GR3)(FINAL POS)8" SY 4,035.000 $30.000 $35.000 $34.000 $45.000 $30.000 $24.250
310 6009 PRIME COAT (MC-30) GAL 1,211.000 $5.700 $7.000 $6.500 $15.000 $6.000 $6.700
316 6024 ASPH (CRS-2P) GAL 1,614.000 $8.200 $7.000 $11.500 $15.000 $7.000 $6.800
316 6078 AGGR(TY-B GR-4 SAC-A) CY 32.000 $240.000 $500.000 $918.000 $1,200.000 $200.000 $290.000
400 6005 CEM STABIL BKFL CY 59.000 $250.000 $300.000 $400.000 $250.000 $500.000 $350.000
416 6004 DRILL SHAFT (36 IN) LF 660.000 $220.000 $330.000 $382.000 $340.000 $375.000 $310.000
420 6013 CL C CONC (ABUT) CY 37.500 $1,420.000 $1,500.000 $1,622.000 $1,500.000 $2,250.000 $2,280.000
420 6029 CL C CONC (CAP) CY 30.000 $1,200.000 $1,500.000 $1,533.000 $1,600.000 $2,250.000 $2,750.000
420 6037 CL C CONC (COLUMN) CY 4.700 $1,250.000 $1,500.000 $2,800.000 $1,800.000 $2,250.000 $3,115.000
422 6001 REINF CONC SLAB SF 5,950.000 $26.000 $36.000 $36.000 $40.000 $40.000 $50.800
422 6015 APPROACH SLAB CY 66.900 $850.000 $800.000 $1,218.000 $1,000.000 $1,750.000 $785.000
425 6035 PRESTR CONC GIRDER (TX28) LF 693.880 $205.000 $240.000 $305.000 $285.000 $255.000 $295.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 295.000 $160.000 $200.000 $227.000 $260.000 $300.000 $200.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 24.000 $950.000 $550.000 $916.000 $650.000 $750.000 $1,025.000
450 6006 RAIL (TY T223) LF 382.000 $140.000 $150.000 $236.000 $200.000 $200.000 $250.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 71.000 $150.000 $250.000 $319.000 $200.000 $300.000 $330.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $62,000.000 $60,000.000 $35,000.000 $60,000.000 $142,500.000 $229,000.000
500 6001 MOBILIZATION LS 1.000 $121,029.750 $150,000.000 $154,000.000 $165,000.000 $135,000.000 $225,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $3,500.000 $2,300.000 $1,500.000 $10,000.000 $20,000.000 $30,000.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 300.000 $7.000 $12.000 $7.000 $10.000 $10.000 $9.400
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 100.000 $47.000 $38.000 $38.000 $40.000 $34.000 $41.200
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,500.000 $2,400.000 $2,800.000 $2,500.000 $2,750.000 $3,115.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 80.000 $5.000 $5.000 $30.000 $5.000 $20.000 $4.250
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,300.000 $3,800.000 $3,800.000 $3,200.000 $3,400.000 $4,000.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $25.000 $15.000 $24.000 $30.000 $25.000 $21.150
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 12.000 $35.000 $30.000 $36.000 $30.000 $27.000 $21.150
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 3,200.000 $5.000 $3.200 $3.000 $3.500 $2.750 $2.900
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 400.000 $5.000 $3.200 $3.000 $3.000 $2.750 $2.900
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 425.000 $5.000 $3.200 $3.000 $3.000 $2.750 $2.900
6185 6002 TMA (STATIONARY) DAY 4.000 $245.000 $250.000 $671.000 $500.000 $950.000 $590.000
Totals: $1,306,327.65 $1,575,474.20 $1,822,319.10 $1,888,229.80 $1,979,253.65 $2,255,278.70