Bid Cobra

HALE IH0027 (6432-32-001)

Items: 23

County: HALE
Length: N/A
Highway: IH0027
District: LUBBOCK
Control Number: 6432-32-001
DBE Goal: N/A
Project: RMC - 643232001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,295,050.00
Date: 02/02/2023 (3 years ago)
Contract Number: N/A
Type: TRAFFIC CONTROL SERVICES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,295,050.00
$1,040,386.00
Over/Under Est: -19.66% -$254,664.00
$1,072,568.00
Over/Under Est: -17.18% -$222,482.00
Amt Left: 3.09% $32,182.00
Over/Under Est: 2.07% $26,800.00
Amt Left: 27.05% $281,464.00
Delta: -23.24% -$249,282.00

Bid Items & Bid Tabulations

23 Total 0 of 23
HALE  |  IH0027  |  LUBBOCK  |  6432-32-001  |  02/02/2023  |  $1,295,050.00  |  RMC - 643232001  |  TRAF CONTROL SERVICES  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FC TRAFFIC CONTROL, INC.
BARRICADES UNLIMITED
STATEWIDE SAFETY SYSTEMS
TMA (STATIONARY)
DAY 200.000 $350.000 $200.000 $800.000 $650.000
TMA (MOBILE OPERATION)
HR 6,000.000 $100.000 $166.000 $120.000 $80.000
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 250.000 $500.000 $1.000 $150.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 2)
EA 100.000 $500.000 $1.000 $250.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 50.000 $450.000 $1.000 $300.000 $375.000
LANE CLOSURE (SETUP AND REMOV)(TY 5)
EA 20.000 $500.000 $1.000 $300.000 $425.000
LANE CLOSURE (SETUP AND REMOV)(TY 9)
EA 2.000 $1,000.000 $1.000 $400.000 $450.000
LANE CLOSURE (SETUP AND REMOV)(TY 10)
EA 1.000 $600.000 $1.000 $1.000 $1,350.000
LANE CLOSURE (SETUP AND REMOV)(TY 11)
EA 1.000 $1,250.000 $1.000 $1.000 $1,500.000
LANE CLOSURE (SETUP AND REMOV)(TY 12)
EA 5.000 $800.000 $1.000 $1.000 $350.000
LANE CLOSURE (SETUP AND REMOV)(TY 16)
EA 5.000 $500.000 $1.000 $1.000 $300.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 2,000.000 $100.000 $1.000 $20.000 $160.000
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 800.000 $100.000 $1.000 $40.000 $160.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 400.000 $100.000 $1.000 $40.000 $120.000
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 160.000 $100.000 $1.000 $40.000 $140.000
LANE CLOSURE (MAINTENANCE) (TY 9)
HR 16.000 $100.000 $1.000 $50.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 10)
HR 8.000 $100.000 $1.000 $1.000 $350.000
LANE CLOSURE (MAINTENANCE) (TY 11)
HR 8.000 $100.000 $1.000 $1.000 $200.000
LANE CLOSURE (MAINTENANCE) (TY 12)
HR 40.000 $100.000 $1.000 $1.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 16)
HR 40.000 $100.000 $1.000 $1.000 $95.000
LANE CLOSURE (SETUP AND REMOV)(TY 21)
HR 160.000 $200.000 $1.000 $1.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 160.000 $100.000 $1.000 $30.000 $60.000
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 160.000 $75.000 $1.000 $50.000 $75.000
Totals: $1,295,050.000 $1,040,386.000 $1,072,568.000 $1,321,850.000