HALE BI 27U (0067-09-033)
Items: 102
County: HALE
Length: 0.0000 MILES
Highway: BI 27U
District: LUBBOCK
Control Number: 0067-09-033
DBE Goal: 4.0%
Project: BR 2017(748)
Guaranty: $100,000.00
Time: 279 WORKING DAYS
Engineer's Estimate: $7,580,980.70
Date: 04/04/2025 1:00 PM CDT (1 year ago)
Contract Number: 4253212
Type: BRIDGE REPLACEMENT
Project ID: A00121832
Contract Type: FEDERAL
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HEATH BOZEMAN
HALE BI 27U (0067-09-033)
Project Name: N/A
Project: BR 2017(748)
Length: 0.0000 MILES (0.4649 MILES)
Project Class: CONSTRUCTION
Limits From: FM 3466
Limits To: W 3RD STREET
Project Description: BRIDGE REPLACEMENT
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,580,980.70 | |||
| $6,813,362.60 |
-10.13%
-$767,618.10
|
|||
| $7,678,802.30 |
1.29%
$97,821.60
|
12.7%
$865,439.70
|
||
| $8,299,989.76 |
9.48%
$719,009.06
|
21.82%
$1,486,627.16
|
-8.09%
-$621,187.46
|
|
| $9,863,292.30 |
30.11%
$2,282,311.60
|
44.76%
$3,049,929.70
|
-18.83%
-$1,563,302.54
|
|
| $10,691,886.90 |
41.04%
$3,110,906.20
|
56.93%
$3,878,524.30
|
-8.40%
-$828,594.60
|
|
| $11,462,192.70 |
51.2%
$3,881,212.00
|
68.23%
$4,648,830.10
|
-7.20%
-$770,305.80
|
E
Engineer's Estimate
$7,580,980.70
1
Awarded
$6,813,362.60
Over/Under Est:
-10.13%
-$767,618.10
$7,678,802.30
Over/Under Est:
1.29%
$97,821.60
Amt Left:
12.7%
$865,439.70
$8,299,989.76
Over/Under Est:
9.48%
$719,009.06
Amt Left:
21.82%
$1,486,627.16
Delta:
-8.09%
-$621,187.46
$9,863,292.30
Over/Under Est:
30.11%
$2,282,311.60
Amt Left:
44.76%
$3,049,929.70
Delta:
-18.83%
-$1,563,302.54
$10,691,886.90
Over/Under Est:
41.04%
$3,110,906.20
Amt Left:
56.93%
$3,878,524.30
Delta:
-8.40%
-$828,594.60
$11,462,192.70
Over/Under Est:
51.2%
$3,881,212.00
Amt Left:
68.23%
$4,648,830.10
Delta:
-7.20%
-$770,305.80
Bid Items & Bid Tabulations
102
Total
0 of 102
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $76,000.00 |
| PUBLIC UTILITY FORCE ACCT WORK (PART) | $5,000.00 |
| ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) | $50,000.00 |
| Total: | $136,000.00 |