Job Info for 6374-41-001

County: GUADALUPE Highway: UA0090 Date: 05/04/2022 (2 years ago) Engineer's Estimate: $651,803 Control Number: 6374-41-001
Project: RMC - 637441001 District: SAN ANTONIO Time: 64 W Type: METAL BEAM GUARDFENCE UPGRADE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $651,803.00
ABOVE ALL CONSTRUCTION   $711,960.80 1
9.23% | $60,157.80
TALBRAN ENTERPRISES LLC   $822,361.00 2
26.17% | $170,558.00
15.51% | $110,400.20
3LW CIVIL LLC   $836,179.00 3
28.29% | $184,376.00
17.45% | $124,218.20
1.68% | $13,818.00
LONE STAR PAVING COMPANY   $1,423,015.70 4
118.32% | $771,212.70
99.87% | $711,054.90
70.18% | $586,836.70

Bid Items

Items: 23, 0 filtered
GUADALUPE UA0090  |  SAN ANTONIO  |  6374-41-001  |  05/04/2022  |  $651,803  |  RMC - 637441001  |  METAL BEAM GUARDFENCE UPGRADE  |  64 W
Item code Description Unit Quantity Engineer's Estimate ABOVE ALL CONSTRUCTION TALBRAN ENTERPRISES LLC 3LW CIVIL LLC LONE STAR PAVING COMPANY
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 244.000 $30.000 $150.000 $55.000 $40.000 $175.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 5,065.000 $2.000 $7.750 $1.000 $6.000 $2.150
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 5,065.000 $1.000 $1.500 $1.000 $3.000 $0.350
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 5,065.000 $3.000 $2.670 $1.000 $3.000 $2.150
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 411.000 $475.000 $250.000 $500.000 $510.000 $650.000
500 6001 MOBILIZATION LS 1.000 $25,000.000 $1.000 $81,000.000 $55,000.000 $130,500.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $1,000.000 $4,000.000 $1.000 $6,000.000 $60,000.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 3,932.000 $32.500 $30.000 $24.000 $25.000 $32.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,330.000 $1,600.000 $3,500.000 $2,300.000 $2,300.000
540 6012 TERMINAL ANCHOR SECTION ADJUSTMENT EA 1.000 $300.000 $1,000.000 $2,500.000 $1,000.000 $715.000
540 6014 SHORT RADIUS LF 75.000 $30.000 $60.000 $40.000 $50.000 $50.000
540 6020 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 258.000 $34.000 $100.000 $85.000 $68.500 $95.000
540 6035 MTL BM GD FEN TRANS (31"-28") EA 3.000 $600.000 $1,200.000 $2,000.000 $800.000 $1,950.000
540 6037 MTL BM GD FEN TRANS (ANCHOR PLATE) EA 4.000 $1,000.000 $800.000 $2,500.000 $500.000 $1,200.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 3,125.000 $2.000 $3.000 $2.000 $2.000 $3.600
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 29.000 $200.000 $200.000 $500.000 $250.000 $180.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 39.000 $3,500.000 $3,100.000 $4,400.000 $3,200.000 $3,900.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 10.000 $300.000 $200.000 $500.000 $250.000 $300.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 69.000 $30.000 $20.000 $50.000 $25.000 $25.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 69.000 $30.000 $20.000 $50.000 $25.000 $40.000
3076 6066 TACK COAT GAL 737.000 $3.000 $20.000 $40.000 $13.000 $4.850
3076 6074 D-GR HMA TY-C SAC-B PG70-22 (EXEMPT) TON 811.000 $85.000 $200.000 $150.000 $225.000 $425.000
6185 6002 TMA (STATIONARY) DAY 64.000 $200.000 $250.000 $1.000 $100.000 $315.000
Totals: $651,803.00 $711,960.80 $822,361.00 $836,179.00 $1,423,015.70