GUADALUPE FM 78 (0025-10-097)

Items: 52

County: GUADALUPE
Length: N/A
Highway: FM 78
District: SAN ANTONIO
Control Number: 0025-10-097
DBE Goal: N/A
Project: STP 2023(558)HES
Guaranty: N/A
Time: 86 WORKING DAYS
Engineer's Estimate: $1,505,464.88
Date: 04/05/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
WILL LOCKETT
ISMAEL SOLALINDE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$1,505,464.88
$1,371,678.58
Over/Under Est: -8.89% -$133,786.30
Over/Under Est: -6.11% -$92,048.24
Amt Left: 3.04% $41,738.06
Subcontractor Percentage Amount
FLASHER EQUIPMENT COMPANY 3.10% $42,522.04
LONE STAR EROSION CONTROL 3.08% $42,247.70
GREYCO CONSTRUCTION, LLC 1.30% $17,831.82
MURRAY CONSTRUCTION 1.03% $14,128.29
H J HENKE, LLC 0.70% $9,601.75
Total: 9.21% $126,331.60

Bid Items & Bid Tabulations

52 Total 0 of 52
GUADALUPE  |  FM 78  |  SAN ANTONIO  |  0025-10-097  |  04/05/2023  |  $1,505,464.88  |  STP 2023(558)HES  |  HAZARD ELIM & SAFETY  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
ACME BRIDGE COMPANY, INC.
PREPARING ROW
STA 30.000 $2,500.000 $1,729.000 $1,440.000
REMOVING CONC (DRIVEWAYS)
SY 123.000 $27.880 $39.000 $22.300
REMOVING STAB BASE & ASPH PAV (0"-10")
SY 717.000 $15.000 $15.250 $33.500
EXCAVATION (ROADWAY)
CY 2,576.000 $22.000 $29.000 $21.900
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 130.000 $50.000 $45.000 $14.600
COMPOST MANUF TOPSOIL (4")
SY 11,516.000 $2.840 $2.340 $2.100
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 11,516.000 $0.570 $0.220 $0.230
DRILL SEED (TEMP)(WARM OR COOL)
SY 11,516.000 $0.250 $0.150 $0.160
VEGETATIVE WATERING
MG 186.000 $38.700 $25.000 $38.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 11,516.000 $2.000 $0.950 $1.000
PROOF ROLLING
HR 5.000 $148.740 $139.000 $92.100
FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS
CY 2,387.000 $50.000 $73.250 $61.700
PRIME COAT(MC-30 OR AE-P)
GAL 1,078.000 $12.130 $8.000 $4.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 5,101.000 $50.000 $40.250 $47.700
PLANE ASPH CONC PAV (2")
SY 11,617.000 $3.000 $1.400 $3.000
PLANE ASPH CONC PAV (6")
SY 1,489.000 $5.830 $5.500 $7.700
MOBILIZATION
LS 1.000 $136,860.440 $137,000.000 $112,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $12,000.000 $4,520.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $42.070 $40.000 $42.300
ROCK FILTER DAMS (REMOVE)
LF 50.000 $12.000 $10.000 $25.400
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $33.990 $24.000 $25.400
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $12.630 $5.000 $2.100
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,084.000 $4.000 $1.950 $2.050
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,084.000 $1.000 $0.500 $0.530
DRIVEWAYS (CONC)
SY 123.000 $122.180 $131.000 $140.000
DRIVEWAYS (ACP)(TYPE 1)
SY 717.000 $64.110 $58.000 $90.700
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 12.000 $271.420 $360.000 $311.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $793.060 $808.000 $865.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $910.450 $975.000 $1,070.000
IN SM RD SN SUP&AM TYS80(1)SB(U)
EA 2.000 $1,233.990 $1,450.000 $1,750.000
REMOVE SM RD SN SUP&AM
EA 8.000 $147.860 $140.000 $130.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 12,400.000 $1.240 $0.690 $1.300
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 12,400.000 $1.120 $0.690 $1.300
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 2.000 $490.810 $449.000 $476.000
PAVEMENT SEALER 4"
LF 5,563.000 $0.380 $0.310 $0.530
PAVEMENT SEALER 6"
LF 6,313.000 $2.100 $0.470 $0.630
PAVEMENT SEALER (MED NOSE)
EA 2.000 $163.920 $147.000 $159.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 6,313.000 $0.740 $0.790 $1.300
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 860.000 $0.870 $0.510 $1.050
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,703.000 $0.960 $0.480 $1.000
REFL PAV MRKR TY I-C
EA 46.000 $6.100 $4.440 $10.600
REFL PAV MRKR TY II-A-A
EA 87.000 $7.080 $4.440 $10.600
ELIM EXT PAV MRK & MRKS (4")
LF 1,000.000 $0.950 $0.870 $2.650
TACK COAT
GAL 720.000 $5.000 $3.500 $3.500
D-GR HMA TY-C PG64-22
TON 2,316.000 $90.000 $97.000 $106.000
SP MIXES SP-C SAC-B PG70-22
TON 1,357.000 $125.000 $105.000 $111.000
BONDING COURSE
GAL 1,435.000 $6.170 $3.500 $4.200
UNDERSEAL COURSE
GAL 1,238.000 $4.100 $3.500 $4.750
GEOGRID BASE REINFORCEMENT (TY II)
SY 7,219.000 $3.270 $1.300 $3.300
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $13,646.790 $6,000.000 $11,500.000
TMA (STATIONARY)
DAY 76.000 $335.380 $250.000 $128.000
TMA (MOBILE OPERATION)
HR 104.000 $105.230 $80.000 $106.000
Totals: $1,505,464.880 $1,371,678.580 $1,413,416.640