Show Job Controls
Bid Cobra

GRIMES SH0105 (6407-57-001)

Items: 22

County: GRIMES
Length: N/A
Highway: SH0105
District: BRYAN
Control Number: 6407-57-001
DBE Goal: N/A
Project: BPM - 640757001
Guaranty: N/A
Time: 24 W
Engineer's Estimate: $249,025.00
Date: 09/20/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$249,025.00
$213,025.00
Over/Under Est: -14.46% -$36,000.00
Over/Under Est: 2.56% $6,375.00
Amt Left: 19.89% $42,375.00
Over/Under Est: 11.2% $27,897.50
Amt Left: 30% $63,897.50
Delta: -8.43% -$21,522.50

Bid Items & Bid Tabulations

22 Total 0 of 22
GRIMES  |  SH0105  |  BRYAN  |  6407-57-001  |  09/20/2022  |  $249,025.00  |  BPM - 640757001  |  BRIDGE PREVENT MAINT  |  24 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBRAN ENTERPRISES LLC
CROSS PLUS CONSTRUCTION, LLC
FORDE CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 5.000 $1,000.000 $1,500.000 $1,100.000 $2,325.000
REMOVE CONC (WINGWALL)
CY 7.000 $360.000 $500.000 $825.000 $1,275.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 2,000.000 $1.250 $1.000 $1.000 $0.400
BROADCAST SEED (TEMP) (WARM)
SY 1,000.000 $0.550 $1.000 $1.000 $0.400
BROADCAST SEED (TEMP) (COOL)
SY 1,000.000 $0.550 $1.000 $1.000 $0.400
VEGETATIVE WATERING
MG 20.000 $85.000 $1.000 $22.000 $120.000
TEMPORARY SPL SHORING
SF 360.000 $50.000 $20.000 $28.000 $22.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 300.000 $60.000 $1.000 $83.000 $30.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 6.000 $50.000 $120.000 $22.000 $230.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 6.000 $200.000 $260.000 $276.000 $240.000
CONC STR REPAIR (EPOXY MORTAR)
SF 4.000 $280.000 $300.000 $303.000 $470.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 100.000 $180.000 $240.000 $275.000 $367.000
CLEANING AND SEALING JOINTS (FOAM)
LF 92.500 $50.000 $130.000 $50.000 $105.000
WINGWALL (FW - 0) (HW=8 FT)
EA 2.000 $20,000.000 $9,000.000 $14,300.000 $28,500.000
MOBILIZATION
LS 1.000 $20,000.000 $20,000.000 $27,500.000 $12,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $6,000.000 $4,500.000 $4,400.000 $7,800.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 400.000 $4.300 $1.000 $11.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 400.000 $1.500 $1.000 $1.000 $3.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 12.000 $720.000 $200.000 $1,650.000 $520.000
REPLACE ELASTOMERIC BEARING PADS
EA 12.000 $6,000.000 $7,500.000 $5,500.000 $6,100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $3,500.000 $1,500.000 $220.000 $3,000.000
TMA (STATIONARY)
DAY 24.000 $250.000 $200.000 $550.000 $175.000
Totals: $249,025.000 $213,025.000 $255,400.000 $276,922.500