Job Info for 0917-17-081

County: GRIMES Highway: CS Date: 08/02/2023 (1 year ago) Engineer's Estimate: $732,188 Control Number: 0917-17-081
Project: STP 2023(205)TAPS District: BRYAN Time: 144 WORKING DAYS Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $732,188.25
FUQUA CONSTRUCTION CO., INC.   $854,654.98 1
16.73% | $122,466.73
LARRY YOUNG PAVING, INC.   $859,199.48 2
17.35% | $127,011.23
0.53% | $4,544.50
ENCINO LANDSCAPE, INC.   $923,758.20 3
26.16% | $191,569.95
8.09% | $69,103.22
7.51% | $64,558.72
TI-ZACK CONCRETE, INC.   $994,202.42 4
35.79% | $262,014.17
16.33% | $139,547.44
7.63% | $70,444.22
TEXCON GENERAL CONTRACTORS   $1,071,510.21 5
46.34% | $339,321.96
25.37% | $216,855.23
7.78% | $77,307.79
TEXAS MATERIALS GROUP, INC.   $1,148,264.20 6
56.83% | $416,075.95
34.35% | $293,609.22
7.16% | $76,753.99
Subcontractor Percentage Amount
CEN TEX HYDROSEED, INC. 3.50% $29,912.93
BATTEN DRILLING, INC. 0.77% $6,580.84
BRAZOS PAVING, INC. 0.71% $6,068.05
LONESTAR TRAFFIC SAFETY, LLC 0.48% $4,102.34
AWP SAFETY 0.33% $2,820.36
Total: 5.79% $49,484.52

Bid Items

Items: 38, 0 filtered
GRIMES CS  |  BRYAN  |  0917-17-081  |  08/02/2023  |  $732,188  |  STP 2023(205)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  144 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FUQUA CONSTRUCTION CO., INC. LARRY YOUNG PAVING, INC. ENCINO LANDSCAPE, INC. TI-ZACK CONCRETE, INC. TEXCON GENERAL CONTRACTORS TEXAS MATERIALS GROUP, INC.
100 6002 PREPARING ROW STA 4.050 $6,500.000 $9,962.428 $1,068.870 $1,000.000 $1,100.000 $4,500.000 $8,400.000
100 6004 PREPARING ROW(TREE)(12" TO 24" DIA) EA 3.000 $2,000.000 $951.118 $926.350 $1,000.000 $1,925.000 $2,000.000 $3,000.000
100 6011 PREPARING ROW(TREE)(24" TO 36" DIA.) EA 2.000 $3,500.000 $2,280.082 $1,710.190 $2,500.000 $3,080.000 $10,000.000 $5,000.000
104 6015 REMOVING CONC (SIDEWALKS) SY 218.000 $12.000 $14.994 $25.630 $40.000 $28.450 $46.500 $40.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 209.000 $16.000 $19.236 $25.620 $40.000 $37.090 $46.500 $40.000
105 6014 REMOVING STAB BASE & ASPH PAV (7"-12") SY 500.000 $16.000 $6.384 $23.940 $40.000 $31.010 $24.000 $33.000
110 6001 EXCAVATION (ROADWAY) CY 25.000 $25.000 $12.012 $80.150 $40.000 $31.010 $50.000 $100.000
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 387.000 $18.500 $16.282 $81.870 $40.000 $120.560 $30.000 $84.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 1,473.000 $3.500 $1.596 $8.540 $30.000 $8.420 $9.650 $10.000
162 6002 BLOCK SODDING SY 1,473.000 $5.500 $4.998 $8.340 $3.000 $6.600 $6.500 $6.000
168 6001 VEGETATIVE WATERING MG 44.200 $25.000 $14.574 $35.680 $1.000 $1.100 $115.000 $36.000
351 6039 FLEX PAVEMENT STRUCTURE REPAIR (8"-12") SY 61.000 $85.000 $119.000 $270.180 $200.000 $126.500 $236.000 $190.000
400 6005 CEM STABIL BKFL CY 17.000 $75.000 $111.230 $319.900 $200.000 $330.000 $338.000 $300.000
416 6001 DRILL SHAFT (18 IN) LF 60.000 $79.000 $168.938 $303.320 $250.000 $440.000 $370.000 $430.000
420 6013 CL C CONC (ABUT) CY 12.440 $1,200.000 $1,572.396 $1,761.730 $1,200.000 $4,235.000 $2,000.000 $3,000.000
423 6004 RETAINING WALL (CONC BLOCK) SF 1,665.000 $60.000 $66.010 $68.860 $60.000 $60.500 $112.000 $150.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 162.000 $150.000 $210.294 $213.410 $200.000 $220.000 $180.000 $315.000
450 6051 RAIL (HANDRAIL)(TY E) LF 57.000 $200.000 $198.184 $136.820 $160.000 $280.500 $262.000 $200.000
465 6005 JCTBOX(COMPL)(PJB)(3FTX3FT) EA 2.000 $4,000.000 $7,121.618 $6,011.010 $10,000.000 $9,350.000 $5,000.000 $7,000.000
479 6001 ADJUSTING MANHOLES EA 1.000 $1,200.000 $1,089.802 $544.970 $800.000 $487.920 $3,300.000 $1,400.000
496 6099 REMOVE STR (RAIL) LF 30.000 $30.000 $37.814 $25.290 $50.000 $27.500 $50.000 $40.000
500 6001 MOBILIZATION LS 1.000 $85,000.000 $77,695.800 $85,201.890 $81,000.000 $62,851.260 $125,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $3,000.000 $12,374.278 $1,623.140 $8,500.000 $4,950.000 $5,000.000 $7,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 496.000 $7.500 $3.920 $7.130 $1.000 $5.500 $5.600 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 493.000 $2.500 $0.966 $2.140 $1.000 $1.100 $1.670 $1.500
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 1,289.000 $5.000 $6.664 $6.410 $1.000 $11.000 $5.000 $4.500
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,289.000 $1.250 $1.680 $1.430 $1.000 $1.100 $1.150 $1.000
530 6004 DRIVEWAYS (CONC) SY 125.000 $75.000 $115.836 $139.170 $120.000 $148.000 $156.000 $130.000
530 6017 DRIVEWAYS (CONC) (HES) SY 594.000 $95.000 $110.236 $139.820 $180.000 $154.720 $167.000 $130.000
531 6003 CONC SIDEWALKS (6") SY 1,365.000 $72.000 $97.902 $94.650 $110.000 $148.000 $122.000 $125.000
531 6004 CURB RAMPS (TY 1) EA 2.000 $2,000.000 $2,695.840 $2,583.350 $2,500.000 $2,790.000 $3,000.000 $2,900.000
531 6010 CURB RAMPS (TY 7) EA 8.000 $2,000.000 $2,792.874 $2,524.560 $2,500.000 $2,790.000 $3,000.000 $2,600.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 2.000 $750.000 $881.258 $961.990 $800.000 $275.000 $800.000 $810.000
644 6071 RELOCATE SM RD SN SUP&AM TY TWT EA 3.000 $475.000 $548.842 $705.450 $300.000 $715.000 $590.000 $720.000
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 87.000 $30.000 $18.676 $64.130 $30.000 $44.000 $26.500 $29.000
4122 6004 THERMO PIPE(18")(HDPE)(TY S)(CSB) LF 55.000 $60.000 $94.262 $185.480 $200.000 $60.500 $90.000 $120.000
4196 6007 PED STL TRUSS BRG SPAN (60 FT) EA 1.000 $160,000.000 $109,480.000 $135,406.720 $120,000.000 $137,500.000 $128,720.000 $110,000.000
6185 6005 TMA (MOBILE OPERATION) DAY 20.000 $350.000 $280.000 $425.120 $300.000 $1.100 $250.000 $300.000
Totals: $732,188.25 $854,655.08 $859,199.49 $923,758.20 $994,202.42 $1,071,510.21 $1,148,264.20