Bid Cobra

GRIMES SH 105 (0315-04-083)

Items: 71

County: GRIMES
Length: N/A
Highway: SH 105
District: BRYAN
Control Number: 0315-04-083
DBE Goal: N/A
Project: F 2023(554)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $2,241,574.57
Date: 04/05/2023 (3 years ago)
Contract Number: N/A
Type: INSTALL TWO-WAY LT TURN LANE
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$2,241,574.57
$2,060,026.16
Over/Under Est: -8.1% -$181,548.41
Over/Under Est: -3.65% -$81,819.94
Amt Left: 4.84% $99,728.47
Over/Under Est: 12.46% $279,281.66
Amt Left: 22.37% $460,830.07
Delta: -16.72% -$361,101.60
$2,628,999.99
Over/Under Est: 17.28% $387,425.42
Amt Left: 27.62% $568,973.83
Delta: -4.29% -$108,143.76
$2,825,938.24
Over/Under Est: 26.07% $584,363.67
Amt Left: 37.18% $765,912.08
Delta: -7.49% -$196,938.25
Subcontractor Percentage Amount
D. I. J. CONSTRUCTION, INC. 4.22% $86,933.10
CEN TEX HYDROSEED, INC. 2.21% $45,526.58
TRAFFIC SIGNS & LINES, LLC 0.48% $9,888.13
DUSTROL, INC. 0.47% $9,682.12
PROFESSIONAL TRAFFIC CONTROL LLC 0.27% $5,562.07
LONESTAR TRAFFIC SAFETY, LLC 0.22% $4,532.06
Total: 7.87% $162,124.06

Bid Items & Bid Tabulations

71 Total 0 of 71
GRIMES  |  SH 105  |  BRYAN  |  0315-04-083  |  04/05/2023  |  $2,241,574.57  |  F 2023(554)  |  INSTL TWO-WAY LT TURN LANE  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
ICON GC, LLC
BRAZOS PAVING, INC.
PREPARING ROW
STA 0.250 $2,000.000 $10,000.000 $10,000.000 $32,239.200 $77,715.100 $73,129.000
REMOVING CONC (RIPRAP)
SY 44.000 $23.500 $33.000 $13.500 $12.570 $39.620 $64.250
REMOVING CONC (DRIVEWAYS)
SY 323.000 $23.500 $20.000 $17.000 $6.850 $58.400 $31.500
EXCAVATION (ROADWAY)
CY 5,798.000 $15.000 $10.000 $11.000 $15.370 $28.460 $25.050
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 3,292.000 $20.000 $15.000 $5.700 $17.400 $4.900 $12.200
FURNISHING AND PLACING TOPSOIL (4")
SY 31,583.000 $1.500 $1.000 $1.000 $1.010 $0.700 $10.300
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 31,583.000 $0.550 $0.520 $0.570 $0.590 $0.700 $0.650
CELL FBR MLCH SEED(TEMP)(WARM)
SY 15,793.000 $0.500 $0.480 $0.520 $0.550 $0.700 $0.600
CELL FBR MLCH SEED(TEMP)(COOL)
SY 15,793.000 $0.500 $0.480 $0.520 $0.550 $0.700 $0.600
VEGETATIVE WATERING
MG 315.800 $26.520 $9.000 $37.000 $33.490 $1.700 $14.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 18,934.000 $20.000 $23.000 $16.850 $25.000 $31.000 $22.350
CEMENT
TON 198.000 $250.000 $230.000 $235.000 $285.000 $255.000 $285.000
CEMENT TREAT(EXIST MATL)(8")
SY 19,976.000 $3.240 $2.000 $2.000 $5.000 $3.700 $4.800
ASPH (AC-20-5TR)
GAL 11,166.000 $5.750 $4.600 $5.740 $4.280 $6.600 $5.650
ASPH (RC-250)
GAL 4,994.000 $5.500 $5.700 $7.210 $5.770 $9.700 $8.000
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 148.000 $200.000 $240.000 $212.000 $185.790 $138.900 $205.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 235.000 $160.000 $220.000 $226.000 $181.770 $181.900 $245.000
PLANE ASPH CONC PAV(4" TO 6")
SY 11,504.000 $4.800 $4.000 $4.990 $2.520 $2.700 $4.750
RIPRAP (CONC)(4 IN)
CY 2.000 $730.000 $950.000 $1,087.000 $1,510.500 $3,342.700 $900.000
RC PIPE (CL III)(18 IN)
LF 192.000 $95.840 $93.000 $65.000 $120.560 $114.400 $86.500
RC PIPE (CL III)(24 IN)
LF 136.000 $127.000 $105.000 $152.000 $135.860 $135.400 $118.000
RC PIPE (CL III)(30 IN)
LF 40.000 $202.770 $249.000 $217.000 $199.500 $155.900 $200.000
RC PIPE (CL III)(36 IN)
LF 90.000 $206.170 $164.000 $310.000 $214.450 $216.000 $264.100
RC PIPE (ARCH)(CL III)(DES 6)
LF 38.000 $450.000 $525.000 $490.000 $312.000 $469.100 $750.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $1,550.000 $1,250.000 $1,087.000 $1,683.210 $1,764.300 $2,250.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 10.000 $2,000.000 $2,000.000 $1,630.000 $2,042.310 $2,167.700 $2,400.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 2.000 $1,980.330 $2,700.000 $2,717.000 $3,040.380 $2,264.900 $2,650.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $2,500.000 $2,900.000 $2,718.000 $3,057.480 $2,458.900 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $5,000.000 $6,200.000 $4,348.000 $4,712.760 $8,479.400 $7,400.000
SET (TY II) (DES 6) (RCP) (6: 1) (P)
EA 2.000 $6,000.000 $7,500.000 $7,065.000 $5,714.820 $4,459.100 $10,660.000
REMOV STR (SET)
EA 15.000 $1,800.000 $400.000 $815.000 $796.100 $738.800 $642.000
REMOV STR (HEADWALL)
EA 2.000 $2,365.000 $900.000 $2,174.000 $951.900 $753.600 $2,500.000
REMOV STR (PIPE)
EA 13.000 $350.000 $1,200.000 $1,300.000 $1,167.180 $10.300 $39.200
MOBILIZATION
LS 1.000 $224,000.000 $176,000.000 $237,250.000 $250,000.000 $200,000.000 $205,470.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $2,000.000 $4,000.000 $5,000.000 $7,625.000 $6,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $45.000 $35.000 $38.000 $39.900 $51.600 $43.700
ROCK FILTER DAMS (REMOVE)
LF 100.000 $27.500 $12.000 $13.000 $13.680 $16.600 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,669.000 $5.000 $4.500 $4.890 $5.130 $5.000 $5.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,669.000 $1.500 $1.000 $1.000 $1.140 $1.400 $1.250
CONC CURB (TY I)
LF 19.000 $30.000 $50.000 $109.000 $75.000 $69.500 $135.000
DRIVEWAYS (CONC)
SY 261.000 $125.000 $130.000 $163.000 $109.480 $170.000 $104.250
DRIVEWAYS (ACP)
SY 854.000 $50.000 $83.000 $91.000 $70.180 $48.400 $61.250
DRIVEWAYS (SURF TREAT)
SY 681.000 $30.000 $65.000 $90.000 $51.640 $47.600 $125.000
CURB RAMPS (TY 3)
EA 2.000 $2,000.000 $3,500.000 $4,000.000 $3,874.180 $2,648.900 $3,170.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 9,188.000 $0.750 $0.430 $0.730 $0.810 $1.200 $0.350
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 9,158.000 $0.750 $0.430 $0.730 $0.810 $1.200 $0.200
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 6.000 $300.000 $340.000 $364.000 $285.000 $379.700 $420.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 1.000 $660.000 $700.000 $740.000 $627.000 $771.800 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 9.000 $800.000 $640.000 $678.000 $969.000 $707.200 $780.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $750.000 $750.000 $809.000 $1,140.000 $843.200 $930.000
REMOVE SM RD SN SUP&AM
EA 6.000 $96.080 $100.000 $147.000 $285.000 $153.000 $168.500
INSTL OM ASSM (OM-2Z)(WFLX)SRF)SRF
EA 2.000 $105.660 $85.000 $93.000 $285.000 $96.400 $106.100
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 15,438.000 $0.600 $0.250 $0.570 $0.570 $0.600 $0.300
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 2,544.000 $0.600 $0.330 $0.570 $0.570 $1.200 $0.400
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 11,682.000 $0.600 $0.250 $0.570 $0.570 $0.600 $0.300
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 31,376.000 $1.040 $0.650 $1.000 $2.280 $1.200 $0.770
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 34,756.000 $1.100 $0.650 $1.000 $2.280 $1.200 $0.770
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 798.000 $1.800 $1.400 $1.000 $2.280 $0.500 $1.380
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 15,438.000 $0.870 $0.570 $0.960 $0.740 $0.700 $0.690
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,544.000 $0.870 $0.520 $0.960 $0.740 $1.200 $0.620
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,682.000 $0.870 $0.570 $0.960 $0.740 $0.700 $0.690
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 31.000 $21.000 $50.000 $22.000 $22.800 $17.000 $62.400
PREFAB PAV MRK TY C (W) (ARROW)
EA 16.000 $240.000 $150.000 $326.000 $404.700 $255.000 $187.250
REFL PAV MRKR TY II-A-A
EA 533.000 $6.000 $7.300 $6.850 $7.980 $4.600 $8.950
ELIM EXT PAV MRK & MRKS (4")
LF 19,862.000 $1.000 $0.370 $0.350 $1.140 $0.800 $0.440
SP MIXES SP-C SAC-B PG64-22
TON 1,939.000 $120.000 $111.000 $104.000 $130.000 $148.500 $141.100
SP MIXES SP-C SAC-A PG70-22
TON 1,997.000 $145.000 $124.000 $121.500 $150.000 $151.900 $159.250
BONDING COURSE
GAL 1,828.000 $4.000 $4.400 $6.000 $6.550 $5.100 $6.450
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,000.000 $5,000.000 $10,700.000 $9,690.000 $19,946.100 $12,180.000
TMA (STATIONARY)
DAY 79.000 $250.000 $240.000 $570.000 $159.600 $209.700 $240.000
TMA (MOBILE OPERATION)
DAY 12.000 $250.000 $240.000 $900.000 $798.000 $396.700 $475.000
Totals: $2,241,574.566 $2,060,026.160 $2,159,754.630 $2,520,856.232 $2,628,999.995 $2,825,938.240