GREGG US 80 (0096-04-071)
Items: 80
County: GREGG
Length: N/A
Highway: US 80
District: TYLER
Control Number: 0096-04-071
DBE Goal: N/A
Project: C 96-4-71
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $3,566,383.09
Date: 03/08/2023 (3 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
KYLE DYKES
STACY WYLIE1
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,566,383.09 | |||
| $3,878,619.61 |
8.75%
$312,236.52
|
|||
| $3,899,859.25 |
9.35%
$333,476.16
|
0.55%
$21,239.64
|
||
| $4,505,455.90 |
26.33%
$939,072.81
|
16.16%
$626,836.29
|
-15.53%
-$605,596.65
|
|
| $4,644,460.75 |
30.23%
$1,078,077.66
|
19.75%
$765,841.14
|
-3.09%
-$139,004.85
|
E
Engineer's Estimate
$3,566,383.09
1
Awarded
$3,878,619.61
Over/Under Est:
8.75%
$312,236.52
$3,899,859.25
Over/Under Est:
9.35%
$333,476.16
Amt Left:
0.55%
$21,239.64
$4,505,455.90
Over/Under Est:
26.33%
$939,072.81
Amt Left:
16.16%
$626,836.29
Delta:
-15.53%
-$605,596.65
$4,644,460.75
Over/Under Est:
30.23%
$1,078,077.66
Amt Left:
19.75%
$765,841.14
Delta:
-3.09%
-$139,004.85
| Subcontractor | Percentage | Amount |
|---|---|---|
| REYNOLDS & KAY, LTD. | 56.89% | $2,367,320.80 |
| STRIPING TECHNOLOGY, L.P. | 1.84% | $76,566.54 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 0.76% | $31,625.31 |
| PANOLA SIGN & BARRICADE, INC. | 0.29% | $12,067.55 |
| ISAACS CONSTRUCTION SERVICES LLC | 0.20% | $8,322.45 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 0.06% | $2,496.73 |
| CHEROKEE SERVICES | 0.00% | $0.00 |
| DUSTROL, INC. | 0.00% | $0.00 |
| Total: | 60.04% | $2,498,399.38 |
Bid Items & Bid Tabulations
80
Total
0 of 80