Job Info for 0901-19-228

County: GRAYSON Highway: VA Date: 04/05/2024 (7 months ago) Engineer's Estimate: $1,810,758 Control Number: 0901-19-228
Project: C 901-19-228 District: PARIS Time: 213 WORKING DAYS Type: BRIDGE MAINTENANCE
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,810,758.00
DCC CONSTRUCTION AND SERVICES, L.L.C.   $1,799,705.00 1
-0.61% | -$11,053.00
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $2,192,001.00 2
21.05% | $381,243.00
21.8% | $392,296.00
ICOS MANAGEMENT, LLC   $2,334,727.00 3
28.94% | $523,969.00
29.73% | $535,022.00
6.51% | $142,726.00
MB WESTERN INDUSTRIAL CONTRACTING CO.   $2,509,752.50 4
38.6% | $698,994.50
39.45% | $710,047.50
7.50% | $175,025.50

Bid Items

Items: 33, 0 filtered
GRAYSON VA  |  PARIS  |  0901-19-228  |  04/05/2024  |  $1,810,758  |  C 901-19-228  |  BRIDGE MAINT  |  213 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DCC CONSTRUCTION AND SERVICES, L.L.C. BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC ICOS MANAGEMENT, LLC MB WESTERN INDUSTRIAL CONTRACTING CO.
100 6002 PREPARING ROW STA 19.000 $1,500.000 $1,000.000 $1,000.000 $1,650.000 $5,000.000
104 6009 REMOVING CONC (RIPRAP) SY 123.000 $100.000 $100.000 $25.000 $220.000 $50.000
104 6028 REMOVING CONC (MISC) SY 185.000 $50.000 $100.000 $25.000 $220.000 $90.000
110 6002 EXCAVATION (CHANNEL) CY 633.000 $60.000 $20.000 $50.000 $220.000 $40.000
110 6003 EXCAVATION (SPECIAL) CY 100.000 $100.000 $100.000 $50.000 $275.000 $350.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 1,362.000 $35.000 $25.000 $25.000 $77.000 $50.000
158 6005 SPEC EXCAV WORK (ORIGINAL) CY 243.000 $75.000 $100.000 $50.000 $275.000 $40.000
400 6005 CEM STABIL BKFL CY 1,237.000 $50.000 $200.000 $300.000 $262.000 $250.000
400 6008 CUT & RESTORE ASPH PAVING SY 135.000 $250.000 $175.000 $400.000 $385.000 $250.000
401 6001 FLOWABLE BACKFILL CY 459.000 $300.000 $200.000 $290.000 $275.000 $250.000
402 6001 TRENCH EXCAVATION PROTECTION LF 75.000 $25.000 $100.000 $75.000 $1.000 $25.000
420 6158 CL C CONC(PILE ENCASEMENT) LF 43.000 $1,000.000 $1,000.000 $1,200.000 $1,100.000 $3,500.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 44.000 $225.000 $125.000 $275.000 $275.000 $350.000
429 6009 CONC STR REPAIR (STANDARD) SF 1.000 $500.000 $5,000.000 $500.000 $550.000 $500.000
432 6001 RIPRAP (CONC)(4 IN) CY 9.000 $600.000 $1,000.000 $650.000 $880.000 $900.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 3,877.000 $150.000 $150.000 $205.000 $198.000 $250.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 631.000 $200.000 $150.000 $225.000 $198.000 $185.000
432 6037 RIPRAP (STONE PROTECTION) (36 IN) CY 475.000 $225.000 $150.000 $225.000 $220.000 $175.000
432 6051 RIPRAP (STONE COMMON)(GROUT)(18 IN) CY 110.000 $500.000 $200.000 $225.000 $440.000 $250.000
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 258.000 $70.000 $60.000 $60.000 $66.000 $87.500
446 6022 CLEAN & PAINT EXIST PILING (SYSTEM I-A) LS 2.000 $20,000.000 $15,000.000 $12,500.000 $16,500.000 $18,000.000
459 6001 GABIONS (GALV) CY 154.000 $275.000 $600.000 $225.000 $220.000 $250.000
464 6005 RC PIPE (CL III)(24 IN) LF 94.000 $75.000 $300.000 $135.000 $302.000 $150.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 1.000 $1,200.000 $4,000.000 $1,500.000 $4,400.000 $3,000.000
467 6580 SET (REMOV & REINSTALL) EA 1.000 $1,500.000 $1,000.000 $1,500.000 $5,500.000 $1,200.000
496 6007 REMOV STR (PIPE) LF 100.000 $10.000 $100.000 $20.000 $11.000 $55.000
496 6079 REMOVE STR (PILING) EA 19.000 $300.000 $500.000 $500.000 $2,200.000 $500.000
500 6001 MOBILIZATION LS 1.000 $200,000.000 $150,000.000 $200,000.000 $1.000 $175,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 13.000 $8,000.000 $3,000.000 $2,000.000 $1.000 $5,000.000
738 6011 CLEANING / SWEEPING (HANDWORK) SY 187.000 $4.000 $20.000 $3.000 $330.000 $7.500
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 30.000 $125.000 $500.000 $100.000 $385.000 $100.000
6185 6002 TMA (STATIONARY) DAY 100.000 $225.000 $400.000 $200.000 $275.000 $200.000
7000 6001 REML & DISPL DRIFTWOOD & DEBRIS CY 283.000 $125.000 $100.000 $100.000 $55.000 $100.000
Totals: $1,810,758.00 $1,799,705.00 $2,192,001.00 $2,334,727.00 $2,509,752.50