Job Info for 0045-19-065

County: GRAYSON Highway: US 82 Date: 08/02/2023 (1 year ago) Engineer's Estimate: $2,883,292 Control Number: 0045-19-065
Project: F 2B23(047) District: PARIS Time: 156 WORKING DAYS Type: HIGHWAY IMPROVEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,883,292.45
FNH CONSTRUCTION, LLC   $3,393,359.00 1
17.69% | $510,066.55
WEBBER, LLC   $3,421,222.22 2
18.66% | $537,929.77
0.82% | $27,863.22
ED BELL CONSTRUCTION COMPANY   $3,459,889.00 3
20% | $576,596.55
1.96% | $66,530.00
1.13% | $38,666.78
Subcontractor Percentage Amount
AARON CONCRETE CONTRACTORS, LLC 12.78% $433,671.28
KING GEORGE TRAFFIC SOLUTIONS LLC 1.03% $34,951.60
SOUTHWEST ENVIRONMENT SERVICES LLC 0.73% $24,771.52
BARRICADES UNLIMITED 0.35% $11,876.76
WEST TEXAS ROCK RESOURCES, LLC 0.12% $4,072.03
ROYAL REBAR 0.00% $0.00
Total: 15.01% $509,343.19

Bid Items

Items: 42, 0 filtered
GRAYSON US 82  |  PARIS  |  0045-19-065  |  08/02/2023  |  $2,883,292  |  F 2B23(047)  |  HWY IMPRV  |  156 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FNH CONSTRUCTION, LLC WEBBER, LLC ED BELL CONSTRUCTION COMPANY
104 6023 REMOVING CONC (CTB) LF 95.000 $30.000 $85.000 $35.000 $70.000
104 6044 REMOVING CONC (FLUME) SY 112.000 $150.000 $100.000 $100.000 $50.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 1,003.000 $15.000 $50.000 $30.400 $9.000
112 6001 SUBGRADE WIDENING (ORD COMP) STA 120.000 $1,250.000 $450.000 $1,550.000 $2,800.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 6,048.000 $40.000 $50.000 $41.000 $50.000
134 6008 BACKFILL (TY A OR B) CY 3.000 $55.000 $1,000.000 $511.000 $2,000.000
162 6002 BLOCK SODDING SY 1,985.000 $8.000 $6.000 $6.100 $6.500
164 6009 BROADCAST SEED (TEMP) (WARM) SY 47,038.000 $1.000 $0.500 $0.100 $0.130
164 6011 BROADCAST SEED (TEMP) (COOL) SY 47,038.000 $1.000 $0.500 $0.100 $0.130
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 94,076.000 $1.000 $0.500 $0.300 $0.500
168 6001 VEGETATIVE WATERING MG 282.000 $45.000 $30.000 $70.450 $95.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 5,360.000 $4.350 $20.000 $8.550 $6.500
420 6005 CL A CONC (CURB OUTLET)(TY I) EA 4.000 $1,500.000 $12,500.000 $2,900.000 $7,000.000
420 6007 CL A CONC (FLUME) CY 24.000 $575.000 $1,000.000 $882.000 $1,200.000
500 6001 MOBILIZATION LS 1.000 $258,317.500 $300,000.000 $342,100.170 $290,031.470
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $7,000.000 $8,500.000 $34,210.000 $20,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 700.000 $4.000 $4.000 $3.000 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 700.000 $1.250 $2.000 $1.000 $2.500
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 2,200.000 $55.000 $85.000 $73.000 $40.000
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 1,200.000 $9.000 $20.000 $20.000 $15.000
512 6053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) LF 2,200.000 $20.000 $20.000 $19.500 $20.000
514 6001 PERM CTB (SGL SLOPE) (TY 1) (42 ) LF 12,054.000 $115.000 $125.000 $124.650 $123.000
514 6047 PERM CTB (SGL SLOPE)(TY 1)(TRANSITION) LF 150.000 $175.000 $200.000 $344.000 $350.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 12,054.000 $0.600 $0.500 $0.350 $0.400
542 6001 REMOVE METAL BEAM GUARD FENCE LF 810.000 $5.000 $3.000 $3.050 $10.500
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 6.000 $350.000 $500.000 $254.000 $840.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 6.000 $350.000 $1,500.000 $254.000 $840.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 1.000 $2,000.000 $6,500.000 $3,113.000 $1,600.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 1.000 $1,500.000 $2,500.000 $2,347.000 $800.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 1.000 $12,000.000 $3,000.000 $8,976.000 $12,500.000
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 836.000 $30.000 $100.000 $23.300 $52.500
658 6027 INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI) EA 1,254.000 $24.000 $100.000 $20.150 $52.500
658 6100 INSTL OM ASSM (OM-2Z)(WFLX)GND(BI) EA 20.000 $115.000 $100.000 $104.200 $210.000
662 6046 WK ZN PAV MRK REMOV (REFL) TY I-A EA 1,723.000 $11.000 $6.000 $3.700 $6.000
662 6048 WK ZN PAV MRK REMOV (REFL) TY I-C EA 2,585.000 $6.000 $6.000 $3.700 $6.000
662 6052 WK ZN PAV MRK REMOV (REFL) TY II-C-R EA 325.000 $6.000 $6.000 $4.050 $6.000
666 6167 REFL PAV MRK TY II (W) 4" (BRK) LF 13,477.000 $1.000 $2.000 $0.800 $1.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 13,477.000 $1.150 $2.000 $0.600 $0.750
3076 6069 D-GR HMA TY-C SAC-B PG64-22 (EXEMPT) TON 597.000 $100.000 $200.000 $168.000 $180.400
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $13,000.000 $16,500.000 $21,974.000 $15,000.000
6185 6002 TMA (STATIONARY) DAY 25.000 $275.000 $250.000 $500.000 $275.000
6185 6005 TMA (MOBILE OPERATION) DAY 75.000 $400.000 $55.000 $800.000 $1,000.000
Totals: $2,883,292.45 $3,393,359.00 $3,421,222.22 $3,459,889.00