Job Info for 0045-18-038

County: GRAYSON Highway: US 82 Date: 04/03/2019 (5 years ago) Engineer's Estimate: $7,649,585 Control Number: 0045-18-038
Project: NH 2019(723) District: PARIS Time: 93 WORKING DAYS Type: OVERLAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $7,649,584.98
AUSTIN BRIDGE & ROAD SERVICES, LP   $7,390,532.53 1
-3.39% | -$259,052.45
EUROVIA ATLANTIC COAST LLC   $7,727,693.89 2
1.02% | $78,108.91
4.56% | $337,161.36
JAGOE-PUBLIC COMPANY   $8,122,138.84 3
6.18% | $472,553.86
9.9% | $731,606.31
5.10% | $394,444.95
RK HALL, LLC   $8,442,981.08 4
10.37% | $793,396.10
14.24% | $1,052,448.55
3.95% | $320,842.24

Bid Items

Items: 49, 0 filtered
GRAYSON US 82  |  PARIS  |  0045-18-038  |  04/03/2019  |  $7,649,585  |  NH 2019(723)  |  OVERLAY  |  93 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate AUSTIN BRIDGE & ROAD SERVICES, LP EUROVIA ATLANTIC COAST LLC JAGOE-PUBLIC COMPANY RK HALL, LLC
104 6054 REMOVING CONCRETE(MOW STRIP) LF 735.000 $8.000 $6.000 $19.000 $35.370 $11.940
105 6019 REMOVING STAB BASE & ASPH PAV(14") SY 1,319.000 $4.650 $7.000 $11.000 $8.420 $9.200
110 6001 EXCAVATION (ROADWAY) CY 494.000 $14.000 $18.000 $25.000 $18.500 $20.570
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 386.000 $25.000 $73.000 $35.000 $90.000 $30.140
134 6001 BACKFILL (TY A) STA 1,206.000 $300.000 $147.000 $250.000 $212.000 $194.090
164 6009 BROADCAST SEED (TEMP) (WARM) SY 42,324.000 $0.200 $0.140 $0.130 $0.070 $0.120
164 6011 BROADCAST SEED (TEMP) (COOL) SY 42,324.000 $0.100 $0.140 $0.130 $0.070 $0.120
164 6015 STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY) SY 84,646.000 $0.250 $0.300 $0.260 $0.210 $0.230
168 6001 VEGETATIVE WATERING MG 2,031.000 $13.000 $44.100 $32.000 $23.920 $23.000
314 6013 EMULS ASPH (EROSN CONT)(CSS-1H) GAL 25,395.000 $3.600 $3.350 $2.500 $3.500 $4.060
340 6011 D-GR HMA(SQ) TY-B PG64-22 TON 580.000 $90.000 $94.000 $78.000 $78.000 $101.890
341 6020 D-GR HMA TY-C SAC-A PG64-22 TON 59,917.000 $72.000 $77.900 $82.000 $92.250 $90.180
351 6008 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 4,800.000 $65.000 $89.000 $75.000 $60.500 $110.550
354 6022 PLANE ASPH CONC PAV(0" TO 3") SY 532,062.000 $2.400 $0.950 $1.270 $1.310 $1.480
400 6008 CUT & RESTORE ASPH PAVING SY 27.000 $111.000 $230.000 $150.000 $90.000 $134.710
401 6001 FLOWABLE BACKFILL CY 16.000 $125.000 $300.000 $250.000 $246.310 $250.330
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 36.000 $455.000 $510.000 $700.000 $1,157.890 $1,015.210
464 6005 RC PIPE (CL III)(24 IN) LF 64.000 $70.000 $100.000 $115.000 $158.020 $108.350
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 2.000 $1,030.000 $1,500.000 $1,500.000 $1,252.970 $1,360.650
496 6004 REMOV STR (SET) EA 2.000 $400.000 $250.000 $400.000 $425.960 $818.070
496 6007 REMOV STR (PIPE) LF 54.000 $12.000 $6.000 $23.000 $13.200 $19.510
500 6001 MOBILIZATION LS 1.000 $689,318.100 $735,000.000 $600,000.000 $600,000.000 $500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $15,000.000 $19,750.000 $17,000.000 $3,500.000 $14,442.010
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 50.000 $55.000 $89.010 $42.000 $47.370 $46.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 50.000 $10.000 $26.280 $10.000 $21.050 $11.500
530 6005 DRIVEWAYS (ACP) SY 2,136.000 $29.000 $39.100 $45.000 $16.000 $119.450
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 244,972.000 $0.140 $0.150 $0.150 $0.180 $0.090
543 6001 CABLE BARRIER SYSTEM (TL-3) LF 703.000 $25.000 $19.000 $14.500 $42.110 $14.330
543 6019 CABLE BARRIER TERMINAL SECTION (TL-3) EA 1.000 $3,750.000 $2,600.000 $4,300.000 $5,894.720 $4,777.480
543 6021 REMOVE CABLE BARRIER LF 703.000 $7.000 $3.000 $5.000 $11.580 $4.780
543 6022 REMOVE CABLE BARRIER TERMINAL SECTION EA 1.000 $1,000.000 $700.000 $1,000.000 $2,105.260 $1,194.370
658 6050 INSTL OM ASSM (OM-2Z)(FLX)SRF EA 3.000 $85.000 $50.000 $200.000 $94.740 $238.870
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 31,180.000 $0.200 $0.500 $0.550 $0.420 $0.400
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 6,840.000 $0.550 $0.650 $0.700 $0.530 $0.630
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 10,745.000 $1.300 $1.000 $2.500 $0.550 $1.010
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 7,455.000 $0.700 $0.840 $0.910 $0.880 $1.120
666 6053 REFL PAV MRK TY I (W)(ARROW)(090MIL) EA 42.000 $105.000 $130.000 $140.000 $142.630 $132.250
666 6074 REFL PAV MRK TY I (W)(NUMBER)(090MIL) EA 4.000 $475.000 $226.000 $250.000 $126.320 $178.250
666 6077 REFL PAV MRK TY I (W)(WORD)(090MIL) EA 42.000 $140.000 $156.000 $170.000 $174.210 $155.250
666 6224 PAVEMENT SEALER 4" LF 4,992.000 $0.130 $0.120 $0.130 $0.260 $0.290
666 6299 RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) LF 31,180.000 $0.470 $0.400 $0.430 $0.440 $0.470
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 124,692.000 $0.380 $0.380 $0.410 $0.390 $0.410
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 124,692.000 $0.370 $0.380 $0.410 $0.390 $0.410
672 6010 REFL PAV MRKR TY II-C-R EA 3,119.000 $4.050 $5.000 $5.400 $3.680 $3.970
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 4,992.000 $0.500 $1.000 $1.100 $1.050 $1.150
678 6001 PAV SURF PREP FOR MRK (4") LF 4,992.000 $0.070 $0.200 $0.250 $0.210 $0.290
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $13,500.000 $16,500.000 $7,500.000 $7,500.000 $7,066.240
6185 6002 TMA (STATIONARY) DAY 68.000 $250.000 $375.000 $1,000.000 $446.000 $570.500
6185 6005 TMA (MOBILE OPERATION) DAY 28.000 $250.000 $715.000 $750.000 $1,250.000 $830.710
Totals: $7,649,584.98 $7,390,532.53 $7,727,693.89 $8,122,138.84 $8,442,981.08