Show Job Controls
Bid Cobra

GONZALES US 183 (0153-02-040)

Items: 62

County: GONZALES
Length: N/A
Highway: US 183
District: YOAKUM
Control Number: 0153-02-040
DBE Goal: N/A
Project: NH 1802(495)
Guaranty: N/A
Time: 160 WORKING DAYS
Engineer's Estimate: $7,207,873.45
Date: 08/08/2018 (7 years ago)
Contract Number: N/A
Type: PAVEMENT REPAIR AND RESURFACING; MILLED R. STRIPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$7,207,873.45
$6,756,349.44
Over/Under Est: -6.26% -$451,524.01
Over/Under Est: -3.24% -$233,300.79
Amt Left: 3.23% $218,223.22
$7,714,388.99
Over/Under Est: 7.03% $506,515.54
Amt Left: 14.18% $958,039.55
Delta: -10.61% -$739,816.33
Over/Under Est: 10.41% $750,696.98
Amt Left: 17.79% $1,202,220.99
Delta: -3.17% -$244,181.44
Over/Under Est: 10.92% $787,380.22
Amt Left: 18.34% $1,238,904.23
Delta: -0.46% -$36,683.24

Bid Items & Bid Tabulations

62 Total 0 of 62
GONZALES  |  US 183  |  YOAKUM  |  0153-02-040  |  08/08/2018  |  $7,207,873.45  |  NH 1802(495)  |  PAVMT REPAIR AND RESURF; MILLED R. S...  |  160 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
AUSTIN MATERIALS, LLC
LONE STAR PAVING COMPANY
DEAN WORD COMPANY, LTD.
REMOVING CONC (DRIVEWAYS)
SY 305.000 $25.000 $9.990 $18.000 $16.000 $15.000 $20.280
REMOVING CONCRETE(MOW STRIP)
LF 3,823.250 $10.000 $2.520 $10.000 $6.000 $5.000 $10.847
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 110.000 $25.000 $18.570 $104.000 $20.000 $30.000 $35.920
BACKFILL (TY A OR B)
STA 793.330 $100.000 $78.000 $129.000 $94.000 $60.000 $155.844
BLADING
HR 60.000 $100.000 $85.500 $100.000 $155.000 $95.000 $104.093
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 3,900.000 $0.500 $0.400 $0.350 $0.350 $1.000 $0.416
BROADCAST SEED (TEMP) (WARM)
SY 975.000 $0.300 $0.300 $0.900 $0.870 $1.000 $0.312
BROADCAST SEED (TEMP) (COOL)
SY 975.000 $0.300 $0.300 $0.900 $0.870 $1.000 $0.312
VEGETATIVE WATERING
MG 65.700 $60.000 $16.650 $84.000 $20.000 $25.000 $58.650
PRIME COAT (MULTI OPTION)
GAL 13,222.000 $3.100 $3.050 $3.300 $3.050 $3.000 $0.978
AGGR(TY-PE GR-4 SAC-B)
CY 1,664.000 $80.000 $57.180 $65.000 $95.000 $125.000 $71.410
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 73,515.000 $3.000 $3.140 $3.000 $2.200 $3.250 $3.324
D-GR HMA TY-D SAC-B PG64-22
TON 26,196.000 $70.000 $59.180 $63.000 $71.500 $75.000 $65.181
D-GR HMA TY-D SAC-B PG70-22
TON 48,495.000 $70.000 $62.760 $65.500 $72.500 $75.000 $65.424
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,500.000 $30.000 $24.730 $30.500 $32.000 $35.000 $22.143
PLANE ASPH CONC PAV(0" TO 2")
SY 91,816.000 $2.000 $1.020 $1.100 $1.750 $1.250 $1.736
PLANE ASPH CONC PAV (2")
SY 97,585.000 $2.000 $1.020 $1.000 $2.350 $1.250 $2.132
CLEANING AND SEALING EXISTING JOINTS
LF 1,914.000 $25.000 $18.440 $20.000 $18.440 $20.000 $19.178
MOBILIZATION
LS 1.000 $1.000 $484,554.690 $275,000.000 $467,000.000 $265,000.000 $879,388.111
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $3,000.000 $3,361.900 $3,500.000 $1,600.000 $3,500.000 $1,632.415
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $5.000 $5.000 $5.300 $5.000 $5.000 $5.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $2.000 $3.000 $2.650 $2.500 $3.000 $3.120
DRIVEWAYS (CONC)
SY 305.000 $100.000 $83.900 $68.000 $100.000 $85.000 $83.096
TURNOUTS (SURF TREAT)
SY 4,952.000 $30.000 $14.190 $18.750 $2.900 $2.500 $1.733
RUMBLE STRIPS (SHOULDER)
LF 282,334.000 $0.150 $0.120 $0.150 $0.110 $0.150 $0.173
RUMBLE STRIPS (CENTERLINE)
LF 141,688.000 $0.150 $0.150 $0.150 $0.120 $0.150 $0.201
MTL W-BEAM GD FEN (TIM POST)
LF 4,950.000 $20.000 $17.500 $22.700 $21.450 $18.000 $22.308
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 40.000 $1,500.000 $1,950.000 $2,060.000 $1,445.000 $1,500.000 $1,502.800
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 112.500 $50.000 $58.000 $57.650 $54.430 $60.000 $56.607
REMOVE METAL BEAM GUARD FENCE
LF 5,962.500 $1.500 $3.000 $1.050 $1.000 $3.000 $1.040
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $200.000 $75.000 $132.400 $125.000 $80.000 $130.000
GUARDRAIL END TREATMENT (INSTALL)
EA 51.000 $2,200.000 $2,400.000 $2,765.000 $2,615.000 $2,500.000 $2,719.600
GUARDRAIL END TREATMENT (REMOVE)
EA 45.000 $200.000 $200.000 $132.000 $125.000 $200.000 $130.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,000.000 $1,000.000 $1,050.000 $1,000.000 $1,000.000 $1,040.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $20,000.000 $23,000.000 $19,500.000 $18,500.000 $20,000.000 $19,240.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 178.000 $30.000 $20.000 $14.500 $13.750 $20.000 $14.300
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 21,386.000 $0.200 $0.300 $0.320 $0.300 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (W)4"(DOT)
LF 2,082.000 $0.200 $0.160 $0.170 $0.160 $1.000 $1.040
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 328,213.000 $0.150 $0.160 $0.170 $0.160 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,430.000 $0.500 $0.300 $0.320 $0.300 $1.000 $1.040
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 7,555.000 $0.200 $0.160 $0.170 $0.160 $0.500 $0.520
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 290,774.000 $0.150 $0.160 $0.170 $0.160 $0.500 $0.520
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,812.000 $1.250 $1.250 $0.750 $1.000 $0.500 $1.321
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 16,026.000 $1.250 $1.250 $0.750 $1.000 $0.500 $1.321
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 425.000 $1.250 $0.750 $0.790 $0.750 $1.500 $1.560
REFL PAV MRK TY I(W)(LNDP ARW)(090MIL)
EA 6.000 $300.000 $350.000 $370.670 $350.000 $450.000 $457.600
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 70.000 $20.000 $10.000 $10.590 $10.000 $20.000 $20.800
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $300.000 $250.000 $264.760 $250.000 $300.000 $312.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $300.000 $250.000 $264.760 $250.000 $300.000 $312.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 800.000 $15.000 $10.000 $10.590 $10.000 $15.000 $14.560
REFL PAV MRKR TY I-C
EA 439.000 $3.500 $5.000 $5.300 $5.000 $5.000 $5.200
REFL PAV MRKR TY II-A-A
EA 3,290.000 $3.500 $3.000 $3.180 $3.000 $5.000 $4.618
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 5,862.000 $1.500 $0.920 $0.790 $0.550 $5.000 $1.418
LONG CHANNEL MOUNT CURB SYS (INSTALL)
LF 350.000 $50.000 $65.000 $69.000 $65.000 $65.000 $67.600
REFL PAV MRK AWT (W) (4")(SLD)(125 MIL)
LF 158,443.000 $0.300 $0.500 $0.530 $0.500 $0.600 $0.624
REFL PAV MRK AWT (W) (4")(BRK)(125 MIL)
LF 9,887.000 $0.350 $0.500 $0.530 $0.500 $0.690 $0.676
REFL PAV MRK AWT (W) (4")(DOT)(125 MIL)
LF 1,041.000 $0.400 $0.500 $0.530 $0.500 $1.000 $1.040
REFL PAV MRK AWT (Y) (4")(SLD)(125 MIL)
LF 145,931.000 $0.300 $0.500 $0.530 $0.500 $0.600 $0.624
REFL PAV MRK AWT (Y) (4")(BRK)(125 MIL)
LF 18,685.000 $0.350 $0.500 $0.530 $0.500 $0.690 $0.676
REFL PAV MRK AWT (Y) (4")(DOT)(125 MIL)
LF 95.000 $0.400 $0.500 $0.530 $0.500 $2.500 $2.600
TMA (STATIONARY)
EA 2.000 $10,000.000 $8,118.750 $10,000.000 $19,800.000 $2,500.000 $26,250.000
TMA (MOBILE OPERATION)
DAY 12.000 $500.000 $108.250 $500.000 $450.000 $475.000 $468.000
Totals: $7,207,873.450 $6,756,349.445 $6,974,572.670 $7,714,388.995 $7,958,570.430 $7,995,253.750