PREPARING ROW
|
STA
|
793.110
|
$500.000
|
$27.750
|
$119.810
|
$310.830
|
$265.570
|
$250.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (6")
|
SY
|
1,592.000
|
$5.000
|
$7.190
|
$5.010
|
$3.330
|
$8.830
|
$12.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
14,931.000
|
$5.000
|
$8.720
|
$7.880
|
$11.220
|
$11.780
|
$8.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
17,015.000
|
$10.000
|
$6.040
|
$8.100
|
$11.220
|
$10.820
|
$13.000
|
|
|
BLADING
|
HR
|
179.000
|
$100.000
|
$44.100
|
$100.110
|
$96.900
|
$100.000
|
$125.000
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
657,619.000
|
$0.300
|
$0.500
|
$0.180
|
$0.310
|
$0.300
|
$0.250
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
164,409.000
|
$0.300
|
$0.470
|
$0.250
|
$0.250
|
$0.250
|
$0.190
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
164,409.000
|
$0.300
|
$0.470
|
$0.250
|
$0.250
|
$0.250
|
$0.190
|
|
|
VEGETATIVE WATERING
|
MG
|
17,985.000
|
$20.000
|
$16.880
|
$3.000
|
$3.330
|
$18.000
|
$3.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
500.000
|
$1.000
|
$5.550
|
$4.000
|
$4.080
|
$4.000
|
$3.500
|
|
|
PROOF ROLLING
|
HR
|
179.000
|
$100.000
|
$27.750
|
$70.290
|
$85.500
|
$60.000
|
$79.000
|
|
|
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
|
CY
|
67,357.000
|
$65.000
|
$83.750
|
$71.460
|
$70.840
|
$76.990
|
$76.000
|
|
|
REWORK BS MTL (TY C) (9") (DENS CONT)
|
SY
|
316,754.000
|
$3.500
|
$0.830
|
$1.790
|
$1.710
|
$1.550
|
$1.550
|
|
|
LIME (HYDRATED LIME (SLURRY))
|
TON
|
2,148.000
|
$200.000
|
$184.360
|
$167.620
|
$168.000
|
$267.070
|
$230.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
119,331.000
|
$3.250
|
$2.560
|
$2.980
|
$2.280
|
$3.670
|
$3.100
|
|
|
CEMENT
|
TON
|
7,210.300
|
$150.000
|
$170.950
|
$157.250
|
$164.850
|
$157.000
|
$175.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
5,755.000
|
$1.500
|
$2.180
|
$1.600
|
$1.940
|
$10.790
|
$7.000
|
|
|
CEMENT TREAT(MX EXST MTL & NW BS)(12")
|
SY
|
388,820.000
|
$2.750
|
$1.210
|
$2.350
|
$2.850
|
$3.140
|
$2.500
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
124,424.000
|
$3.000
|
$2.520
|
$3.730
|
$3.830
|
$3.050
|
$4.600
|
|
|
ASPH (RC-250)
|
GAL
|
77,788.000
|
$4.000
|
$4.130
|
$3.160
|
$4.470
|
$4.350
|
$4.000
|
|
|
AGGR(TY-B GR-5 SAC-B)
|
CY
|
2,877.500
|
$90.000
|
$130.830
|
$103.530
|
$71.870
|
$116.750
|
$140.000
|
|
|
ASPH(AC-15P, HFRS-2P OR CRS-2P)
|
GAL
|
104,977.000
|
$3.500
|
$2.810
|
$3.530
|
$3.830
|
$3.550
|
$3.500
|
|
|
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
|
CY
|
3,528.600
|
$90.000
|
$96.720
|
$95.070
|
$94.410
|
$99.500
|
$130.000
|
|
|
AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B)
|
CY
|
4,576.100
|
$65.000
|
$132.880
|
$90.810
|
$95.180
|
$99.500
|
$120.000
|
|
|
CEM STABIL BKFL
|
CY
|
95.000
|
$125.000
|
$105.450
|
$115.000
|
$157.200
|
$95.000
|
$220.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
83.000
|
$160.000
|
$316.350
|
$85.000
|
$125.000
|
$200.000
|
$25.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
132.000
|
$15.000
|
$5.550
|
$10.000
|
$5.960
|
$20.000
|
$8.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
315.000
|
$15.000
|
$16.650
|
$22.000
|
$18.400
|
$32.000
|
$25.000
|
|
|
RIPRAP (CONC)(CL C)
|
CY
|
160.000
|
$550.000
|
$471.750
|
$545.000
|
$573.390
|
$439.340
|
$520.000
|
|
|
RIPRAP (CONC)(DISSIPATER)
|
CY
|
15.300
|
$1,200.000
|
$2,053.500
|
$1,650.000
|
$908.370
|
$782.790
|
$780.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
60.000
|
$450.000
|
$471.750
|
$485.000
|
$625.000
|
$428.630
|
$650.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
363.000
|
$20.000
|
$41.070
|
$15.500
|
$28.000
|
$36.500
|
$30.000
|
|
|
RETROFIT RAIL (TY SSTR)
|
LF
|
481.000
|
$150.000
|
$249.750
|
$130.000
|
$158.720
|
$164.330
|
$215.000
|
|
|
GABION MATTRESSES (PVC)(12 IN)
|
SY
|
65.000
|
$80.000
|
$149.850
|
$155.000
|
$135.000
|
$82.560
|
$145.000
|
|
|
GABIONS (PVC)( 3FT X 3 FT)
|
CY
|
78.000
|
$250.000
|
$316.350
|
$210.000
|
$285.000
|
$256.190
|
$310.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,494.000
|
$60.000
|
$65.490
|
$77.500
|
$67.340
|
$67.960
|
$73.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
2,004.000
|
$75.000
|
$75.480
|
$87.750
|
$83.500
|
$90.620
|
$85.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
128.000
|
$100.000
|
$116.550
|
$105.050
|
$115.040
|
$137.850
|
$105.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
272.000
|
$120.000
|
$132.090
|
$159.500
|
$159.340
|
$180.230
|
$140.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
130.000
|
$200.000
|
$179.270
|
$260.680
|
$240.080
|
$310.820
|
$210.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
4.000
|
$10,000.000
|
$10,933.500
|
$12,500.000
|
$13,457.100
|
$10,745.000
|
$11,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
68.000
|
$1,300.000
|
$1,276.500
|
$1,375.000
|
$1,702.900
|
$1,281.950
|
$1,400.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
7.000
|
$1,200.000
|
$1,443.000
|
$1,592.500
|
$2,023.580
|
$1,482.210
|
$1,700.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
27.000
|
$1,800.000
|
$1,665.000
|
$1,595.500
|
$2,023.450
|
$1,607.420
|
$1,800.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
84.000
|
$1,400.000
|
$1,720.500
|
$1,700.000
|
$2,153.020
|
$1,715.630
|
$2,100.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
17.000
|
$1,900.000
|
$2,497.500
|
$1,950.050
|
$2,316.940
|
$1,931.340
|
$2,100.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (C)
|
EA
|
7.000
|
$2,800.000
|
$4,273.500
|
$2,075.000
|
$2,316.610
|
$1,980.170
|
$2,100.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$2,500.000
|
$4,828.500
|
$2,350.000
|
$4,617.100
|
$4,274.380
|
$2,800.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
14.000
|
$3,000.000
|
$4,995.000
|
$2,950.000
|
$4,713.400
|
$4,003.050
|
$2,900.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (C)
|
EA
|
8.000
|
$3,200.000
|
$5,422.350
|
$3,250.000
|
$5,107.870
|
$4,288.390
|
$3,200.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$3,200.000
|
$6,493.500
|
$4,055.050
|
$5,956.910
|
$4,921.530
|
$4,200.000
|
|
|
SET (TY II) (48 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$8,500.000
|
$14,263.500
|
$10,296.270
|
$11,254.830
|
$11,167.420
|
$9,600.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
43.000
|
$1,600.000
|
$1,942.500
|
$1,500.000
|
$2,383.930
|
$1,000.000
|
$930.000
|
|
|
REMOV STR (PIPE)
|
LF
|
368.000
|
$10.000
|
$8.880
|
$10.910
|
$14.910
|
$26.040
|
$11.000
|
|
|
REMOV STR (PIPE)
|
EA
|
85.000
|
$500.000
|
$316.350
|
$29.740
|
$731.850
|
$285.000
|
$460.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$985,000.000
|
$650,475.780
|
$1,659,339.410
|
$1,208,704.560
|
$787,690.000
|
$1,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
22.000
|
$3,500.000
|
$6,584.150
|
$3,355.750
|
$2,818.250
|
$3,912.000
|
$5,400.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
400.000
|
$35.000
|
$68.820
|
$30.000
|
$30.600
|
$30.000
|
$29.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
400.000
|
$15.000
|
$11.100
|
$10.000
|
$10.200
|
$10.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$15.000
|
$16.650
|
$18.000
|
$18.360
|
$18.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$5.000
|
$11.100
|
$6.000
|
$6.120
|
$6.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
500.000
|
$3.000
|
$5.550
|
$4.500
|
$4.590
|
$4.500
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
500.000
|
$1.000
|
$2.220
|
$2.000
|
$2.040
|
$2.000
|
$1.800
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
5,844.000
|
$7.500
|
$6.660
|
$3.250
|
$3.310
|
$3.250
|
$6.200
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
4,008.000
|
$6.000
|
$7.220
|
$4.950
|
$5.050
|
$4.950
|
$8.200
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
9,852.000
|
$2.000
|
$1.670
|
$1.000
|
$1.020
|
$1.000
|
$1.250
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
2,816.000
|
$80.000
|
$62.930
|
$93.720
|
$102.600
|
$30.000
|
$92.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
780.000
|
$30.000
|
$25.480
|
$28.500
|
$40.000
|
$66.550
|
$80.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
750.000
|
$10.000
|
$17.680
|
$8.000
|
$20.000
|
$18.660
|
$25.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
780.000
|
$10.000
|
$25.480
|
$14.000
|
$20.000
|
$30.770
|
$29.000
|
|
|
CONCRETE CURB (SPECIAL)
|
LF
|
335.000
|
$35.000
|
$38.850
|
$12.050
|
$23.640
|
$29.710
|
$53.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
7,705.000
|
$25.000
|
$27.370
|
$45.430
|
$30.660
|
$27.010
|
$33.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
300.000
|
$25.000
|
$32.190
|
$28.500
|
$25.800
|
$25.800
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,600.000
|
$2,252.190
|
$1,850.000
|
$2,528.850
|
$2,028.850
|
$1,900.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,161.000
|
$2.000
|
$1.820
|
$2.000
|
$1.640
|
$1.640
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
6.000
|
$250.000
|
$321.900
|
$150.000
|
$289.200
|
$289.200
|
$155.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,800.000
|
$4,068.150
|
$2,950.000
|
$3,364.930
|
$3,364.930
|
$3,100.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$250.000
|
$227.700
|
$200.000
|
$205.130
|
$205.130
|
$210.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
4.000
|
$1,000.000
|
$2,775.000
|
$273.700
|
$1,250.000
|
$1,250.000
|
$1,300.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$1,000.000
|
$1,665.000
|
$381.850
|
$750.000
|
$750.000
|
$1,300.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$8,500.000
|
$8,325.000
|
$8,000.000
|
$7,200.000
|
$7,200.000
|
$9,500.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
3.000
|
$220.000
|
$260.850
|
$320.000
|
$221.000
|
$221.000
|
$330.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
1.000
|
$590.000
|
$777.000
|
$650.000
|
$326.000
|
$326.000
|
$680.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
12.000
|
$670.000
|
$832.500
|
$680.000
|
$552.000
|
$552.000
|
$710.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
|
EA
|
1.000
|
$700.000
|
$1,309.800
|
$930.000
|
$597.000
|
$597.000
|
$970.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
17.000
|
$800.000
|
$954.600
|
$800.000
|
$640.000
|
$640.000
|
$840.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$970.000
|
$1,114.440
|
$980.000
|
$896.000
|
$896.000
|
$1,100.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$1,060.000
|
$1,228.770
|
$1,130.000
|
$913.000
|
$913.000
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
|
EA
|
2.000
|
$900.000
|
$1,370.850
|
$1,220.000
|
$934.000
|
$934.000
|
$1,300.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$1,020.000
|
$1,409.700
|
$1,200.000
|
$958.000
|
$958.000
|
$1,300.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
34.000
|
$80.000
|
$111.000
|
$20.000
|
$93.000
|
$93.000
|
$21.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
60.000
|
$15.000
|
$16.100
|
$3.000
|
$10.000
|
$10.000
|
$4.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$35.000
|
$39.960
|
$33.000
|
$30.000
|
$30.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)SRF(BI)
|
EA
|
51.000
|
$80.000
|
$122.100
|
$75.000
|
$78.000
|
$78.000
|
$55.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
540.000
|
$5.000
|
$5.550
|
$5.000
|
$3.000
|
$5.000
|
$5.100
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
|
EA
|
450.000
|
$2.000
|
$2.500
|
$2.250
|
$3.000
|
$2.250
|
$2.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
6,688.000
|
$0.500
|
$0.490
|
$0.440
|
$0.650
|
$0.440
|
$0.450
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
21,518.000
|
$0.700
|
$0.470
|
$0.420
|
$0.650
|
$0.420
|
$0.450
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
417.000
|
$0.700
|
$2.220
|
$2.000
|
$0.950
|
$2.000
|
$2.100
|
|
|
PAVEMENT SEALER 4"
|
LF
|
1,090.000
|
$0.250
|
$0.280
|
$0.250
|
$0.200
|
$0.250
|
$0.250
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
158,339.000
|
$0.500
|
$0.750
|
$0.680
|
$0.650
|
$0.680
|
$0.700
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
|
LF
|
18,126.000
|
$0.500
|
$0.830
|
$0.750
|
$0.650
|
$0.750
|
$0.800
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
31,370.000
|
$0.500
|
$0.830
|
$0.750
|
$0.650
|
$0.750
|
$0.800
|
|
PREFAB PAV MRK TY B (W)(24")(SLD)
|
LF
|
34.000
|
$60.000
|
$37.740
|
$34.000
|
$15.000
|
$34.000
|
$36.000
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
2.000
|
$370.000
|
$860.250
|
$775.000
|
$400.000
|
$775.000
|
$810.000
|
|
PREFAB PAV MRK TY B (W)(WORD)
|
EA
|
2.000
|
$1,000.000
|
$1,082.250
|
$975.000
|
$475.000
|
$975.000
|
$1,100.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
22.000
|
$5.000
|
$7.770
|
$7.000
|
$3.000
|
$7.000
|
$7.300
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,507.000
|
$4.000
|
$5.000
|
$4.500
|
$3.000
|
$4.500
|
$4.700
|
|
|
TREE REMOVAL (12" - 18" DIA)
|
EA
|
2.000
|
$1,100.000
|
$1,665.000
|
$1,020.000
|
$1,050.000
|
$1,020.000
|
$1,200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$11,000.000
|
$13,320.000
|
$10,466.030
|
$7,500.000
|
$25,000.000
|
$10,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
352.000
|
$150.000
|
$194.250
|
$200.000
|
$300.000
|
$100.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
16.000
|
$190.000
|
$1,110.000
|
$40.000
|
$750.000
|
$100.000
|
$200.000
|
|
Totals: |
$14,951,862.850
|
$14,990,020.832
|
$15,084,903.752
|
$15,376,888.736
|
$15,659,360.635
|
$15,941,009.770
|