Job Info for 0916-26-019

County: GOLIAD Highway: CR Date: 04/02/2019 (5 years ago) Engineer's Estimate: $481,069 Control Number: 0916-26-019
Project: BR 2018(845) District: CORPUS CHRISTI Time: 68 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $481,069.20
CONSTAR CONSTRUCTION   $518,768.35 1
7.84% | $37,699.15
HILL COUNTRY BRIDGE, INC.   $636,995.25 2
32.41% | $155,926.05
22.79% | $118,226.90
RELMCO, INC.   $763,671.92 3
58.74% | $282,602.72
47.21% | $244,903.57
19.89% | $126,676.67
FNH CONSTRUCTION, LLC   $825,549.50 4
71.61% | $344,480.30
59.14% | $306,781.15
8.10% | $61,877.58
FUQUA CONSTRUCTION CO., INC.   $886,105.76 5
84.2% | $405,036.56
70.81% | $367,337.41
7.34% | $60,556.26

Bid Items

Items: 39, 0 filtered
GOLIAD CR  |  CORPUS CHRISTI  |  0916-26-019  |  04/02/2019  |  $481,069  |  BR 2018(845)  |  REPLACE BRIDGE AND APPROACHES  |  68 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CONSTAR CONSTRUCTION HILL COUNTRY BRIDGE, INC. RELMCO, INC. FNH CONSTRUCTION, LLC FUQUA CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 3.500 $3,000.000 $700.000 $5,640.000 $5,000.000 $12,500.000 $2,460.000
104 6009 REMOVING CONC (RIPRAP) SY 83.000 $15.000 $24.000 $12.750 $25.000 $30.000 $20.000
110 6001 EXCAVATION (ROADWAY) CY 809.000 $10.000 $10.000 $20.200 $15.000 $20.000 $40.000
110 6002 EXCAVATION (CHANNEL) CY 551.000 $5.000 $12.000 $26.300 $15.000 $30.000 $40.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 80.000 $15.000 $17.000 $16.000 $35.000 $40.000 $100.000
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 7,548.000 $0.100 $0.700 $0.010 $0.500 $2.000 $0.360
166 6002 FERTILIZER TON 0.290 $600.000 $675.000 $727.000 $900.000 $3,500.000 $600.000
168 6001 VEGETATIVE WATERING MG 122.000 $15.000 $70.000 $21.000 $20.000 $50.000 $10.350
247 6041 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 501.000 $60.000 $97.000 $91.400 $75.000 $92.500 $85.000
310 6009 PRIME COAT (MC-30) GAL 218.000 $4.000 $10.000 $15.950 $8.000 $10.000 $12.000
316 6001 ASPH (MULTI OPTION) GAL 426.000 $3.000 $13.000 $6.900 $7.000 $10.000 $12.000
316 6413 ASPH(AC-15P, HFRS-2P OR CRS-2P) GAL 350.000 $3.000 $13.000 $6.900 $7.000 $10.000 $12.000
316 6427 AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B) CY 10.000 $100.000 $250.000 $164.750 $225.000 $300.000 $500.000
316 6430 AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B) CY 13.000 $100.000 $250.000 $164.750 $225.000 $300.000 $160.000
400 6005 CEM STABIL BKFL CY 163.000 $100.000 $72.000 $133.200 $150.000 $250.000 $118.290
402 6001 TRENCH EXCAVATION PROTECTION LF 46.000 $5.000 $15.000 $27.000 $30.000 $50.000 $2.870
432 6001 RIPRAP (CONC)(4 IN) CY 48.000 $475.000 $420.000 $520.000 $415.000 $500.000 $428.890
432 6002 RIPRAP (CONC)(5 IN) CY 72.000 $450.000 $420.000 $555.000 $415.000 $600.000 $396.800
450 6018 RAIL (TY T631) LF 246.000 $100.000 $55.000 $66.150 $75.000 $185.000 $87.530
462 6031 CONC BOX CULV (10 FT X 7 FT) LF 184.000 $1,000.000 $1,000.000 $1,049.000 $1,575.000 $1,400.000 $2,100.000
466 6171 WINGWALL (PW - 1) (HW=10 FT) EA 1.000 $30,000.000 $27,000.000 $47,500.000 $47,500.000 $25,000.000 $42,000.000
466 6184 WINGWALL (PW - 1) (HW=9 FT) EA 1.000 $25,000.000 $25,000.000 $40,700.000 $39,500.000 $22,500.000 $38,000.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $20,000.000 $12,000.000 $23,450.000 $35,000.000 $35,000.000 $18,179.010
500 6001 MOBILIZATION LS 1.000 $35,500.000 $42,000.000 $63,500.000 $75,000.000 $80,000.000 $130,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $1,000.000 $1,200.000 $3,120.000 $5,500.000 $8,500.000 $1,400.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 100.000 $15.000 $27.000 $26.200 $21.850 $30.000 $18.140
506 6024 CONSTRUCTION EXITS (REMOVE) SY 100.000 $5.000 $10.000 $11.000 $8.160 $15.000 $6.743
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 456.000 $3.000 $6.000 $2.800 $3.160 $4.000 $3.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 456.000 $1.000 $1.000 $0.800 $0.570 $2.000 $0.611
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 240.000 $6.000 $8.000 $5.000 $9.770 $15.000 $9.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 240.000 $1.000 $2.000 $1.600 $2.300 $10.000 $2.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,800.000 $3,300.000 $3,150.000 $3,500.000 $2,850.000 $2,702.165
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 14.000 $20.000 $33.000 $53.000 $55.000 $100.000 $21.984
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 702.000 $0.600 $9.000 $2.760 $10.810 $5.000 $0.531
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 702.000 $0.600 $9.000 $2.760 $10.810 $5.000 $0.543
672 6009 REFL PAV MRKR TY II-A-A EA 18.000 $3.000 $13.000 $9.350 $115.000 $5.000 $2.871
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 30.000 $100.000 $130.000 $110.000 $300.000 $150.000 $77.224
6185 6002 TMA (STATIONARY) DAY 10.000 $75.000 $400.000 $695.000 $300.000 $550.000 $164.411
6185 6003 TMA (MOBILE OPERATION) HR 50.000 $50.000 $55.000 $69.000 $200.000 $100.000 $295.000
Totals: $481,069.20 $518,768.35 $636,995.25 $763,671.92 $825,549.50 $886,105.79