Job Info for 0516-02-031

County: GOLIAD Highway: SH 239 Date: 01/07/2022 (2 years ago) Engineer's Estimate: $10,169,973 Control Number: 0516-02-031
Project: F 2022(257) District: CORPUS CHRISTI Time: 225 WORKING DAYS Type: REHABILITATE EXISTING ROADWAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $10,169,972.65
HUNTER INDUSTRIES, LTD.   $10,110,262.65 1
-0.59% | -$59,710.00
FARIS INDUSTRIES, INC.   $10,597,660.91 2
4.21% | $427,688.26
4.82% | $487,398.26
CK NEWBERRY, LLC   $11,344,455.59 3
11.55% | $1,174,482.94
12.21% | $1,234,192.94
7.05% | $746,794.68
ANDERSON COLUMBIA CO., INC.   $12,564,247.96 4
23.54% | $2,394,275.31
24.27% | $2,453,985.31
10.75% | $1,219,792.37
TEXAS MATERIALS GROUP, INC.   $12,743,656.82 5
25.31% | $2,573,684.17
26.05% | $2,633,394.17
1.43% | $179,408.86
Subcontractor Percentage Amount
LISKA CONSTRUCTION COMPANY, INC. 12.56% $1,269,848.99
TERRA CONSTRUCTION LLC 3.81% $385,201.01
TEXAS GUARDRAIL CONTRACTORS LLC 2.54% $256,800.67
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 2.10% $212,315.52
FLASHER EQUIPMENT COMPANY 1.10% $111,212.89
DIIBS SPECIALISTS, LLC 0.41% $41,452.08
HIGHWAY BARRICADES AND SERVICES, LLC 0.40% $40,441.05
EGGEMEYER LAND CLEARING, LLC 0.28% $28,308.74
BARRICADES UNLIMITED 0.19% $19,209.50
SURFACE PREPARATION TECHNOLOGIES, LLC 0.13% $13,143.34
M & D FOUNDATION DRILLING INDUSTRIES, INC. 0.00% $0.00
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 23.52% $2,377,933.79

Bid Items

Items: 119, 0 filtered
GOLIAD SH 239  |  CORPUS CHRISTI  |  0516-02-031  |  01/07/2022  |  $10,169,973  |  F 2022(257)  |  REHAB EXIST ROADWAY  |  225 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. FARIS INDUSTRIES, INC. CK NEWBERRY, LLC ANDERSON COLUMBIA CO., INC. TEXAS MATERIALS GROUP, INC.
100 6002 PREPARING ROW STA 255.500 $550.000 $373.840 $557.920 $200.000 $500.000 $1,140.000
104 6009 REMOVING CONC (RIPRAP) SY 30.000 $10.000 $16.650 $40.000 $25.000 $70.000 $18.250
105 6062 REMOVING STAB BASE AND ASPH PAV(4"-16") SY 1,592.000 $5.000 $4.560 $5.110 $15.000 $14.000 $7.000
110 6001 EXCAVATION (ROADWAY) CY 61,960.000 $9.500 $8.940 $8.610 $8.500 $8.500 $15.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 17,061.000 $10.000 $8.940 $10.320 $9.250 $18.000 $11.000
150 6002 BLADING HR 81.500 $100.000 $91.200 $75.250 $130.000 $120.000 $115.000
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 207,036.000 $0.400 $0.340 $0.330 $0.340 $0.320 $0.340
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 103,518.000 $0.300 $0.310 $0.260 $0.300 $0.240 $0.320
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 103,518.000 $0.300 $0.310 $0.260 $0.300 $0.240 $0.320
168 6001 VEGETATIVE WATERING MG 5,141.000 $18.000 $16.650 $3.000 $12.000 $30.000 $15.000
169 6006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY 23,639.000 $1.000 $1.330 $2.150 $1.500 $1.400 $1.750
247 6466 FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS CY 17,937.000 $58.000 $61.580 $65.780 $77.500 $88.000 $86.000
275 6001 CEMENT TON 1,227.000 $160.000 $168.000 $160.000 $165.000 $184.000 $176.000
275 6020 CEMENT TREAT (MX EXST MTL & NW BS)(9") SY 127,436.000 $1.600 $1.710 $1.510 $1.150 $2.900 $1.650
275 6075 CEMENT TREAT(NEW BASE)(9") SY 6,693.000 $1.600 $1.940 $1.510 $1.150 $2.900 $1.650
316 6029 ASPH (RC-250) GAL 26,824.000 $4.000 $3.950 $4.350 $3.750 $3.500 $4.950
316 6177 AGGR(TY-B GR-5 SAC-B) CY 990.000 $85.000 $69.460 $101.050 $115.000 $125.000 $150.000
316 6413 ASPH(AC-15P, HFRS-2P OR CRS-2P) GAL 50,967.000 $3.300 $3.620 $3.640 $3.250 $3.250 $4.000
316 6430 AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B) CY 1,571.000 $85.000 $86.570 $87.550 $95.000 $140.000 $145.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 2,000.000 $35.000 $33.920 $39.020 $45.000 $36.000 $49.000
400 6005 CEM STABIL BKFL CY 150.000 $150.000 $220.500 $117.500 $200.000 $120.000 $158.000
403 6001 TEMPORARY SPL SHORING SF 1,893.000 $20.000 $30.000 $22.000 $15.000 $20.000 $29.000
416 6004 DRILL SHAFT (36 IN) LF 1,004.000 $250.000 $241.290 $267.500 $400.000 $310.000 $227.000
420 6013 CL C CONC (ABUT) CY 65.400 $1,000.000 $1,312.480 $1,225.000 $2,500.000 $1,350.000 $1,520.000
420 6029 CL C CONC (CAP) CY 54.600 $1,200.000 $1,286.230 $1,275.000 $3,000.000 $1,400.000 $1,375.000
420 6037 CL C CONC (COLUMN) CY 15.700 $1,000.000 $1,233.730 $850.000 $2,250.000 $960.000 $1,600.000
422 6001 REINF CONC SLAB SF 9,300.000 $20.000 $24.150 $22.000 $25.000 $24.000 $29.000
425 6035 PRESTR CONC GIRDER (TX28) LF 1,149.000 $145.000 $150.150 $157.500 $200.000 $180.000 $180.000
432 6002 RIPRAP (CONC)(5 IN) CY 24.000 $500.000 $510.970 $485.000 $650.000 $520.000 $495.000
432 6008 RIPRAP (CONC)(CL B)(RR8&RR9) CY 228.000 $500.000 $524.990 $490.000 $600.000 $550.000 $530.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 196.000 $150.000 $162.030 $165.000 $140.000 $185.000 $185.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 58.000 $520.000 $515.960 $475.000 $650.000 $500.000 $485.000
450 6006 RAIL (TY T223) LF 358.000 $100.000 $152.250 $135.000 $250.000 $150.000 $115.000
454 6004 ARMOR JOINT (SEALED) LF 112.000 $100.000 $110.250 $119.270 $100.000 $135.000 $117.000
462 6048 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 10.000 $600.000 $696.800 $694.820 $1,000.000 $750.000 $710.000
464 6003 RC PIPE (CL III)(18 IN) LF 840.000 $65.000 $72.340 $66.470 $85.000 $75.000 $68.000
464 6005 RC PIPE (CL III)(24 IN) LF 88.000 $75.000 $147.120 $82.700 $95.000 $92.000 $84.500
464 6009 RC PIPE (CL III)(42 IN) LF 32.000 $175.000 $212.000 $185.490 $225.000 $190.000 $189.000
464 6018 RC PIPE (CL IV)(24 IN) LF 16.000 $175.000 $101.330 $84.220 $130.000 $95.000 $86.000
464 6019 RC PIPE (CL IV)(30 IN) LF 40.000 $200.000 $133.990 $115.570 $150.000 $130.000 $118.000
467 6146 SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C) EA 1.000 $8,000.000 $9,770.580 $7,750.000 $20,000.000 $8,800.000 $8,000.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 46.000 $1,200.000 $1,500.710 $1,249.920 $2,000.000 $1,400.000 $1,275.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 2.000 $1,500.000 $1,744.870 $1,231.720 $2,500.000 $1,400.000 $1,260.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 2.000 $1,500.000 $1,960.880 $1,231.720 $2,600.000 $1,400.000 $1,260.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 16.000 $1,500.000 $1,961.280 $1,231.720 $2,400.000 $1,400.000 $1,260.000
467 6419 SET (TY II) (30 IN) (RCP) (4: 1) (C) EA 10.000 $2,000.000 $2,466.820 $3,500.000 $2,500.000 $4,000.000 $3,575.000
467 6466 SET (TY II) (42 IN) (RCP) (6: 1) (P) EA 2.000 $6,000.000 $8,614.460 $5,540.920 $8,000.000 $6,300.000 $5,660.000
480 6001 CLEAN EXIST CULVERTS EA 8.000 $2,000.000 $2,248.240 $2,250.000 $3,000.000 $2,500.000 $2,300.000
496 6005 REMOV STR (WINGWALL) EA 1.000 $2,000.000 $1,754.460 $1,125.000 $2,000.000 $1,400.000 $1,250.000
496 6007 REMOV STR (PIPE) LF 693.000 $20.000 $17.550 $12.260 $15.000 $14.000 $12.500
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $80,000.000 $62,999.140 $77,500.000 $100,000.000 $80,000.000 $90,000.000
500 6001 MOBILIZATION LS 1.000 $922,000.000 $856,184.380 $1,165,744.690 $450,000.000 $1,250,000.000 $1,079,700.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $5,000.000 $3,489.130 $3,400.000 $10,000.000 $3,100.000 $19,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 400.000 $30.000 $34.990 $32.250 $35.000 $36.000 $35.750
506 6011 ROCK FILTER DAMS (REMOVE) LF 400.000 $10.000 $12.590 $19.950 $13.000 $22.000 $10.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 312.000 $20.000 $24.470 $34.750 $25.000 $38.000 $30.650
506 6024 CONSTRUCTION EXITS (REMOVE) SY 312.000 $5.000 $7.420 $26.250 $8.000 $30.000 $10.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,258.000 $4.000 $4.050 $2.950 $4.000 $3.000 $3.060
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,258.000 $1.000 $0.820 $1.450 $1.000 $1.500 $1.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 900.000 $6.000 $6.640 $10.000 $6.000 $11.000 $6.130
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 900.000 $1.750 $0.730 $1.900 $1.000 $2.000 $1.000
508 6001 CONSTRUCTING DETOURS SY 1,055.000 $75.000 $21.720 $64.800 $75.000 $75.000 $60.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 14.000 $4,000.000 $1,000.000 $3,000.000 $7,500.000 $8,000.000 $5,500.000
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 870.000 $30.000 $18.370 $28.400 $80.000 $32.000 $30.000
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 630.000 $10.000 $7.350 $12.000 $20.000 $14.000 $9.000
512 6053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) LF 870.000 $10.000 $14.700 $15.000 $30.000 $17.000 $20.000
530 6004 DRIVEWAYS (CONC) SY 106.000 $75.000 $94.640 $82.680 $150.000 $140.000 $90.000
530 6005 DRIVEWAYS (ACP) SY 3,213.000 $35.000 $30.660 $35.850 $30.000 $65.000 $50.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 50,450.000 $0.150 $0.160 $0.070 $0.200 $0.200 $0.160
533 6002 RUMBLE STRIPS (CENTERLINE) LF 24,950.000 $0.150 $0.160 $0.110 $0.300 $0.250 $0.230
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 750.000 $25.000 $22.560 $24.870 $25.000 $28.000 $27.600
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,000.000 $1,823.790 $2,089.000 $2,500.000 $2,900.000 $2,655.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 750.000 $5.000 $1.020 $1.250 $2.000 $1.400 $1.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,000.000 $2,664.010 $2,508.000 $3,000.000 $2,800.000 $3,300.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $300.000 $268.410 $350.000 $350.000 $400.000 $280.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $2,000.000 $1,500.000 $850.000 $1,000.000 $1,700.000 $965.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $1,100.000 $550.000 $750.000 $1,000.000 $1,130.000 $620.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $8,000.000 $8,120.000 $7,500.000 $15,000.000 $8,100.000 $8,975.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 13.000 $250.000 $175.000 $175.000 $250.000 $200.000 $178.000
560 6012 MAILBOX INSTALL-D (TWW-POST) TY 4 EA 1.000 $300.000 $185.000 $185.000 $275.000 $210.000 $188.000
560 6013 MAILBOX INSTALL-M (TWW-POST) TY 4 EA 1.000 $600.000 $525.000 $525.000 $600.000 $590.000 $536.000
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 12.000 $525.000 $700.000 $700.000 $800.000 $790.000 $715.000
644 6028 IN SM RD SN SUP&AM TYS80(1)SA(P-BM) EA 4.000 $650.000 $850.000 $850.000 $1,000.000 $960.000 $868.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 13.000 $675.000 $775.000 $775.000 $900.000 $870.000 $790.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 3.000 $850.000 $950.000 $950.000 $1,200.000 $1,070.000 $970.000
644 6037 IN SM RD SN SUP&AM TYS80(1)SA(U-WC) EA 1.000 $900.000 $1,300.000 $1,300.000 $1,500.000 $1,460.000 $1,325.000
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 2.000 $800.000 $575.000 $575.000 $600.000 $650.000 $585.000
644 6076 REMOVE SM RD SN SUP&AM EA 36.000 $70.000 $70.000 $70.000 $100.000 $80.000 $71.000
644 6080 RELOCATE SM RD SN SUP & AM TY TEMP EA 39.000 $200.000 $125.000 $125.000 $500.000 $140.000 $127.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $20.000 $18.000 $18.000 $50.000 $20.000 $18.400
658 6060 REMOVE DELIN & OBJECT MARKER ASSMS EA 16.000 $20.000 $15.000 $15.000 $50.000 $17.000 $15.300
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 20.000 $27.000 $35.000 $35.000 $50.000 $40.000 $35.750
658 6081 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI) EA 16.000 $120.000 $85.000 $85.000 $100.000 $96.000 $86.500
658 6099 INSTL OM ASSM (OM-2Z)(WFLX)GND EA 16.000 $75.000 $90.000 $90.000 $150.000 $100.000 $91.500
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 50,900.000 $0.300 $0.240 $0.240 $0.500 $0.400 $0.250
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 162,800.000 $0.300 $0.240 $0.240 $0.390 $0.400 $0.250
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 6,820.000 $0.700 $0.630 $0.630 $0.560 $0.600 $0.640
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 24.000 $8.000 $12.000 $12.000 $15.000 $16.000 $12.260
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 12,000.000 $0.750 $0.630 $0.630 $0.750 $0.600 $0.640
662 6110 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 8,127.000 $1.750 $1.470 $0.940 $2.000 $1.250 $1.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 610.000 $1.000 $1.000 $1.000 $1.000 $0.850 $1.020
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 50,890.000 $0.300 $0.400 $0.400 $0.500 $0.400 $0.410
666 6311 RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) LF 4,420.000 $0.300 $0.440 $0.440 $0.500 $0.400 $0.450
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 28,344.000 $0.300 $0.410 $0.410 $0.500 $0.400 $0.420
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 18.000 $12.000 $25.000 $25.000 $20.000 $16.000 $25.540
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 4.000 $250.000 $250.000 $250.000 $300.000 $250.000 $255.390
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 4.000 $300.000 $250.000 $250.000 $350.000 $280.000 $255.390
672 6007 REFL PAV MRKR TY I-C EA 37.000 $3.000 $6.000 $6.000 $6.000 $6.000 $6.100
672 6009 REFL PAV MRKR TY II-A-A EA 770.000 $3.500 $3.770 $3.770 $6.000 $4.500 $3.850
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 16,800.000 $1.000 $0.470 $0.470 $2.000 $0.600 $0.500
678 6001 PAV SURF PREP FOR MRK (4") LF 155.000 $0.100 $3.000 $3.000 $1.000 $1.000 $3.060
752 6015 TREE AND BRUSH REMOVAL AC 0.430 $20,000.000 $2,100.000 $23,700.000 $50,000.000 $26,800.000 $5,000.000
3076 6002 D-GR HMA TY-B SAC-B PG64-22 TON 36,760.000 $75.000 $74.190 $74.900 $81.000 $85.000 $86.000
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 14,411.000 $80.000 $84.690 $87.190 $96.000 $97.000 $98.000
3076 6066 TACK COAT GAL 21,378.000 $3.000 $3.170 $2.220 $3.500 $3.000 $3.240
4171 6001 INSTALL BRIDGE IDENTIFICATION NUMBERS EA 4.000 $400.000 $150.000 $113.400 $500.000 $130.000 $340.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $7,500.000 $20,000.000 $25,000.000 $33,200.000 $12,500.000
6185 6002 TMA (STATIONARY) DAY 40.000 $300.000 $350.000 $300.000 $375.000 $175.000 $400.000
6185 6003 TMA (MOBILE OPERATION) HR 120.000 $75.000 $100.000 $20.000 $25.000 $40.000 $55.000
Totals: $10,169,972.65 $10,110,262.66 $10,597,660.92 $11,344,455.59 $12,564,247.96 $12,743,656.82