Items: 61

County: GOLIAD
Length: 2.0800 MILES (2.6700 MILES)
Highway: US 59
District: CORPUS CHRISTI
Control Number: 0088-02-063
DBE Goal: 0.0%
Project: F 2026(754)
Guaranty: $55,000.00
Time: 78 WORKING DAYS
Engineer's Estimate: $2,373,039.29
Date: 07/01/2026 1:00 PM CDT (17 days ago)
Contract Number: 7263012
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00072146
Contract Type: FEDERAL
Project Description: MILL AND OVERLAY ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
NICK NOVOSAD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,373,039.29
Over/Under Est: -10.14% -$240,669.89
$2,200,359.88
Over/Under Est: -7.28% -$172,679.41
Amt Left: 3.19% $67,990.48
Over/Under Est: 1.54% $36,469.25
Amt Left: 13% $277,139.14
Delta: -9.51% -$209,148.66
Over/Under Est: 4.25% $100,922.91
Amt Left: 16.02% $341,592.80
Delta: -2.67% -$64,453.66
Over/Under Est: 14.59% $346,126.71
Amt Left: 27.52% $586,796.60
Delta: -9.91% -$245,203.80
Over/Under Est: 20.41% $484,385.16
Amt Left: 34% $725,055.05
Delta: -5.08% -$138,258.45
Over/Under Est: 24.69% $585,869.27
Amt Left: 38.76% $826,539.16
Delta: -3.55% -$101,484.11

Bid Items & Bid Tabulations

61 Total 0 of 61
GOLIAD  |  US 59  |  CORPUS CHRISTI  |  0088-02-063  |  07/01/2026 1:00 PM CDT  |  $2,373,039.29  |  F 2026(754)  |  SURF/ROADWAY RESTOR  |  78 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CK NEWBERRY, LLC
LCR TOTAL TRANSPORT LLC
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
J E CONSTRUCTION SERVICES, LLC
ANDERSON COLUMBIA CO., INC.
PREPARING ROW
STA 50.000 $500.000 $366.300 $95.000 $374.000 $1,100.000 $260.000 $790.000 $590.000
BACKFILL (TY A OR B)
STA 50.000 $100.000 $132.000 $135.000 $269.389 $200.000 $250.000 $190.000 $264.000
AGGR (TY-PD, GR-4 OR 4S)(SAC-B)
CY 670.000 $100.000 $108.900 $130.000 $171.751 $160.000 $270.000 $220.000 $201.000
ASPH (MULTI OPTION)
GAL 29,320.000 $4.000 $3.740 $3.000 $4.705 $4.000 $4.100 $6.000 $4.200
D-GR HMA TY-D SAC-B PG70-22
TON 8,859.000 $90.000 $111.100 $115.000 $140.000 $130.000 $130.700 $130.000 $159.000
TACK COAT
GAL 6,445.000 $5.000 $3.190 $4.000 $4.452 $4.000 $3.600 $7.000 $3.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 6,930.000 $65.000 $21.520 $35.000 $26.000 $30.000 $40.000 $48.000 $41.000
PLANE ASPH CONC PAV(0" TO 2")
SY 81,112.000 $1.500 $1.430 $1.000 $1.826 $2.200 $1.900 $2.000 $1.850
CONC STR REPAIR (STANDARD)
SF 50.000 $400.000 $150.000 $225.000 $19.745 $350.000 $350.000 $40.000 $163.000
RIPRAP (MOW STRIP)(4 IN)
CY 49.000 $650.000 $700.240 $700.000 $687.500 $600.000 $640.000 $650.000 $757.000
RAIL (TY T631)
LF 200.000 $140.000 $100.930 $110.000 $97.900 $150.000 $92.000 $124.000 $108.000
CLEAN EXIST CULVERTS
EA 14.000 $2,750.000 $900.000 $1,500.000 $1,299.226 $1,100.000 $1,700.000 $1,420.000 $2,110.000
MOBILIZATION
LS 1.000 $241,413.000 $207,939.460 $200,000.000 $120,000.000 $230,000.000 $212,600.000 $254,120.000 $95,300.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $13,751.210 $10,000.000 $2,200.000 $2,800.000 $30,000.000 $1,960.000 $21,400.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $5,000.000 $4,082.020 $2,500.000 $3,748.367 $5,000.000 $2,800.000 $1,750.000 $10,500.000
TMA (STATIONARY)
DAY 64.000 $200.000 $153.080 $25.000 $539.000 $300.000 $190.000 $390.000 $347.000
TMA (MOBILE OPERATION)
HR 56.000 $20.000 $40.820 $15.000 $47.258 $100.000 $56.000 $74.000 $10.000
TMA (MOBILE OPERATION)
DAY 14.000 $100.000 $229.610 $25.000 $343.035 $300.000 $630.000 $742.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 460.000 $2.500 $3.510 $6.500 $3.575 $6.500 $3.400 $4.000 $3.950
TEMP SEDMT CONT FENCE (REMOVE)
LF 460.000 $1.000 $1.030 $3.000 $1.045 $3.000 $0.950 $2.000 $1.150
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 800.000 $2.000 $3.780 $8.000 $3.850 $8.000 $3.600 $9.000 $4.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 800.000 $1.000 $1.080 $2.000 $1.100 $2.000 $1.050 $2.000 $1.200
INTERSECTIONS (ACP)
SY 817.000 $100.000 $39.600 $45.000 $30.009 $25.000 $69.000 $72.000 $52.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 10,472.000 $0.500 $0.120 $0.500 $0.374 $0.120 $0.120 $1.000 $0.750
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 3,720.000 $0.500 $0.160 $0.500 $0.605 $0.160 $0.160 $1.000 $1.050
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $25.000 $28.620 $35.000 $29.150 $40.000 $28.000 $35.000 $32.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,400.000 $3,834.000 $4,075.000 $3,905.000 $4,000.000 $3,600.000 $5,540.000 $4,300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BR)
EA 7.000 $30.000 $12.960 $15.000 $13.200 $15.000 $12.500 $10.000 $15.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 16.000 $30.000 $23.760 $25.000 $24.200 $25.000 $23.000 $94.000 $27.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 6,790.000 $0.500 $0.330 $0.350 $0.363 $0.330 $0.340 $0.500 $0.800
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 29,005.710 $0.500 $0.330 $0.350 $0.363 $0.330 $0.340 $0.500 $0.350
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 1,268.000 $10.000 $2.000 $2.000 $2.200 $2.000 $2.100 $7.000 $8.450
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 6,790.000 $0.400 $0.330 $0.350 $0.363 $0.330 $0.340 $0.500 $0.800
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 27,630.000 $0.400 $0.330 $0.350 $0.363 $0.330 $0.340 $0.500 $0.350
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 697.000 $2.000 $2.210 $1.100 $2.075 $1.000 $3.100 $3.000 $1.600
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,361.000 $2.000 $2.210 $1.100 $2.078 $1.000 $3.100 $3.000 $1.650
RE PM TY II (W) 6" (BRK)
LF 6,878.570 $0.400 $0.300 $0.300 $0.330 $0.300 $0.310 $0.500 $0.600
RE PM TY II (W) 6" (SLD)
LF 28,884.290 $0.150 $0.300 $0.300 $0.330 $0.300 $0.310 $0.500 $0.350
RE PM TY II (W) 24" (SLD)
LF 567.000 $1.000 $2.000 $2.000 $2.200 $2.000 $2.100 $1.000 $1.350
RE PM TY II (Y) 6" (SLD)
LF 27,515.720 $0.150 $0.300 $0.300 $0.330 $0.300 $0.310 $0.500 $0.350
TY I HIGH PERF PM (W)6"(BRK)(090MIL)
LF 6,878.570 $0.700 $0.520 $0.600 $0.572 $0.520 $0.550 $1.000 $1.150
TY I HIGH PERF PM (W)6"(SLD)(090MIL)
LF 27,515.720 $0.700 $0.520 $0.600 $0.572 $0.520 $0.550 $0.500 $0.800
TY I HIGH PERF PM (Y)6"(SLD)(090MIL)
LF 27,515.720 $0.700 $0.520 $0.600 $0.572 $0.520 $0.550 $0.500 $0.800
PREFAB PM TY B (W)(6")(BRK)CONTRAST
LF 386.000 $6.000 $9.000 $9.000 $9.900 $9.000 $9.300 $15.000 $18.000
PREFAB PM TY B (W)(8")(SLD)
LF 318.000 $9.000 $12.000 $12.000 $13.200 $12.000 $12.500 $14.000 $16.000
PREFAB PM TY B (W)(24")(SLD)CONTRAST
LF 613.000 $25.000 $15.000 $15.000 $16.500 $15.000 $15.500 $28.000 $35.000
PREFAB PM TY B (Y)(6")(SLD)
LF 1,544.000 $6.000 $9.000 $9.000 $9.900 $9.000 $9.300 $6.000 $7.850
PREFAB PM TY B (Y)(6")(BRK)CONTRAST
LF 386.000 $6.000 $10.000 $10.000 $11.000 $10.000 $10.250 $15.000 $18.000
PREFAB PM TY B (W)(WORD)CONTRAST
EA 4.000 $460.000 $300.000 $300.000 $330.000 $300.000 $310.000 $5,630.000 $6,660.000
PREFAB PM TY B (W)(ARROW)CONTRAST
EA 6.000 $460.000 $350.000 $350.000 $385.000 $350.000 $360.000 $4,920.000 $5,870.000
PREFAB PM TY C (W)(24")(SLD)
LF 655.000 $20.000 $15.000 $15.000 $16.500 $15.000 $15.500 $12.000 $15.000
PREFAB PM TY C (W)(ARROW)
EA 39.000 $450.000 $250.000 $250.000 $275.000 $250.000 $260.000 $152.000 $182.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $600.000 $300.000 $300.000 $330.000 $300.000 $310.000 $281.000 $333.000
REFL PAV MRKR TY I-C
EA 410.000 $4.000 $3.500 $3.500 $3.850 $3.500 $3.600 $7.000 $9.100
ELIM EXT PM & MRKS (4")
LF 863.000 $1.000 $1.000 $1.000 $1.100 $1.000 $1.050 $3.000 $0.400
ELIM EXT PM & MRKS (8")
LF 612.000 $2.000 $1.000 $1.000 $1.100 $1.000 $1.050 $4.000 $0.750
ELIM EXT PM & MRKS (24")
LF 658.000 $5.000 $4.000 $4.000 $4.400 $4.000 $4.100 $5.000 $2.400
ELIM EXT PM & MRKS (ARROW)
EA 7.000 $100.000 $100.000 $100.000 $110.000 $100.000 $110.000 $41.000 $48.000
ELIM EXT PM & MRKS (WORD)
EA 5.000 $100.000 $100.000 $100.000 $110.000 $100.000 $520.000 $41.000 $48.000
TREE TRIMMING / BRUSH REMOVAL
MI 1.300 $2,000.000 $8,250.000 $12,000.000 $13,131.038 $5,000.000 $10,300.000 $13,740.000 $13,100.000
DRAIN INLET CLEANING
EA 40.000 $900.000 $900.000 $750.000 $324.543 $200.000 $530.000 $269.000 $1,220.000
Totals: $2,373,039.292 $2,132,369.404 $2,200,359.878 $2,409,508.535 $2,473,962.204 $2,719,165.997 $2,857,424.435 $2,958,908.552
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $20,000.00