Job Info for 0088-02-062

County: GOLIAD Highway: US 59 Date: 10/01/2024 (7 weeks ago) Engineer's Estimate: $24,425,868 Control Number: 0088-02-062
Project: BR 2025(159) District: CORPUS CHRISTI Time: 579 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $24,425,867.53
HUNTER INDUSTRIES, LTD.   $31,574,353.16 1
29.27% | $7,148,485.63
ZACHRY CONSTRUCTION CORPORATION   $39,078,124.62 2
59.99% | $14,652,257.09
23.77% | $7,503,771.46

Bid Items

Items: 105, 0 filtered
GOLIAD US 59  |  CORPUS CHRISTI  |  0088-02-062  |  10/01/2024  |  $24,425,868  |  BR 2025(159)  |  BRIDGE REPL  |  579 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. ZACHRY CONSTRUCTION CORPORATION
100 7002 PREPARING ROW STA 35.000 $4,025.000 $63,296.000 $111,000.000
104 7005 REMOV CONC (MOWSTRIP) LF 1,030.000 $9.000 $14.000 $10.000
110 7001 EXCAV (ROADWAY) CY 4,611.190 $10.000 $35.000 $11.000
132 7006 EMBANK (FNL)(DC)(TY C) CY 37,143.060 $16.000 $63.850 $7.300
152 7004 ROAD GRADER WORK (DENS CONT) SY 2,500.000 $5.000 $12.000 $4.200
164 7018 HYDRO MULCH SEED (PERM_RURAL_CLAY) SY 96,207.000 $0.850 $0.440 $0.500
164 7021 HYDRO MULCH SEED (TEMP_WARM) SY 48,104.000 $0.450 $0.410 $0.500
164 7022 HYDRO MULCH SEED (TEMP_COOL) SY 48,104.000 $0.450 $0.410 $0.500
166 7001 FERTILIZER AC 19.900 $360.000 $656.230 $773.000
168 7001 VEGETATIVE WATERING TGL 14,032.700 $25.000 $7.000 $22.000
169 7043 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 10,018.000 $2.750 $1.640 $1.900
247 7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 3,517.000 $100.000 $118.660 $300.000
275 7001 CEMENT TON 253.000 $225.000 $220.000 $350.000
275 7017 CEMENT TREAT (SUBGRADE) (8") SY 14,068.000 $4.000 $4.800 $5.000
305 7001 SALV, HAUL & STKPL RECLM ASPH PAV CY 2,771.000 $10.000 $17.500 $27.000
310 7004 PRIME COAT (MC-30) GAL 3,517.000 $5.000 $9.100 $3.400
316 7016 ASPH (RC-250) GAL 3,517.000 $5.000 $7.900 $5.900
341 7007 D-GR HMA TY-B SAC-B PG70-22 TON 3,660.000 $135.000 $147.700 $167.000
341 7050 D-GR HMA TY-D SAC-B PG70-22 TON 1,847.000 $115.000 $153.200 $195.000
341 7082 TACK COAT GAL 1,007.000 $4.500 $3.780 $4.900
400 7010 CEM STABIL BKFL CY 241.000 $150.000 $213.840 $182.000
403 7001 TEMPORARY SPL SHORING SF 26,629.000 $45.000 $58.590 $59.000
405 7003 FOUNDATON LOADTEST(D4945)(DRILLD SHAFT) EA 1.000 $20,000.000 $38,267.900 $45,277.000
416 7006 DRILL SHAFT (36 IN) LF 1,323.000 $220.000 $339.800 $422.000
416 7008 DRILL SHAFT (48 IN) LF 1,950.000 $550.000 $493.540 $605.000
416 7010 DRILL SHAFT (60 IN) LF 1,320.000 $715.000 $704.800 $880.000
420 7012 CL C CONC (ABUT) CY 89.600 $2,000.000 $2,000.000 $1,740.000
420 7022 CL C CONC (CAP) CY 289.000 $1,900.000 $1,500.000 $2,133.000
420 7038 CL C CONC (COLUMN) CY 246.200 $1,220.000 $1,500.000 $1,364.000
420 7067 CL C CONC (MISC) CY 199.600 $1,450.000 $2,000.000 $1,386.000
420 7071 CL F CONC (CAP) CY 62.000 $1,250.000 $1,800.000 $1,667.000
422 7001 REINF CONC SLAB SF 83,160.000 $25.000 $42.000 $36.000
423 7001 RETAINING WALL (MSE) SF 37,558.000 $55.000 $76.000 $191.000
423 7012 RETAINING WALL (TEMP WALL) SF 30,055.000 $30.000 $18.000 $18.000
425 7005 PRESTR CONC GIRDER (TX54) LF 4,380.400 $170.000 $190.000 $199.000
432 7001 RIPRAP (CONC)(4 IN) CY 10.000 $1,200.000 $2,015.960 $1,200.000
432 7013 RIPRAP (MOW STRIP)(4 IN) CY 107.200 $560.000 $1,079.980 $1,700.000
432 7043 RIPRAP (STONE PROTECTION)(18 IN) CY 452.000 $230.000 $289.810 $350.000
434 7026 ELASTOMERIC BEARING (E6) EA 10.000 $4,000.000 $3,500.000 $5,085.000
434 7036 ELASTOMERIC BEARING (F6) EA 10.000 $4,000.000 $3,500.000 $5,084.000
434 7045 SLIDING ELASTOMERIC BEARING (ES 5) EA 20.000 $4,000.000 $3,500.000 $5,410.000
442 7001 STR STEEL (PLATE GIRDER) LB 2,058,000.000 $2.600 $2.860 $3.100
450 7024 RAIL (TY SSTR) LF 1,262.000 $120.000 $70.180 $85.000
450 7066 RAIL (TY SSTR)(MOD) LF 1,980.000 $83.000 $72.340 $73.000
454 7005 SEALED EXPANSION JOINT (5 IN) (SEJ - M) LF 332.000 $200.000 $300.000 $332.000
464 7005 RC PIPE (CL III)(24 IN) LF 146.000 $125.000 $332.560 $300.000
467 7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 2.000 $2,160.000 $7,917.720 $8,500.000
496 7004 REMOV STR (SET) EA 4.000 $654.000 $1,374.510 $200.000
496 7007 REMOV STR (PIPE) LF 89.000 $2,136.000 $64.780 $75.000
496 7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) EA 1.000 $550,000.000 $325,000.000 $519,846.000
496 7028 REMOVE STR (BOLLARD) EA 16.000 $194.340 $250.000 $150.000
496 7036 REMOV STR (SMALL) EA 1.000 $500.000 $3,909.960 $4,135.000
500 7001 MOBILIZATION LS 1.000 $2,296,937.090 $2,978,461.770 $3,850,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 35.000 $7,300.000 $5,777.860 $15,000.000
506 7002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 473.000 $45.000 $54.630 $65.000
506 7011 ROCK FILTER DAMS (REMOVE) LF 473.000 $33.000 $19.870 $24.000
506 7020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 340.000 $39.000 $44.770 $53.000
506 7024 CONSTRUCTION EXITS (REMOVE) SY 340.000 $12.000 $14.240 $17.000
506 7039 TEMP SEDMT CONT FENCE (INSTALL) LF 24,812.000 $3.600 $3.450 $4.100
506 7041 TEMP SEDMT CONT FENCE (REMOVE) LF 24,812.000 $1.200 $1.100 $1.300
506 7045 BIODEG EROSN CONT LOGS (INSTL) (18") LF 246.000 $7.250 $14.260 $17.000
506 7046 BIODEG EROSN CONT LOGS (REMOVE) LF 246.000 $1.400 $4.560 $5.400
508 7001 CONSTRUCTING DETOURS SY 3,794.000 $55.000 $89.600 $118.000
512 7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 7,360.000 $44.000 $30.000 $60.000
512 7025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 3,002.000 $10.000 $12.000 $10.000
512 7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 7,340.000 $22.000 $12.000 $25.000
514 7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) LF 1,290.000 $90.000 $99.340 $160.000
533 7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) LF 6,920.000 $0.200 $1.180 $0.600
533 7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) LF 1,536.000 $0.250 $1.410 $0.700
540 7001 MTL W-BEAM GD FEN (TIM POST) LF 100.000 $25.000 $27.600 $33.000
540 7037 TL-2 31" SHORT RADIUS (W/O DAT) EA 1.000 $22,500.000 $37,500.000 $44,193.000
542 7001 REMOVE METAL BEAM GUARD FENCE LF 500.000 $3.000 $3.000 $3.600
542 7004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $275.000 $275.000 $323.000
544 7001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,400.000 $3,495.000 $4,118.000
544 7003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $320.000 $243.710 $1,767.000
545 7002 CRASH CUSH ATTEN (MOVE & RESET) EA 13.000 $1,100.000 $1,100.000 $1,297.000
545 7004 CRASH CUSH ATTEN (REMOVE) EA 8.000 $1,000.000 $950.000 $1,120.000
545 7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 4.000 $38,500.000 $29,395.000 $34,642.000
545 7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 8.000 $28,000.000 $8,850.000 $10,430.000
550 7016 GATE (REMOVE) EA 1.000 $377.000 $781.990 $1,238.000
556 7006 PIPE UNDERDRAINS (TY 6) (6") LF 3,005.000 $28.000 $40.000 $25.000
644 7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 2.000 $670.000 $875.000 $1,032.000
644 7004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 5.000 $890.000 $1,250.000 $1,473.000
644 7028 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 2.000 $1,000.000 $1,150.000 $1,355.000
644 7061 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N) EA 2.000 $2,200.000 $2,450.000 $2,888.000
644 7073 REMOVE SM RD SN SUP&AM EA 8.000 $100.000 $125.000 $147.000
658 7014 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BR) EA 32.000 $15.000 $45.000 $53.000
658 7016 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF1 (BI) EA 5.000 $60.000 $28.000 $33.000
658 7033 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BR) EA 12.000 $22.000 $45.000 $53.000
658 7066 INSTL OM ASSM (OM-3L)(TWT)GND EA 2.000 $250.000 $550.000 $648.000
658 7070 INSTL OM ASSM (OM-3R)(TWT)GND EA 2.000 $250.000 $550.000 $648.000
662 7064 WK ZN PAV MRK REMOV (W)4"(SLD) LF 21,667.000 $0.600 $0.480 $0.600
662 7097 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 20,924.000 $0.600 $0.480 $0.600
666 7017 REFL PAV MRK TY I (W)8"(DOT)(090MIL) LF 38.000 $1.500 $1.100 $1.300
666 7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 887.000 $0.800 $0.880 $1.000
666 7265 RE PROFILE PM TY I(W)6"(SLD)(090MIL) LF 9,100.000 $1.200 $1.250 $1.500
666 7269 RE PROFILE PM TY I(Y)6"(SLD)(090MIL) LF 13,882.000 $0.750 $1.250 $1.500
666 7273 RE PROFILE PM TY I(Y)6"(BRK)(090MIL) LF 150.000 $0.750 $2.000 $2.400
668 7091 PREFAB PM TY C (W)(ARROW) EA 3.000 $200.000 $200.000 $236.000
668 7103 PREFAB PM TY C (W)(WORD) EA 3.000 $285.000 $300.000 $353.000
672 7002 REFL PAV MRKR TY I-C EA 22.000 $5.000 $7.500 $8.900
672 7004 REFL PAV MRKR TY II-A-A EA 593.000 $5.000 $7.500 $8.900
677 7001 ELIM EXT PM & MRKS (4") LF 14,766.000 $0.500 $0.400 $0.500
677 7008 ELIM EXT PM & MRKS (24") LF 631.000 $3.400 $6.000 $7.100
4003 7001 TIP TESTING(DRILL SHAFT) EA 24.000 $5,000.000 $8,839.970 $8,202.000
Totals: $24,425,867.54 $31,574,353.17 $39,078,124.63