Job Info for 0905-15-012

County: GARZA Highway: CR Date: 12/02/2021 (2 years ago) Engineer's Estimate: $955,618 Control Number: 0905-15-012
Project: BR 2020(458) District: LUBBOCK Time: 126 WORKING DAYS Type: BRIDGE REPLACEMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $955,618.00
BLACKSTONE CONCRETE VENTURES, LLC   $847,049.80 1
-11.36% | -$108,568.20
EARTH BUILDERS, L.P.   $855,615.00 2
-10.46% | -$100,003.00
1.01% | $8,565.20
DIGG COMMERCIAL, LLC   $949,002.00 3
-0.69% | -$6,616.00
12.04% | $101,952.20
10.91% | $93,387.00
GILVIN-TERRILL, LTD.   $1,988,585.42 4
108.09% | $1,032,967.42
134.77% | $1,141,535.62
109.54% | $1,039,583.42

Bid Items

Items: 36, 0 filtered
GARZA CR  |  LUBBOCK  |  0905-15-012  |  12/02/2021  |  $955,618  |  BR 2020(458)  |  BRIDGE REPL  |  126 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BLACKSTONE CONCRETE VENTURES, LLC EARTH BUILDERS, L.P. DIGG COMMERCIAL, LLC GILVIN-TERRILL, LTD.
100 6002 PREPARING ROW STA 4.000 $2,500.000 $10,000.000 $10,000.000 $3,346.000 $3,500.000
110 6001 EXCAVATION (ROADWAY) CY 408.000 $20.000 $30.000 $20.000 $30.000 $50.000
110 6002 EXCAVATION (CHANNEL) CY 955.000 $25.000 $25.000 $20.000 $33.000 $51.740
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 277.000 $30.000 $5.500 $20.000 $48.000 $50.590
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 813.000 $1.000 $5.100 $2.000 $4.000 $9.500
216 6001 PROOF ROLLING HR 10.000 $150.000 $500.000 $85.000 $223.000 $400.610
247 6344 FL BS (CMP IN PLACE)(TY D GR 4)(12") SY 1,008.000 $30.000 $25.000 $50.000 $41.000 $93.280
314 6013 EMULS ASPH (EROSN CONT)(CSS-1H) GAL 106.000 $10.000 $10.000 $10.000 $22.000 $12.000
400 6005 CEM STABIL BKFL CY 28.000 $300.000 $650.000 $300.000 $680.000 $608.890
402 6001 TRENCH EXCAVATION PROTECTION LF 61.000 $20.000 $250.000 $10.000 $8.000 $10.000
403 6006 TEMPORARY SPL SHORING (COFFERDAM) SF 1,700.000 $30.000 $5.000 $5.000 $24.000 $28.000
450 6006 RAIL (TY T223) LF 202.000 $150.000 $250.000 $175.000 $259.000 $351.130
459 6008 GABION MATTRESSES (GALV)(18 IN) SY 610.000 $250.000 $55.000 $125.000 $165.000 $265.760
459 6009 GABIONS (3' X 3')(GALV) CY 180.000 $250.000 $100.000 $200.000 $256.000 $440.120
462 6034 CONC BOX CULV (10 FT X 10 FT) LF 152.500 $1,500.000 $850.000 $1,600.000 $1,590.000 $3,000.000
466 6173 WINGWALL (PW - 1) (HW=12 FT) EA 2.000 $70,000.000 $35,000.000 $60,000.000 $47,553.000 $250,707.110
480 6001 CLEAN EXIST CULVERTS EA 1.000 $2,500.000 $5,000.000 $2,500.000 $13,385.000 $15,094.920
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $25,000.000 $222,700.000 $25,000.000 $52,426.000 $52,089.050
500 6001 MOBILIZATION LS 1.000 $87,000.000 $75,000.000 $90,000.000 $96,309.000 $150,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $1,500.000 $1,000.000 $2,000.000 $779.000 $10,000.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 222.000 $30.000 $50.000 $30.000 $28.000 $115.330
506 6024 CONSTRUCTION EXITS (REMOVE) SY 222.000 $10.000 $10.000 $10.000 $6.000 $33.290
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,000.000 $5.000 $5.000 $5.000 $4.000 $14.360
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 500.000 $1.000 $5.000 $1.000 $1.000 $9.310
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,200.000 $10.000 $5.000 $8.000 $2.000 $13.030
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 600.000 $1.000 $5.000 $1.000 $1.000 $3.880
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 50.000 $40.000 $125.000 $40.000 $57.000 $50.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,500.000 $3,500.000 $2,500.000 $1,160.000 $1,850.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,000.000 $4,000.000 $3,500.000 $2,219.000 $3,600.000
552 6001 WIRE FENCE (TY A) LF 298.000 $20.000 $25.000 $19.500 $20.000 $30.000
644 6076 REMOVE SM RD SN SUP&AM EA 4.000 $100.000 $550.000 $50.000 $335.000 $100.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $50.000 $25.000 $21.000 $70.000 $5.750
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 12.000 $50.000 $25.000 $21.000 $82.000 $5.750
734 6002 LITTER REMOVAL CYC 2.000 $1,000.000 $1,000.000 $500.000 $1,115.000 $4,654.030
4171 6001 INSTALL BRIDGE IDENTIFICATION NUMBERS EA 1.000 $250.000 $250.000 $2,000.000 $726.000 $721.560
6185 6002 TMA (STATIONARY) DAY 126.000 $250.000 $10.000 $50.000 $167.000 $288.620
Totals: $955,618.00 $847,049.80 $855,615.00 $949,002.00 $1,988,585.42