Job Info for 0053-04-042

County: GARZA Highway: US 84 Date: 04/05/2017 (7 years ago) Engineer's Estimate: $3,021,299 Control Number: 0053-04-042
Project: NH 1702(189) District: LUBBOCK Time: 51 WORKING DAYS Type: CONCRETE REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,021,299.00
TOTAL HIGHWAY MAINTENANCE, LLC   $2,405,439.70 1
-20.38% | -$615,859.30
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC   $2,560,010.15 2
-15.27% | -$461,288.85
6.43% | $154,570.45
DEANGELO BROTHERS LLC   $2,697,410.40 3
-10.72% | -$323,888.60
12.14% | $291,970.70
5.37% | $137,400.25
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $3,218,915.40 4
6.54% | $197,616.40
33.82% | $813,475.70
19.33% | $521,505.00
ALLEN BUTLER CONSTRUCTION, INC.   $3,467,621.76 5
14.77% | $446,322.76
44.16% | $1,062,182.06
7.73% | $248,706.36
CHAMPION INFRASTRUCTURE, LLC   $3,927,084.00 6
29.98% | $905,785.00
63.26% | $1,521,644.30
13.25% | $459,462.24

Bid Items

Items: 27, 0 filtered
GARZA US 84  |  LUBBOCK  |  0053-04-042  |  04/05/2017  |  $3,021,299  |  NH 1702(189)  |  CONC REPAIR  |  51 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TOTAL HIGHWAY MAINTENANCE, LLC AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC DEANGELO BROTHERS LLC SALINAS CONSTRUCTION TECHNOLOGIES, LTD. ALLEN BUTLER CONSTRUCTION, INC. CHAMPION INFRASTRUCTURE, LLC
104 6009 REMOVING CONC (RIPRAP) SY 260.000 $15.000 $132.000 $24.000 $22.000 $37.590 $56.440 $60.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 2,000.000 $7.000 $4.700 $18.000 $16.000 $7.510 $18.810 $20.000
361 6004 FULL - DEPTH REPAIR CRCP (10") SY 259.300 $500.000 $391.000 $290.000 $285.000 $409.910 $689.770 $800.000
361 6019 HALF - DEPTH REPAIR CRCP (10") SY 111.400 $275.000 $258.000 $990.000 $1,000.000 $453.120 $689.770 $600.000
401 6001 FLOWABLE BACKFILL CY 102.000 $200.000 $662.000 $415.000 $420.000 $247.560 $627.060 $320.000
432 6001 RIPRAP (CONC)(4 IN) CY 32.000 $450.000 $993.000 $1,050.000 $1,000.000 $896.810 $1,504.950 $900.000
465 6021 INLET (COMPL)(PCO)(5FT)(NONE) EA 9.000 $2,000.000 $7,000.000 $7,000.000 $6,400.000 $6,423.120 $6,270.640 $10,000.000
496 6002 REMOV STR (INLET) EA 5.000 $500.000 $814.000 $550.000 $525.000 $1,913.110 $12,541.270 $6,500.000
500 6001 MOBILIZATION LS 1.000 $275,000.000 $84,000.000 $250,000.000 $210,000.000 $229,970.190 $144,813.020 $300,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $15,000.000 $13,000.000 $25,000.000 $1,250.000 $18,765.580 $2,630.350 $7,000.000
506 6035 SANDBAGS FOR EROSION CONTROL EA 100.000 $10.000 $6.600 $30.000 $55.000 $9.470 $5.090 $200.000
529 6008 CONC CURB & GUTTER (TY II) LF 2,000.000 $25.000 $53.000 $45.000 $45.000 $29.290 $125.410 $60.000
531 6001 CONC SIDEWALKS (4") SY 32.000 $60.000 $117.000 $110.000 $105.000 $273.400 $627.060 $200.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 3,400.000 $2.000 $1.300 $1.250 $2.550 $1.290 $3.030 $2.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,000.000 $2.000 $1.300 $1.250 $2.550 $1.420 $3.110 $2.000
668 6016 PREFAB PAV MRK TY B (W)(12")(SLD) LF 865.000 $7.000 $9.300 $10.000 $8.770 $14.410 $15.360 $10.000
668 6018 PREFAB PAV MRK TY B (W)(24")(SLD) LF 342.000 $9.000 $18.750 $19.000 $17.550 $26.440 $29.470 $15.000
668 6019 PREFAB PAV MRK TY B (W)(ARROW) EA 15.000 $350.000 $313.000 $380.000 $379.700 $312.920 $333.600 $1,200.000
668 6027 PREFAB PAV MRK TY B (W)(WORD) EA 2.000 $600.000 $459.000 $640.000 $586.000 $715.200 $757.500 $1,800.000
713 6003 JT SEALING AND CLEANING(LNGT CNSTR JTS) LF 17,407.000 $3.000 $2.400 $3.150 $3.250 $5.930 $6.270 $20.000
3037 6001 HIGH FRICTION SURFACE COURSE SY 74,787.000 $30.000 $23.000 $21.300 $25.500 $31.480 $30.690 $32.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 180.000 $100.000 $85.000 $85.000 $79.000 $114.660 $97.970 $200.000
6038 6001 MULTIPOLYMER PAV MRK (W)(4")(SLD) LF 4,620.000 $2.000 $0.410 $1.350 $0.450 $0.960 $1.070 $4.000
6038 6002 MULTIPOLYMER PAV MRK (W)(4")(BRK) LF 4,420.000 $2.000 $0.710 $1.350 $0.450 $1.010 $1.130 $4.000
6038 6007 MULTIPOLYMER PAV MRK (W)(8")(SLD) LF 1,000.000 $4.000 $0.910 $3.250 $0.850 $2.740 $3.010 $4.000
6038 6014 MULTIPOLYMER PAV MRK (Y)(4")(SLD) LF 15,800.000 $2.000 $0.410 $1.950 $0.450 $0.950 $1.070 $4.000
6038 6015 MULTIPOLYMER PAV MRK (Y)(4")(BRK) LF 3,000.000 $2.000 $0.710 $1.950 $0.450 $1.020 $1.130 $4.000
Totals: $3,021,299.00 $2,405,439.70 $2,560,010.15 $2,697,410.40 $3,218,915.41 $3,467,621.77 $3,927,084.00