Show Job Controls
Bid Cobra

GALVESTON FM2004 (6330-39-001)

Items: 14

County: GALVESTON
Length: N/A
Highway: FM2004
District: HOUSTON
Control Number: 6330-39-001
DBE Goal: N/A
Project: RMC - 633039001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $500,002.84
Date: 06/06/2018 (7 years ago)
Contract Number: N/A
Type: REFLECTIVE PAVEMENT MARKINGS (LONG LINE)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$500,002.84
$478,448.20
Over/Under Est: -4.31% -$21,554.64
$480,232.96
Over/Under Est: -3.95% -$19,769.88
Amt Left: 0.37% $1,784.76
Over/Under Est: 6.71% $33,558.16
Amt Left: 11.52% $55,112.80
Delta: -11.10% -$53,328.04
Over/Under Est: 7.41% $37,066.56
Amt Left: 12.25% $58,621.20
Delta: -0.66% -$3,508.40
Over/Under Est: 16.34% $81,687.16
Amt Left: 21.58% $103,241.80
Delta: -8.31% -$44,620.60
$814,756.40
Over/Under Est: 62.95% $314,753.56
Amt Left: 70.29% $336,308.20
Delta: -40.07% -$233,066.40

Bid Items & Bid Tabulations

14 Total 0 of 14
GALVESTON  |  FM2004  |  HOUSTON  |  6330-39-001  |  06/06/2018  |  $500,002.84  |  RMC - 633039001  |  REFL PAVMT MRK (LONG LINE)  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE LINES, INC.
BATTERSON, LLP
PMI PAVEMENT MARKING, INC.
INTERSTATE BARRICADES & MARKINGS, INC.
ROADSAFE TRAFFIC SYSTEMS, INC.
STRIPE-A-ZONE, INC.
MOBILIZATION (CALLOUT)
EA 6.000 $300.000 $500.000 $1,100.000 $100.000 $1,000.000 $500.000 $5,350.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,000.000 $0.580 $0.550 $0.550 $1.000 $0.850 $0.720 $1.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 76,960.000 $0.330 $0.420 $0.290 $0.350 $0.500 $0.400 $0.700
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 163,820.000 $0.310 $0.300 $0.290 $0.350 $0.310 $0.360 $0.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 480,720.000 $0.300 $0.280 $0.290 $0.330 $0.310 $0.360 $0.440
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 163,820.000 $0.310 $0.300 $0.290 $0.350 $0.310 $0.360 $0.500
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 480,720.000 $0.300 $0.280 $0.290 $0.330 $0.310 $0.360 $0.440
REFL PAV MRKR TY I-C
EA 3,000.000 $3.090 $2.300 $3.100 $2.500 $2.950 $2.000 $3.850
REFL PAV MRKR TY II-A-A
EA 15,268.000 $2.650 $2.000 $2.700 $2.500 $2.950 $2.500 $3.850
REFL PAV MRKR TY II-C-R
EA 3,000.000 $2.850 $2.200 $3.100 $2.500 $3.250 $2.500 $3.850
PAV SURF PREP FOR MRK (6")
LF 1,366,040.000 $0.010 $0.010 $0.010 $0.010 $0.010 $0.010 $0.025
PAV SURF PREP FOR MRK (8")
LF 6,000.000 $0.010 $0.020 $0.010 $0.010 $0.020 $0.020 $0.045
PAV SURF PREP FOR MRK (RPM)
EA 18,268.000 $0.010 $0.050 $0.020 $0.050 $0.200 $0.100 $1.000
TMA (MOBILE OPERATION)
HR 272.000 $51.480 $50.000 $1.000 $1.000 $25.000 $45.000 $5.000
Totals: $506,863.040 $478,448.200 $480,232.960 $533,561.000 $537,069.400 $581,690.000 $814,756.400